1 Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys

2 Proton Plan PMG 2/23/06 E Prebys 2 Agenda Operations Report/Technical Progress – Prebys Cost/Schedule Report – Sims Shutdown Preparations - Andrews

3 Proton Plan PMG 2/23/06 E Prebys 3 Operations Report

4 Proton Plan PMG 2/23/06 E Prebys 4 Operational Issues NuMI had a few minor problems and special runs MiniBooNE ran steadily Most effort was devoted to preparing for the shutdown.

5 Proton Plan PMG 2/23/06 E Prebys 5 NuMI FY06

6 Proton Plan PMG 2/23/06 E Prebys 6 MiniBooNE FY06

7 Proton Plan PMG 2/23/06 E Prebys 7 FY06 Total Booster Output

8 Proton Plan PMG 2/23/06 E Prebys 8 Technical Progress

9 Proton Plan PMG 2/23/06 E Prebys 9 Progress Technical Progress Linac  1.01.01 PA Vulnerability – Seven out of twelve new tubes (plus seven ordinary spares) ~On schedule  1.01.02 Quad Power Supplies First of eight cards prototyped and ready to go out for production.  1.01.04 LLRF Upgrade Task force has done characterization measurements on out test stand Planning series of measurements on operational stands over shutdown. Booster  1.02.01 Determine rep. rate limit No real progress because some key players concentrating on other things.  1.02.02 Orbump (+ 400 MeV line) – All six magnets done and tested Chosen three for use Mounted on girder Problems with strip line (more later) Will test next week On schedule (see Andrews’ talk)

10 Proton Plan PMG 2/23/06 E Prebys 10 Progress Booster  1.02.03 Correctors – Several coils potted and being tested. Laminations in, two cores stacked. Going out for bids on winding Electrical specs complete. Working on document.  1.02.04/05 30 Hz/Gamma-t – Mini-review tomorrow –Abandon 30 Hz –Continue to work on gamma-t  1.02.11 Booster Dump Relocation Ready to rock  1.02.13 Booster RF/ Rep. rate Improvements Transformers failed corona test at factory Cez strongly believes the problem is the test, and is going to investigate. If he’s right, we’re on track for the shutdown. If he’s wrong, we probably won’t get it done.

11 Proton Plan PMG 2/23/06 E Prebys 11 Progress Main Injector  1.03.01 Large Aperture Quads – Ready to go for all seven  1.03.02 Collimation – Ready to go (see pictures)  1.03.03 NuMI MultiBatch Operations – Intensity pretty much where it’s going to be until we start slip stacking Still plan to do kicker mods over shutdown, but load testing is tight. –Worse case: complete plumbing over shutdown and install loads later (~2-3 days) Studies: full 11 batch slip stacking and acceleration to 120 at low intensity! Study Group  1.05 Draft submitted to director Hand-off being negototiated with SNuMI effort

12 Proton Plan PMG 2/23/06 E Prebys 12 ORBUMP/Girder Assembly All six magnets complete and tested Best combination chosen based on:  Net dipole moment (<1 mm total beam motion at injection)  Acceptable alternate for each of the three magnets in the case of failure Magnets on girder Miscellaneous hardwared being mounted Electrical test next week On schedule  See. Andrews’ talk for details

13 Proton Plan PMG 2/23/06 E Prebys 13 Stripline Woes Problem one:  Machined too much at connection point Problem two:  Caught by milling machine and destroyed New stripline being fabricated:  Not potted (insulated with kapton and fiberglass padding)  Similar to all other striplines in Booster  On schedule

14 Proton Plan PMG 2/23/06 E Prebys 14 MI-8 Collimator w/o marble (moving configuration) Fully clad

15 Proton Plan PMG 2/23/06 E Prebys 15 The future: Corrector Prototyping Coil on core with complete single lamination Coil with core detail