Presentation is loading. Please wait.

Presentation is loading. Please wait.

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.

Similar presentations


Presentation on theme: "Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight."— Presentation transcript:

1 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Transmission Workgroup 5 January 2012 Exit Capacity Substitution: Alternative Definition of Substitutable Capacity for Interconnector Points.

2 2 Background  On 31 st March 2011 the Authority approved National Grid’s proposed Exit Capacity Substitution methodology statement.  Any unsold baseline capacity may be substituted from one NTS Exit Point to another to enable incremental capacity to be released without investment, (subject to a number of exclusion detailed in the statement).  The approval letter included a requirement to exclude exit capacity at Interconnectors from substitution for 2011, and to identify alternative proposals for defining Substitutable Capacity for these points that are consistent with developing European Regulations.  National Grid has identified a range of options to define “Substitutable Capacity” at interconnectors. Following discussions with Interconnector Operators, National Grid is seeking wider industry views before the inclusion of proposals within the next version of the methodology statement in 2012.

3 3 European Legislation  The exit capacity substitution methodology has been developed to be consistent with UK legislation and, in particular, the obligations placed on National Grid through its Licence. However, it must also be consistent with European legislation.  The key European obligations for National Grid are found in:  Directive 2009/73/EC dated 13 July 2009 concerning common rules for the internal market in natural gas; and  Article 13 sets out an objective that TSOs shall build sufficient cross-border capacity to integrate European transmission infrastructure accommodating all economically reasonable and technically feasible demands for capacity and taking into account security of gas supply.  Article 40 sets out general objectives for the Authority, including promotion of the development of cross-border transmission capacities to meet demand and enhance the integration of national markets.  Regulation (EC) No 715/2009 dated 13 July 2009 on conditions for access to the natural gas transmission networks.  Article 16 requires that the maximum capacity at all relevant points shall be made available to market participants, taking into account system integrity and efficient network operation.  ACER Framework Guidelines FG-2001-G-001 dated 3 August 2011 on capacity allocation mechanisms:  Sets out how capacity will be offered for sale, including an obligation to bundle available capacity. ENTSO-G will issue the CAM NWC consistent with this in March 2012.  Further proposals have been developed for substitution at Interconnectors to ensure consistency with these obligations.

4 4 Options OptionProsCons Peak sold NTS exit capacity (current methodology) Consistent with other exit points. Requires User commitment. Risk that Shippers reduce capacity bookings and excessive substitution occurs, thereby compromising SoS.. Peak sold entry capacity to downstream system. Requires a User commitment (not with NG). Risks excessive substitution if capacity unsold on both sides (currently low bookings at Moffat entry). TYS Peak Forecast DemandShould resolve SoS issues. Variance with CER 2010 forecast, 2011 closer alignment. No I(UK) figure. No User commitment. Downstream Peak Forecast Demand Should resolve SoS issues. Originally proposal from Gaslink. CSA Max Allowed Flow Rate. Linked to physical connection assets. Should resolve SoS issues subject to current build level being sufficient. Not consistent with physical capability of connected system. Protected capacity > capacity available as downstream entry. No User commitment. CSA Max Meter Capability. NTS Technical Capacity Published/Transparent Should resolve SoS issues. Very high value = higher level of protection Based on obligated level: so totally prevents substitution. No User commitment. Protected capacity > capacity available as downstream entry. Downstream Technical Capacity Published/Transparent/independent of NG. Should resolve SoS issues. Does not totally prevent substitution. Based on physical assets, less variable. No User commitment. The following options define the quantity that will be excluded from exit capacity substitution, i.e. is not Substitutable Capacity. For all options, sold capacity will not be substituted, even if this quantity is higher than the quantity determined from the option.

5 5 Views  National Grid has discussed these options with the Interconnector Operators at Bacton [I(UK)] and Moffat.  Interconnector (UK) agree with National Grid’s proposal to use the downstream Technical Capacity to define Substitutable Capacity.  Gaslink believe the “maximum flow profile” stated in the Connected Systems Agreement is more appropriate.  Discussions are on-going.

6 6 Proposal and Next Steps  Subject to further responses from Interconnector Operators, Ofgem and industry participants, National Grid is proposing to amend the definition of Substitutable Capacity in the Exit Capacity Substitution Methodology Statement to exclude any capacity, whether sold or unsold, at interconnector points, up to the published Technical Capacity of the connected system.  Formal consultation on the revised methodology statement is expected to commence late February 2012.


Download ppt "Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight."

Similar presentations


Ads by Google