TASK 3.1 Physical Interoperability State of the progress PIAP Milan, 12-14.10.2015 C2-SENE Milan 1.

Similar presentations


Presentation on theme: "TASK 3.1 Physical Interoperability State of the progress PIAP Milan, 12-14.10.2015 C2-SENE Milan 1."— Presentation transcript:

1 TASK 3.1 Physical Interoperability State of the progress PIAP Milan, 12-14.10.2015 C2-SENE Milan 1

2 Structure C2-SENE Milan 2

3 Wheather station C2-SENE Milan 3 BOSCH BME280 humidity / temperature / pressure SPI / I 2 C LPC 1115 microcontroller data acquisition, conversion and segregation YL-83 rain detection DO / AO SEN-08942 wind speed / wind direction / pluviometer DO / AO GSM/GPRS Module River level RS-232

4 River level measurement C2-SENE Milan 4 sensor How to connect to the C2-SENSE? + radio transceiver + controller radio transceiver Connection seems to be simple. Appropriate sensor has to be developed.

5 River level sensor: state of the art C2-SENE Milan 5 In most cases: Water level determination based on hydrostatic and atmospheric pressure. Two devices: first in the river, second next to it (reference point). Comparison of the measurements in selected points.

6 River level sensor: state of the art C2-SENE Milan 6 Why are these inappropriate for the C2-SENSE? communication incompatibilities, not easy (quick) to set up, requires interference with the environment, definitely not low cost.

7 River level sensor: conception 1 C2-SENE Milan 7 Based on the GPS placed on the buoy. Main problem: uncertainty concerning GPS accuracy, has to be checked experimentaly

8 River level sensor: conception 2 C2-SENE Milan 8 Based on based on the difference in atmospheric pressure Current status: high accuracy pressure sensors was selected(MPXH6115A6U), two nodes in development state to experimental stage air pressure (reference level) air pressure on the buoy level (river level) radio communication

9 Physical layer operation C2-SENE Milan 9 SenderReceiverOperationCommunication Weather StationGPRS ModuleData transmissionRS-232, MODBUS-RTU GPRS ModuleWeather StationConfirmationModule digital output Weather StationCB-RADIO M.Data transmissionRS-232, KISS protocol GPRS ModuleIP GatewayData transmissionGPRS IP GatewayGPRS ModuleDemandGPRS CB-RADIOIP GatewayData transmissionAX.25 IP GatewayCB-RADIO M.DemandAX.25

10 IP Gateway output C2-SENE Milan 10 Facts: Approximately 8 sensors right now (for every node). Optimal message, considering further expansion of the sensors in every node. NODE ID (1) / TIME / SENSOR 1 DATA /…/ SENSOR 8 DATA NODE ID (2) / TIME / SENSOR 1 DATA /…/ SENSOR 8 DATA NODE ID (LAST) / TIME / SENSOR 1 DATA /…/ SENSOR 8 DATA OR NODE ID (1) / TIME / SENSOR 1 DATA/… NODE ID (1) / TIME / SENSOR 2 DATA/… NODE ID (1) / TIME / SENSOR 8 DATA/… NODE ID (2) / TIME / SENSOR 1 DATA/… NODE ID (LAST) / TIME / SENSOR 8 DATA/…

11 Summary C2-SENE Milan 11 focus on sensors integration and communication with the C2-SENSE, searching for physical layer additional capabilities (for example external storage), conception and development of the new water level sensor, IP Gateway output.