1 DOM INTEGRATION MEETING DAAN VAN EIJK 28 JANUARY 2016

2 ISSUES AND ACTIONS FROM PREVIOUS MEETING DOM integration halted at optical splice due to AHRS problems This decision affects us (DOM integration teams) heavily But: PMT structures and bottom hemispheres can be fully integrated! News on AHRS status will follow very soon Firmware and embedded software versions to be flashed on CLB’s Revision to flash: rev150904 DOM registration software: Version 1.7 (bug fixes, added Ti bolts and nuts, A/D filter from unique to batch product) to be redistributed soon. @Daniele: What is status in DB of 6 (or 31?) re-tuned PMTs in Naples during DOM test? New test result? 2

3 CURRENT ITEMS New DOM exploded view (v12) DCR raised (version change request) and new version uploaded Changes: Include Ti bolts and nuts as batch products (STAC request) Change A/D filter from unique product to batch product Ti bolts and nuts: DB: 3.4.1.1.4 Ti bolt gr 5 M6 x 25 3.4.1.1.5Ti nut gr 5 M6 To do: container map (also change A/D filter to batch!) DOM integration software: Changes incorporated, but need to add columns for bolts and nuts Electrostatic discharge safety (ESD): What is done where? 3

4 DOM TEST SHEETS New version DOM test sheets DCR raised (version change request) and new version uploaded Changes: Change humidity ranges to 20-50% (was 30-50%) Change ToT range to 24-30 ns (was 25-28 ns) Change WR temperature to CLB temperature Add SFP temperature (since we also monitor FPGA temperature) 4

5 DOM TEMPERATURES 5 Humidity and temperature should come from same sensor: Hence: change WR temperature to CLB temperature

6 DOM TESTING To analyse the optical data from a DOM test (i.e. the root files), everyone should use http://svn.km3net.de/data_analysis/MRunAnalyzer/ http://svn.km3net.de/data_analysis/MRunAnalyzer/ DOM test sheets should be stored in DB as attachment Next on my list: ask Cristiano whether the data can be saved as “Test” instead of attachment to DB entry. Alternative (preferred, but not possible yet): data is saved automatically as DOM testing will progress to operating a DOM like a mini-detector. 6

7 DOM PRODUCTION STATUS: LINE TYPES Amsterdam: type B and type C Request to build type A for first ORCA line. Currently, no A-type SFP’s at Nikhef anymore and type C line DOM production has already started. Catania: type C Naples: type D Erlangen: Commissioning DOM test setup 7 Type A: CH56C-CH22C Type B: CH55H-CH21H Type C: CH55C-CH21C Type D: CH54H-CH20H

8 DOM PRODUCTION PLANNING 8 Location2014End 2015Spring 2016 End 2016TOTAL Amsterdam1938+80 (doubling 2015 production rate) 137 Naples4+18+3658 Catania4+18+3658 Erlangen+3636 Number of DOMs to be built before the end of 2016: 80+54+54+36= 224 Total number of DOMs produced by the end of 2016: 224+65 = 289

9 DOM COMPONENTS I will bring DOM components for 18 DOMs to Erlangen for Collaboration Meeting Penetrators: Testing of 64 PAVE penetrators at Nikhef done: New order of 100 penetrators placed, expected to arrive end of March (but pushing to send them sooner) Naples still needs 7 penetrators to complete 18 DOMs Catania still needs 12 penetrators to complete 18 DOMs But: there are (legal/tax) issues with shipments for PON money components Waiting for more info 9

10 TODO… Documentation DOM production: List of Applicable Documents Most notably the DOM Integration Procedure In good shape, will rediscuss open questions with Edward/Rene Otherwise, just aesthetics Integration Plan 10

11 DOM PRODUCTION AMSTERDAM (IN ABSENCE OF RONALD) 11 Script to produce plots from local integration DB can be found in: http://svn.km3net.de/integration/DOM_Production_Rate/