1
GLAST LAT ProjectMarch 24, 2003 5B Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 5B: Electronic Parts & Materials Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager johnson@scipp.ucsc.edu Gamma-ray Large Area Space Telescope
2
GLAST LAT ProjectMarch 24, 2003 5B Tracker Peer Review, WBS 4.1.4 2 ASICs See Presentation 5D for more detail. Status: wafers for both GTFE and GTRC chips have been procured and are awaiting wafer probing and screening. Relevant documents: –LAT-PS-01279Overview of Tracker ASIC procurement –LAT-PS-01201GTFE wafer procurement specification –LAT-PS-01222GTRC wafer procurement specification –LAT-PS-01250Tracker ASIC wafer probing procedure –LAT-TD-00247GTFE wafer test procedure –LAT-TD-00248GTRC wafer test procedure –LAT-PS-01321Wafer lapping & dicing procedure and wafer lot acceptance testing –LAT-TD-00249TMCM test plan –LAT-TD-01325Radiation test plan
3
GLAST LAT ProjectMarch 24, 2003 5B Tracker Peer Review, WBS 4.1.4 3 PWB & Pitch Adapter & Bias Final prototypes were recently produced and are being tested: –PWB: loaded with parts and new ASICs for functional testing –Pitch Adapter: Teledyne is bonding 3 of them to MCMs to check that the new design works –Bias: sent to Italy for review PWB: –Design files and specification sent to Young Electronics (L.A.) for quotation –Needs to include raised edge and precision machining of radius –Procurement spec: LAT-DS-01448 Pitch adapter and Bias Circuit: –Local Santa Clara vendor (Tycho) –Procurement spec: LAT-PS-01132 –Pitch adapter is single layer, no vias, very simple, but with Ni/Au plating
4
GLAST LAT ProjectMarch 24, 2003 5B Tracker Peer Review, WBS 4.1.4 4 Flex Circuit Readout Cables Procurement spec: LAT-PS-01132, includes specification of qualification and acceptance testing. Full-size prototypes manufactured by Parlex for the EM are being put through the specified test regime. Planning a visit to Parlex in early April. Short versions for the EM mini-tower were made at a local vendor (Tycho) and are being used in the electronics testing. The designs for the flight versions are being updated and verified in preparation for the procurement.
5
GLAST LAT ProjectMarch 24, 2003 5B Tracker Peer Review, WBS 4.1.4 5 Connectors Nano-connectors: Omnetics was recently approved and the parts are now on order, including the connector savers. Micro-D connectors: Kristek connectors are not yet approved, but we don’t expect any issues On MCM On cable Larger 080 screws
6
GLAST LAT ProjectMarch 24, 2003 5B Tracker Peer Review, WBS 4.1.4 6 SMT Parts HV capacitors: Novacap –Procurement spec: LAT-PS-01194 –On order for the Tracker and Calorimeter Polyswitches: Raychem (Tycho) –Procurement spec: LAT-SS-01116 –Recently finalized and approved, and the parts are on order –Long process of testing at UCSC and discussions with the vendor 100% of parts: screening after thermal cycle 10% of parts: more extensive tests after soldering Smaller sample for qualification testing at UCSC Ceramic & tantalum capacitors: approved with no issues Resistors: approved with no issues Thermistor: approved with no issues