1 Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

2 HillsboroughCountyAviationAuthority  Close Taxiway J  Demolition of Taxiway J Embankment  Build Relocated Bessie Coleman Boulevard Early February 2015 through Early April 2015

3 HillsboroughCountyAviationAuthorityOUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD TAXIWAY J  Close Taxiway J  Demolition of Taxiway J Embankment  Build Relocated Bessie Coleman Boulevard

4 HillsboroughCountyAviationAuthority  Shift Bessie Coleman Traffic; Change to 1-lane Operations  Demolition East Span of Taxiway J Bridge  Build Relocated Inbound George Bean Parkway Early April 2015 through Early May 2015

5 HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD  Shift Bessie Coleman Traffic; Change to 1-lane Operations  Demolition - East Span of Taxiway J Bridge  Build Relocated Inbound George Bean Parkway

6 HillsboroughCountyAviationAuthority  Shift Inbound George Bean Parkway Traffic  Remove Existing Pier 3 & Span over Existing Inbound Parkway  Build Outbound George Bean Parkway and Pier 3 Early May 2015 through Late June 2015

7 HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD  Shift Inbound George Bean Parkway Traffic  Remove Existing Pier 3 & Span over Existing Inbound Parkway  Build Outbound George Bean Parkway and Pier 3

8 HillsboroughCountyAviationAuthority  Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes  Demolish Remaining Spans of Taxiway J Bridge  Build New Spans for George Bean Parkway Late June 2015 through Late January 2016

9 HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD  Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes  Demolish Remaining Spans of Taxiway J Bridge  Build New Spans for George Bean Parkway

10 HillsboroughCountyAviationAuthority  Shift Outbound George Bean Parkway Traffic & Reopen 3 rd Lane  Shift Inbound George Bean Parkway Traffic  Shift Bessie Coleman Boulevard Traffic Late January 2016 through Mid February 2016

11 HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD  Shift Outbound George Bean Parkway Traffic & Reopen 3 rd Lane  Shift Inbound George Bean Parkway Traffic  Shift Bessie Coleman Boulevard Traffic

12 HillsboroughCountyAviationAuthority  Traffic in Interim Configuration  Construct APM Piers & Bessie Coleman Boulevard (By Others)  Complete Taxiway J Bridge and East Approach Late Mid February 2016 through Mid December 2016

13 HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD  Traffic in Interim Configuration  Construct APM Piers & Bessie Coleman Boulevard (By Others)  Complete Taxiway J Bridge and East Approach

14 Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014