1
NIRISS Science Team Meeting Oct 2015 NIRISS Activities in CV3 André Martel
2
NIRISS Science Team Meeting Oct 2015 Goals (for NIRISS performance): 1.Characterize and verify the performance of all the modes of NIRISS (including new detector). 2.Collect data for reference files (JWST calibration pipeline, aXe, etc…). Hardware changes since CV2: new grisms (GR700XD, GR150R), new detector, new wheel motors. Important dates: Oct 21: ISIM CV3 TRR Closeout Review Oct 26: AFC/SFT and pumpdown Since CV2: new grisms, detector, wheel motors characterize all modes of NIRISS Detector Collect reference files for JWST calibration pipeline (update some in commissioning) External stimulus from OTE Simulator (OSIM): monochromatic and continuum sources, diffuser illumination (flat field) Low chamber background Overview
3
NIRISS Science Team Meeting Oct 2015 Commanding: OTP (state tables), OSS, CECIL Illumination sources: 1.NIRISS internal lamps (FLAT1, FLAT2, LAMP1, LAMP2) 2.OTE Simulator (OSIM): a.Monochromatic sources (0.64, 1.06, 1.32, 1.55 μm) b.Continuum sources (Tungsten) (1 – 5 μm) c.Flat field lamp/diffuser Monitor the mechanisms usage (DW, CFM, lamps) Since CV2: new grisms, detector, wheel motors characterize all modes of NIRISS Detector Collect reference files for JWST calibration pipeline (update some in commissioning) External stimulus from OTE Simulator (OSIM): monochromatic and continuum sources, diffuser illumination (flat field) Low chamber background
4
NIRISS Science Team Meeting Oct 2015 NGINTitle JWST-PROC-026716ISIM Element Cryo-Vacuum #3 Test JWST-PROC-027875OSS Warm Darks Cryo-3 Test JWST-PROC-026314OSIM Initial Flux Evaluation JWST-PROC-016344SIDECAR ASIC and FPA Tuning JWST-PROC-026498ISIM Comprehensive Performance Test Part 1 JWST-PROC-026482OSIM and SI Checkout JWST-PROC-026481ISIM CV3 Optical Baseline Procedure JWST-PROC-026318NIRISS Performance Characterization JWST-PROC-027876OSS SI Characterization (SIC) JWST-PROC-027877Day in the Life (DIL) JWST-PROC-026483Final Optical Performance Also: AFC/SFT procedures Test Procedures About 40 test procedures. Most relevant:
5
NIRISS Science Team Meeting Oct 2015 CV3 Timeline
6
NIRISS Science Team Meeting Oct 2015 Functional Tests (AFC/SFT) (Oct 26) start cooldown Warm darks (Nov 17-19) 1.OSS visits (NGROUPS=88) 2.80 – 60 K CV3 Timeline Part 1
7
NIRISS Science Team Meeting Oct 2015 Initial Flux Evaluation (Nov 20-22): 1.Calibration of the OSIM source fluxes, temperature, and attenuation, pulse widths and delays, diffuser lamp, etc…. Updates to the Test Planning Tool (TPT). 2.OTP0.2.9.0.NIS, 0.2.9.6.NIS, 0.2.9.8.NIS, 0.2.9.3.NIS, 0.2.9.7.NIS Reach cold plateau (≈ 37.5K in CV2) Turn on NIRISS FPA heater with CECIL (Nov 22) CV3 Timeline Part 1
8
NIRISS Science Team Meeting Oct 2015 ASIC tuning (Nov 23-27; Thanksgiving) 1.Run 1: NIRCAM (12 hours), NIRISS, G1, G2 (7 hours each) 2.Run 2: fine-tuning (same order, shorter) 3.Analysis by ComDev 4.Quick turnaround (~24-36 hours): parallel analysis, “metrics” Actions for NIRISS team: 1.Update the bad-pixel map. 2.Future state tables: - Update SOSS sweet spot pixel (if necessary). - Update the four NRM science pixels (and subarray). CV3 Timeline Part 1
9
NIRISS Science Team Meeting Oct 2015 CPT (Comprehensive Performance Test) (Nov 28-Dec 6) 1.NIRISS internal lamp checks and parallel darks and backgrounds 2.OTP commanding (state tables) and CECIL CV3 Timeline Part 2
10
NIRISS Science Team Meeting Oct 2015 OSIM + SI Checkout (Dec 6-19) 1.Chamber background checks (OTP0.2.0.2) 2.Focus Sweeps: OSIM and CFM (OTP0.5.NR.1, 0.5.NR.2) 3.Grisms and NRM Checkout (OTP0.2.4.1.NR) a. copy of some lines of the NIRISS Perf Verification b. Verify/confirm (“first light”) - verify location of SOSS sweet spot pixel - spectral and spatial location of GR700XD traces - pointing/subpixel dithers at the four NRM pixels - tilt of GR700XD and GR150C/R traces - ghosts/stray light in the grisms (glint, GR700XD, etc…) - OSIM source fluxes CV3 Timeline Part 2
11
NIRISS Science Team Meeting Oct 2015 4. Actions for NIRISS team: a. Choose best CFM focus. b. Decide if trace tilt tests must be executed (7.15 and 7.16) c. In state tables of Performance Verification: - update focus (TPT) - update pixel of SOSS sweet spot - update pixels of NRM pixels and subpixel offsets - update fluxes of OSIM sources CV3 Timeline Part 2
12
NIRISS Science Team Meeting Oct 2015 Initial Optical Baseline (Dec 20-21) 1.Mostly for trending 2.Short OSIM flat field and pupil alignment check (PAR) Critical Tests (Dec 21-23) 1.Includes 7.17 Detector Linearity (after NIRCAM and before FGS for warm lamps) Christmas break (Dec 24-26) CV3 Timeline Part 2
13
NIRISS Science Team Meeting Oct 2015 NIRISS Performance Verification (Dec 28-31) 1.Majority of NIRISS observations (and mechanism usage). 2.OTP commanding (7.*), e.g., 7.5 NRM Verification, 7.7 GR150C/R Wavelength Calibration, etc… 3.Other ISIM tests for requirements verification (OTP4.3.NR Field-of-View, OTP4.5.NR Rogue Path, etc…) 1.NIRSpec is parallel (OSS) 2.See JWST-STScI-004354 or JWST-RPT-027763 http://www.stsci.edu/~martel/NIRISS_CV3_perfver_martel.pdf CV3 Timeline Part 2
14
NIRISS Science Team Meeting Oct 2015 Transition to warm plateau (≈ 43K) (FPA heater off/on) OSS + SI Characterization (SIC) (Jan 8-10) 1.Exercise OSS scripts for all the NIRISS modes (including a short CFM sweep); NISRAPID and NIS readouts 2.OSIM source on; 31 visits, 67 activities CV3 Timeline Part 3
15
NIRISS Science Team Meeting Oct 2015 NIRISS Darks (Jan 10-11) 1.In parallel to MIRI performance tests 2.CECIL commanding for full frames and subarrays. OSS Day-in-the-Life (Jan 13-15) 1.NIRISS exposures in F158M + CLEAR only 2.7 visits, 21 exposures (38 integrations, NGROUPS = 6-12) CV3 Timeline Part 3
16
NIRISS Science Team Meeting Oct 2015 Final Optical Performance (Jan 16-17) 1.Trending: short OSIM flat field, pupil alignment check 2.CFM adjustment for 0g 3.DW at CLEARP + F444W for ambient metrology Warmup 1.Turn off NIRISS, start warmup (Jan 18) 2.Open chamber (Feb 6) CV3 Timeline Part 3
17
NIRISS Science Team Meeting Oct 2015 Rapid turnaround and formal documentation in order to: 1.Verify requirements. 2.Characterize and assess the performance of each mode. 3.Update or change the operations. 4.Create the final pre-flight set of calibration reference files for all modes (due 6 months after the completion of CV3). Note: other analyses by the ISIM team (alignment, trending, etc…) Post-CV3 Analysis
18
NIRISS Science Team Meeting Oct 2015 Will verify and characterize all the modes of NIRISS and collect all necessary data for launch. OTP number of exposures: > 850 (all of CV2: ~1230) OTP number of integrations: > 4830 (all of CV2: ~10900) Mechanism usage (current tests; no repeats; OSS separate) 1.Test Planning Tool: 85% (PW) and 75% (FW) of allocation 2.Worst-case scenario: 145% (PW) and 135% (FW) Web site with CSV of state tables, OSS visits, etc…: http://www.stsci.edu/~martel/CV3 Summary
19
NIRISS Science Team Meeting Oct 2015 Orientation (Oct 16): Shared Files / Entire JWST Project / ISIM / Reviews / ISIM CV3 Orientation /ISIM CV3 Orientation (10-14-15_CV3_Training.pptx) https://ngin.jwst.nasa.gov/Sharefile/Sharefileview.asp?ID=21558 TRR on NGIN: Root / Entire JWST Project / ISIM / Reviews / ISIM CV3 TRR / Final Charts & Final Backup Optics pre-TRR on NGIN: Root / Entire JWST Project / ISIM Optics / CV3 optics pre-TRR 17 Sep 2015 Material