Britt Kern Mechanical Option Advisor: Dr. Treado Hunter’s Point South School Queens, New York
2
Britt Kern Mechanical Option Introduction i.Building Summary ii.Site Plan iii.Existing Mechanical Proposed Redesign Mechanical Depth Breadth – Electrical Conclusion Size:153,769 sf Occupancy:IM/HS Schoolhouse Levels:5 Stories/No Cellar/Penthouse Cost:$61,098,000 Construction Dates :Jan 10, 2011 to Oct 7, 2013 Project Team Architect:FXFOWLE Architects StructuralYsreal A. Seinuk MEP: Kallen & Lemelson CM:Skanska Hunter’s Point South School
3
Britt Kern Mechanical Option Introduction i.Building Summary ii.Site Plan iii.Existing Mechanical Proposed Redesign Mechanical Depth Breadth – Electrical Conclusion Hunter’s Point South School N Part of the Hunter’s Point South Project Redevelopment of Waterfront Vibrant Sustainable Middle-Income Urban Community
4
Britt Kern Mechanical Option Introduction i.Building Summary ii.Site Plan iii.Existing Mechanical Proposed Redesign Mechanical Depth Breadth – Electrical Conclusion AHU’s 1, 2, and 3 = VAV AHU’s 4, 5, and 6 = CAV 4 Condensing Boilers Fin Tube Radiators (2) 276 ton chillers Problems? Minimum Ventilation No Energy Recovery AHU 2 AHU 1 AHU 3 AHU 4 AHU 6 AHU 5 Mechanical Penthouse ACH-1 ACH-2 Hunter’s Point South School
5
Britt Kern Mechanical Option Introduction Proposed Redesign i.Objectives Mechanical Depth Breadth – Electrical Conclusion Goals Ventilation Always Met Increase Sustainability Better Room Comfort Control Airside Replace AHU’s 1-3 with DOAS Total Energy Recovery Wheel Fan-Powered Induction Units (FPIU’s) Breadths Photovoltaic Solar Panel Array Structural Roof Analysis Hunter’s Point South School Waterside New Chillers Secondary Chilled Water Loop
6
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Ventilation Air Based On: NYC Mechanical Code 30% Above ASHRAE Std. 62.1 Latent Load Reduction in 18% OA and 55% SA Exhaust Rates and ESP of Fans Hunter’s Point South School OA SA
7
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion 2 DOAS Specified by Manufacturer Total Energy Recovery Wheels All Preheating of OA Summer Design Winter Design Hunter’s Point South School 72°F, 30% RH 12.8°F, -5.4 DP
8
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Find CHW Supply Temp Size Coils for Heating and Cooling Optional MERV 8 filter – 1 LEED Point Supply CHW 58°F 75°F, 55% RH Hunter’s Point South School
9
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Current CHW Loop Re-Used: a.(2) 225 ton chillers b.LWT 44°F Higher CHW Temp for FPIU’s Secondary CHW Loop Created 33.5 ton chiller LWT 58°F Current Chilled Water Loop Hunter’s Point South School Secondary Chilled Water Loop
10
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion ρ = constant Hunter’s Point South School
11
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Compare Old and New Systems Validate New System 3 Models: VAV 100% Flow VAV 30% Flow FPIU Criteria: No Drafts (<40 fpm) Uniform Temperature (Setpoint 72°F) Minimal Temperature Stratification Supply Diffuser Exhaust Outlet Hunter’s Point South School Student
12
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Results: VAV 100% Flow -Some Drafts -High Room Temp VAV 30% Flow -Lots of Drafts -High Room Temp 22 fpm 55 fpm 72°F 76°F 53 fpm 12 fpm 42 fpm 77°F 74.5°F Hunter’s Point South School
13
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Results: FPIU No Drafts Steady Room Temp (72-73°F) Conclusions: VAV is Problematic FPIU = Good Air Distribution/Thermal Comfort 22 fpm 60 fpm 73°F72°F Hunter’s Point South School
14
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Reduction in: Electricity = 7% (5% due to solar) Natural Gas = 41% Emissions = 16% CO 2e Electricity Usage by Month Natural Gas Usage by Month Hunter’s Point South School
15
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth i.DOAS/Wheel ii.FPIU iii.Chillers/Loops iv.CFD (MAE) v.Results Breadth – Electrical Conclusion Costs New Rooftop Units Savings = $622,174 Costs Associated with FPIU’s Savings = $651,137 Initial Cost Savings = $1,273,311 Enough Savings to Finance Solar Array Hunter’s Point South School
16
Britt Kern Hunter’s Point South SchoolMechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical i.Roof Layout ii.Schematic iii.Payback Analysis Conclusion Inverter Combiner Boxes 68.99 kW
17
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical i.Roof Layout ii.Schematic iii.Payback Analysis Conclusion Inverter Combiner Boxes < 9’ setback Hunter’s Point South School
18
Britt Kern Mechanical OptionHunter’s Point South School 100 feet away Difference in Height = 153 ft - 73 ft = 80 ft SohCahToa: Tan(x degrees) = 80 / 100 x = 38.7 degrees From 8:25 am on no shading. 100 ft 80 ft Angle Introduction Proposed Redesign Mechanical Depth Breadth – Electrical i.Roof Layout ii.Schematic iii.Payback Analysis Conclusion N Summer Solstice
19
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical i.Roof Layout ii.Schematic iii.Payback Analysis Conclusion Combiner Box DC Disconnect Inverter (75 kW) AC Disconnect Switchboard 2 GFI Fuse Combiner Box X 10 strings X 8 strings Hunter’s Point South School
20
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical i.Roof Layout ii.Schematic iii.Payback Analysis Conclusion Initial Costs $296,666 After Incentives = $60,075 $14,987 Savings/year 188% Life Cycle Payback Profit = $260,745 Hunter’s Point South School
21
Structural: Girders/Non-Composite Deck 25 Year LCC Analysis Performed NPV Savings = $2,018,185 Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical Conclusion i.LCC Analysis ii.Acknowledgments iii.Questions
22
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical Conclusion i.LCC Analysis ii.Acknowledgments iii.Questions Contacts: Patrick Murphy Vanderweil Engineers Chris Bratz Meta Engineers Carter Tse Kallen & Lemelson Sharvil Patel Skanska Manufacturers: Tim Dorman (DOAS/Wheels) David Cunningham (Chillers) Justin Anderson (FPIU) Advisor: Dr. Stephen Treado AE Professors/Faculty and Fellow Students Family and Friends Hunter’s Point South School
23
Britt Kern Mechanical Option Introduction Proposed Redesign Mechanical Depth Breadth – Electrical Conclusion i.LCC Analysis ii.Acknowledgments iii.Questions Questions? Hunter’s Point South School
24
Britt Kern Mechanical Option
25
Britt Kern Mechanical OptionHunter’s Point South School
26
Britt Kern Mechanical OptionHunter’s Point South School
27
Britt Kern Mechanical OptionHunter’s Point South School
28
Britt Kern Mechanical OptionHunter’s Point South School
29
Britt Kern Mechanical OptionHunter’s Point South School
30
Britt Kern Mechanical OptionHunter’s Point South School N No Shadows
31
Britt Kern Mechanical OptionHunter’s Point South School N No Shadows
32
Britt Kern Mechanical OptionHunter’s Point South School 100 feet away Difference in Height = 153 ft - 73 ft = 80 ft SohCahToa: Tan(x degrees) = 80 / 100 x = 38.7 degrees From 8:25 am on no shading. 9 am, Summer Solstice 100 ft 80 ft angle
33
Britt Kern Mechanical OptionHunter’s Point South School
34
Britt Kern Mechanical OptionHunter’s Point South School Under Create Systems Option Tab Advanced Options
35
Britt Kern Mechanical OptionHunter’s Point South School