CS-EE 481 Spring 2006 128 February, 2006 University of Portland School of Engineering Project Snake Automated Guitar String Tuner Team Kenneth Aramaki.

Similar presentations


Presentation on theme: "CS-EE 481 Spring 2006 128 February, 2006 University of Portland School of Engineering Project Snake Automated Guitar String Tuner Team Kenneth Aramaki."— Presentation transcript:

1 CS-EE 481 Spring 2006 128 February, 2006 University of Portland School of Engineering Project Snake Automated Guitar String Tuner Team Kenneth Aramaki Kevin Atebara Petra Carlson Kevin Vitayaudom Advisor Dr. Albright Industry Representative Mr. Howard Voorheis Fluke Instruments, Ret.

2 CS-EE 481 Spring 2006 228 February, 2006 University of Portland School of Engineering Overview Introduction Scorecard Additional Accomplishments Plans Issues/Concerns Conclusions

3 CS-EE 481 Spring 2006 328 February, 2006 University of Portland School of Engineering Introduction What it does? How it works?

4 CS-EE 481 Spring 2006 428 February, 2006 University of Portland School of Engineering Ssssssscorecard February’s Plans –Move Parts to Vector Board –Test/Build Mech. Prototype –Integrate Entire System –Test/Measure System Completed Shortcomings –Move Parts to Vector Board

5 CS-EE 481 Spring 2006 528 February, 2006 University of Portland School of Engineering Additional Accomplishments Modified Enable Circuit Wire Schematic Voltage Regulators

6 CS-EE 481 Spring 2006 628 February, 2006 University of Portland School of Engineering Plans Continue Test/Measure System Debug Begin Final Report

7 CS-EE 481 Spring 2006 728 February, 2006 University of Portland School of Engineering Milestones NumberDescriptionOriginal 9/29/05 Previous 2/28/06 Present 3/27/06 1Product Pre-Approval9/15/059/20/05 2Functional Spec 1.010/7/0510/12/05 3Finalize Parts Needed10/3/0511/25/05 4Project Approval10/7/0510/14/05 5Order Parts10/24/0512/16/06 6Plans 1.011/17/05 7Design Release12/9/051/30/062/27/06 8Receive Parts1/18/062/1/062/24/06 9TOP Approval2/24/06 2/27/06 10Sub-Circuit Integration2/27/06 11System Integration3/9/06 3/27/06 12System Testing Complete4/3/06 13Prototype Release4/7/06 14Founders Day4/11/06 15Final Written Report4/28/06

8 CS-EE 481 Spring 2006 828 February, 2006 University of Portland School of Engineering Concerns/Issues Concerns/Issues: –Additional Testing

9 CS-EE 481 Spring 2006 928 February, 2006 University of Portland School of Engineering Conclusions Project Approach Status On Schedule Additional Accomplishments Milestones Update Concerns/Issues Questions?


Download ppt "CS-EE 481 Spring 2006 128 February, 2006 University of Portland School of Engineering Project Snake Automated Guitar String Tuner Team Kenneth Aramaki."