Clean Air for Europe TFIAM Conference Planning of the CAFE programme AMIENS May 2004 André Zuber & Matti Vainio Environment DG - European Commission TFIAM Conference Planning of the CAFE programme AMIENS May 2004 André Zuber & Matti Vainio Environment DG - European Commission
2
Clean Air for Europe Thematic Strategy Finalisation of RAINS model development Technical inputs of abatement potential and costs Closing of consultations with MS and AC CAFE Baseline published CAFE Baseline ready & agreed Development of TREMOVE transport model Development CBA framework Model runs of policy packages (including iterations) Definition of policy packages to be assessed Advice on health and ecosystems effects (WHO, PM Working Group and ECE) Assessing policy packages qualitatively and quantitatively Drafting CAFE Integrated policy advice and Thematic Strategy on AP 2004 2003 2005 Data on NEC, AQ and own studies Schematic outline of CAFE timeline CAFE – Workplan Saltsjobaden II AIRNET final conference Prague WHO summary report NEC review (2006)
3
Clean Air for Europe CAFE workplan Preparing the Thematic strategy on air pollution l l April 2004 - stakeholder consultation with MS l l May 2004 - CAFE SG and final comments on baseline l l June 2004 - CAFE WG TSPA advice on RAINS PaMs and RAINS ready to run policy scenarios l l July 2004 - RAINS and TREMOVE intercomparison, CBA methodology workshop l l September 2004 – first results of RAINS PaM scenarios and further advice from CAFE WG TSPA on PaMs
4
Clean Air for Europe CAFE workplan Preparing the Thematic strategy on air pollution l l October 2004 – second set of RAINS PaMs scenarios. TREMOVE ready for scenario runs/analysis. CBA starting. l l November 2004 – discussions of results in CAFE WGs and SG. Possibly further advice. Drafting of CAFE integrated policy advice. l l Jan/Feb 2005 – analysis of RAINS scenarios l l March/April 2005 - finalisation of CAFE advice and draft TS. Including CBA and TREMOVE. l l Adoption of TS by Commission 22 July at the latest
5
Clean Air for Europe CAFE workplan Preparing the NEC review l l November 2004 – deadline for MS to submit revised energy baselines for NEC revision, new information on technologies l l February 2005 – updating RAINS for the NEC review l l March to August 2005 – IIASA consultations with MS l l November 2005 - final stakeholder consultations. l l January 2006 –RAINS operational for NEC revision l l June 2006 – Commission proposal of revised NEC directive, including CBA
6
Clean Air for Europe CAFE workplan The EU Thematic strategy and the CLRTAP l l The Thematic strategy not later than 22 July 2005. l l A white paper (action plan) amended with legislation. m Potential measures under discussion at the moment, including new policies m Priority pollutants - O3, PM and NO2 m HM and POP part of the ”Environment and Health” programme l l Revision of the ceilings of the NEC directive – proposal in mid-2006. l l Review of the Gothenburg protocol when 16 parties ratify.