Oregon Department of Transportation Stormwater Management Initiative: Meeting New Challenges Presented by: William Fletcher and Jennifer Sellers January.

Similar presentations


Presentation on theme: "Oregon Department of Transportation Stormwater Management Initiative: Meeting New Challenges Presented by: William Fletcher and Jennifer Sellers January."— Presentation transcript:

1 Oregon Department of Transportation Stormwater Management Initiative: Meeting New Challenges Presented by: William Fletcher and Jennifer Sellers January 22, 2008

2 Overview of Water Quality Issues  Regulation of stormwater is a national issue  Copper has been shown to harm salmonids at very low concentrations  NMFS is basing effect determinations largely on dissolved copper

3 Problem Statement Stormwater has become a major impediment to efficient ESA consultation process due to:  Changing criteria for effect determinations in ESA Section 7 consultations  Potential extension of the “action area” from the point of discharge to the sea

4 Problem Statement Changing Criteria  ODOT has based effect determinations on the change between pre-project and post-project conditions  NMFS is basing effect determinations on the absolute quality of the stormwater at the point of discharge

5 Changing Criteria: Implications to ODOT’s Program Region Biologists were surveyed and estimated a 20 – 50% increase in number of formal consultations Region Biologists were surveyed and estimated a 20 – 50% increase in number of formal consultations

6 Action Area Current ODOT Action Area Definition  2-miles downstream from point of discharge or as project conditions indicate NMFS initially proposed an action area from the point of discharge to the sea Problem Statement

7 Overall Impact to ODOT’s Program Nightmare Scenario  Required numeric standards  Monitoring to demonstrate compliance  Potential remediation requirements  Consultation gridlock

8 Solution Strategy Collaborative approach that includes all of the interested parties –ODOT - USFWS –NMFS - ODFW –FHWA - EPA –DEQ

9 Solution Strategy Review by and consultation with:  A Technical Team comprised of hydraulic engineers and stormwater designers from ODOT, DEQ, and FHWA  ODOT Office of Maintenance  ODOT Environmental Leadership Team, Technical Leadership Team, and Area Managers Team

10 Solution Strategy: ODOT’s Goals Develop a stormwater treatment program to: Develop a stormwater treatment program to:  Provide ODOT and FHWA with certainty regarding scope, schedule, and budget  Streamline the permitting process  Meet all regulatory needs  Result in an overall environmental benefit and promote species recovery

11 Solution Strategy: ODOT’s Goals All solutions must be PermitableConstructibleMaintainable

12 Solution Strategy Twin tracks:  Regulatory: Streamline the ESA consultation process  Technical: Develop the process and tools for effective stormwater management

13 Solution Strategy: Regulatory  Articulation and clarification of Effect Determination criteria and thresholds  Develop tools for Streamlined Permitting

14 Effects Determinations  Agree that copper causes sublethal effects to listed salmonids  NMFS develops guidelines for Effects Determinations based on project elements and stormwater management Solution Strategy: Regulatory

15 Permitting Streamlining  Agree on requirements to obtain NMFS buyoff on projects  Develop programmatic approaches to consultation on stormwater issues  Include technical products in SLOPES IV  Use pilot projects using the technical products in consultation to set precedent

16 Status: Regulatory  Agreement that if “effective” BMPs are used, then stormwater has been treated to maximum extent feasible  We will not be held to numerical standards for ESA purposes

17 Status: Regulatory NMFS has provided written guidance for effect determinations LAA: –New “pollutant generating impervious surface” that discharges to surface waters:  Travel lanes  Shoulder widening  Turn lanes

18 Status: Regulatory NLAA  All stormwater from the Water Quality Design Storm is infiltrated No Effect  Non-Pollutant generating surfaces –Sidewalks –Guardrail flares –Separated bike paths

19 Status: Regulatory Most Recent NMFS Proposed Action Area Definition (or lack thereof) –Potentially from point of discharge to the ocean or major confluence (default) –Determined on a project-by-project basis –Project team should coordinate with NMFS early on the action area

20 Status: Regulatory  Pilot projects selected, with active work on one in Region 1  Proposal for a Stormwater Programmatic rejected  Incorporated preferred BMPs and Design Storms into SLOPES IV

21 Status: Regulatory  For projects that cannot use SLOPES IV, stormwater analysis and conditions can be inserted into consultations via “incorporation by reference”  FHWA considering becoming a “SLOPES” Action Agency

22 Solution Strategy: Technical  Clarify and improve ODOT’s process for addressing stormwater management  Develop tools to select the most effective treatment for individual projects  Select design storms based on science

23 Status: Technical Project Development Process  Baseline Report identified issues  Initial design incorporates stormwater quality management –Low Impact Development techniques –Right-of-way for engineered facilities

24 Status: Technical Project Development Process (2)  Water Resources Impact Assessment identifies any remaining treatment requirements  BMP Selection Tool used to –Identify and select BMPs –Assemble treatment train –Justify BMP selection  BA incorporates results from BMP Selection process

25 Status: Technical Design Guidance  BMP Summary Reports Completed  LID Summary Reports in Development  BMP Selection Tool being tested and refined on pilot projects –Draft rating of BMP effectiveness –Preferred BMPs identified  BMP Selection Tool Users’ Guide to be developed

26 Status: Technical BMP Evaluation  High variability with “effectiveness” data  Based on treatment mechanisms –Hydrologic attenuation –Sedimentation/density separation –Sorption –Filtration –Uptake/storage –Microbially-mediated transformation

27 Status: Technical BMP Selection

28

29 Priority BMPs for Treating Dissolved Metals  Treatment Mechanisms –Hydrologic Attenuation (infiltration) – preferred –Sorption, uptake, microbial transformation  “Preferred” BMPs –Infiltration trench –Bioretention –Bioslope (“Ecology Embankment”) –Amended Swale and Filter Strip

30 Status: Technical BMP Selection  Key selection criteria (metrics) –Treatment capability –Physical site suitability –Maintenance –Cost –Resources, risk and public perception

31 Status: Technical BMP Selection Next Steps  Finalize Metric Ratings  Apply to Pilot Projects  Integrate into an “Electronic Tool”  Develop Users’ Guide

32 Status: Technical Design Storm Evaluation  Water Quality Design Storms have received regulatory acceptance  Flow Control (Water Quantity) Design Storm upper and lower limits accepted  Flow Control threshold of concern proposed

33 Status: Technical Design Storms  Water Quality and Water Quantity  Based on climate data  Regionalized  Economics (cost-benefit) Ultimately a “Policy” decision

34 Status: Technical Water Quality Design Storm Based on analysis of rainfall data from >50 precipitation stations  Cumulative percent of total rainfall vs. storm size  Percentile of storm size  Percent rainfall treated  “Sensitivity Analysis” for sizing treatment facilities

35 Status: Technical Water Quality Design Storm  Design storm corresponding to 85% cumulative rainfall results in: –>95% of rainfall treated –>97 th percentile storm size  Facility size is most “sensitive” to design storms when increasing from 90% to 95% cumulative rainfall design storm

36 Status: Technical Water Quality Design Storm

37  Use the mean storm size corresponding to 85% cumulative rainfall for each station in the climate zones.  Define a water quality design storm for 5 zones ZoneCurrent ODOT NMFS Storm (72% 2 year) 85% Cumulative Rainfall 11.63.452.3 2 and 31.02.161.4 41.53.22.3 50.61.3 6,7,8, and 90.51.080.7

38 Status: Technical Flow Control (Water Quantity) Design Storm Lower Discharge Endpoint  Eastern OR - 2/3 of 1.5-year storm  Western OR - 2/3 of 1.2-year storm Upper Discharge Endpoint  Minimally incised streams - Channel bank overtopping event  Incised Streams -10-year/24-hour storm event

39 Next Steps  Integration of stormwater management tools into ODOT’s project development process  Develop a Watershed Approach to Stormwater Management

40 Definition of Success  When guidance is approved by regulatory partners  When tools and guidance are in use by project teams  When stormwater is no longer a contentious issue

41 Questions?

42

43 Future Steps: Watershed Approach  Treatment on small projects is often not cost effective  Some projects may not be able to meet water quality goals  Many permitted projects can have residual adverse effects  Highway runoff management may not address priority watershed goals

44 Watershed Approach  Trading or banking of credits for small projects or projects that cannot meet water quality treatment goals  Mitigation for residual adverse effects from permitted projects  Focus efforts toward maximum benefit to the watershed

45 I. Streamline the DEQ Stormwater Management Plan Approval Process Problem Statement All applications for SWMPs reviewed in detail by DEQ, which results in  Multiple requests for more information, design changes  Constant danger of schedule slipping  Heavy load on DEQ/ODOT liaison

46 I. Streamline the DEQ Stormwater Management Plan Approval Process Determine Objectives/ Goal(s) Water Resources Impact Assessment Water Quality Management Design Internal ODOT Quality Control - QC Checklist Optimize Treatment Option Selection ODOT Submits to DEQ - Submittal Application Form - Project Description - Objectives and Goals - Stormwater Treatment Measures - Project Plan Sheets DEQ Reviews SWMP Submittal Package DEQ Approves SWMP

47 Anticipated Benefits for ODOT and FHWA  Certainty in project development and construction  Reduction in project delays  Contributes to FHWA’s ESA Section 7(a)(1) requirements  Support of ODOT’s sustainability goals

48 Anticipated Benefits for Regulatory Agencies  Regulatory requirements are met  ESA-listed fish and habitat are protected  Oregon’s water quality and wetland resources are protected  Well-defined permit conditions that allow for flexibility in application  Reduces staff workload

49 Where We are Now: DEQ  Interagency Agreement with DEQ and ODOT signed  DEQ and ODOT developing training for Region and DEQ staff

50 Status: Technical Water Quality Design Storm

51


Download ppt "Oregon Department of Transportation Stormwater Management Initiative: Meeting New Challenges Presented by: William Fletcher and Jennifer Sellers January."