Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014
2
HillsboroughCountyAviationAuthority Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard Early February 2015 through Early April 2015
3
HillsboroughCountyAviationAuthorityOUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD TAXIWAY J Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard
4
HillsboroughCountyAviationAuthority Shift Bessie Coleman Traffic; Change to 1-lane Operations Demolition East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway Early April 2015 through Early May 2015
5
HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD Shift Bessie Coleman Traffic; Change to 1-lane Operations Demolition - East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway
6
HillsboroughCountyAviationAuthority Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3 Early May 2015 through Late June 2015
7
HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3
8
HillsboroughCountyAviationAuthority Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway Late June 2015 through Late January 2016
9
HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway
10
HillsboroughCountyAviationAuthority Shift Outbound George Bean Parkway Traffic & Reopen 3 rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic Late January 2016 through Mid February 2016
11
HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD Shift Outbound George Bean Parkway Traffic & Reopen 3 rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic
12
HillsboroughCountyAviationAuthority Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard (By Others) Complete Taxiway J Bridge and East Approach Late Mid February 2016 through Mid December 2016
13
HillsboroughCountyAviationAuthority TAXIWAY J OUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard (By Others) Complete Taxiway J Bridge and East Approach
14
Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014