Public Financial Management Port of San Francisco Capital Cost Scenarios A Presentation and Discussion June 20, 2007
2
Public Financial Management 2 Capital Cost Scenarios Pier 35 $67,992,459 Major substructure and superstructure repairs within five years Seismic upgrade may be triggered No changes to the shed No extension for longer vessels Pier 27 - Option 2 $52,488,293 Renovate shed without structural changes No seismic upgrade Pier 27 - Option 3$77,000,000 Pier extension for second berth Additional terminal space for second berth
3
Public Financial Management 3 Capital Cost Scenarios Pier 30-32- Option 1$235,614,614 Substructure rehab and seismic upgrade Extend northeast corner One berth at east face Pier 30-32- Option 2$327,087,347 Add additional pier extension for second berth
4
Public Financial Management 4 Potential Joint Use Scenarios Trade shows Solid demand Scheduling conflicts Special events Demand needs further study Unique space should stimulate demand
5
Public Financial Management 5 Potential Revenue Sources Passenger charges$800,000 annually (200,000 passengers @ $4) Joint use revenues$500,000 annually (Special event net revenue) Annual tax revenues $897,000 (From BAE report) Total annual project revenues$2,197,000 Capitalized value$25,900,000
6
Public Financial Management 6 Gap Analysis