WRAP 2002 WORK PLAN Overview and Financial Status Report WRAP Board Meeting November 14, 2001 Salt Lake City, Utah
2
Work Plan Development Process Builds on Nov. 1999 comprehensive work plan and Dec. 2000 update – Nov. 2000 Planning Team Meeting identified critical path & products for 309 SIPs/TIPs – March 2001 Technical Planning Meeting – Quarterly IOC/TOC/Planning Team Meetings in 2001 – Monthly conference calls – Forum and Committee Co-Chairs provided work plan updates – September Planning Team Meeting reached consensus on work plan tasks and budget allocation
3
WRAP Work Plan Provides foundation for development of 308 SIPs and TIPs – Technical: ambient data, inventories, modeling – Policy: market trading, fire, renewables and efficiency, mobile sources
4
1999-2001 Financial Status EPA WRAP Grants in 1999, 2000 & 2001 – WGA and NTEC – Total = $5.14 MM Contract support:74% –83% obligated in contracts –43% spent as of Sept. 30, 2001 Travel and Project Management: 26% –100% obligated –90% spent as of Sept. 30, 2001
5
2002 Budget EPA Grants to WGA and NTEC – Total = $4.09 MM Contract Support:71% Travel and Project Management: 18% Staff Support: 11%
6
Staff Support Assist WRAP Committees and Forums complete their work – Meeting preparation and follow up – Gather data, conduct analysis, write reports – Interface with contractors Working under direction of Committees and Forums with supervision by Co-Directors
7
Staff Support Recognize temporary commitment Hiring options – State or tribe dedicates staff full time – Hire at affiliated organization (NTEC, WGA, WESTAR, Regional Modeling Center) – Independent contractor support
8
Staff Support Positions Co-Directors (NTEC and WGA) Tribal Caucus (NTEC) State Caucus (WESTAR) Economic Analysis (consultant on retainer) Technical Coordinator (at RMC?) – Emission inventory focus Two “policy” staff – Fire, Market Trading, Communications are high need
9
NTEC Air Staff WRAP Grant – Tribal caucus staff person National Air Grant – Policy Analyst (formerly Air Program Coord.) Serves as WRAP Co-Manager. – Working Groups Facilitator – Communications Specialist
10
National Air Grant Goals Formation of national tribal air organization Assist tribal participation in several policy work groups Track & analyze regulatory developments Conduct outreach and communication re all above