Status Report for E391a (Continuation of the previous PAC on April) G.Y.Lim IPNS, KEK Group Meeting at the JINR 26 th – 29 th July 2003 Dzhelepov Laboratory of Nuclear Problems
2
After the previous PAC Start assembling the front barrel Continuous fabrication of the central barrel Evacuation test of the downstream section
3
E391a Detector Upstream section Downstream section Middle Section
4
Upstream Section Module fabrication was done – Dec. 2002 Instrument for assembling was fabricated – Collaboration work with KEK machine shop Start assembling - August 2003 – Will take one month Evacuation/cosmic test will be done Sep. 2003
5
Slide show for FB assembling 5 th August 2003
6
Continuously 22 nd August (Expected)
7
CC02 Shashlik type of beam counter Arrived at KEK on 4 th July from U. of Chicago Beam test at pi2 July 2 nd ~8 th, 2003 8 % resolution @ 1GeV, 10 p.e./MeV deposit (Very preliminary !!!)
8
After CC02 installation ・・・ Aiming to finish by the end of August
9
Middle section Module fabrication – Final stage
10
50 plates/week Finish at the middle of Sep.
11
Stacking on every Wed. Working more than 8 person End of September
12
Middle section Module fabrication – Final stage Vacuum vessel is being constructed – Competition bid – Hitachi Zosen Ltd. – Will arrive at KEK at the end of Oct. 2003 Assembling scenario was fixed – Collaboration work with Entek Assembling will be done by the middle of Dec. 2003
13
Downstream section Assembling was finished – Sep. 2002 Beam test (Engineering run) – Oct. – Dec. 2002 Evacuation test – June 2003 – First time of operation for calorimeter in vacuum – Test for the water cooling mechanism
14
Cooling System Control PMT temperature within 1 0 C with circulating water
15
Installation of the cooling system
16
Temperature Measurement Divider CsI
17
We got clear Cosmic response 5 0 C Cooling water10 0 C Cooling water 15 0 C Cooling water20 0 C Cooling water p Q/cm
18
Temp. dependency Cosmic Peak position Cosmic Peak width(sigma) Normalized by the engineering data CsI temp. ( 0 C) MeV/pC Light Yield : -1.3% / 0 C
19
Schedule Aug. Sep. Oct. Nov. Dec. Jan. Feb. FB assembling CB fabrication CB assembling Cosmic test/counter tuning Start data taking Evacuate system Unite three sectionsCheck Membrane Moving downstream Cosmic and evacuate test for the upstream A/D Card upgrade ADC Replacement BA and CC05 installation CV PMT install CC04/CC05 Fabrication CC04 Installation Cooling system for Barrel Additional Cabling Downstream vacuum test Middle section fabricationMembrane BCV Beam
20
Summary E391a is aiming at measuring the BR( K L ) – Realizing Step-by-step Preparation of E391a – Three parts are being prepared in parallel – Manage to catch up the schedule Prompt start – Well tuned electronics and DAQ at the engineering run – Cosmic test for each detector components – Minimum beam time for tuning