Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 14 Mar 2012 Doc: Source: [ETSI]

Similar presentations


Presentation on theme: "Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 14 Mar 2012 Doc: Source: [ETSI]"— Presentation transcript:

1 Timeline for the oneM2M Partnership Project Timeline and Milestones [Joachim Koss, ETSI] Contribution to oneM2M plenary, 14 Mar 2012 Doc: Source: [ETSI] TIA C.Blum Agenda item: Editors note: [Text in red within square brackets: To be deleted] Text in blue: New inserted text Text in purple: New inserted text (TIA) based on version of 20 Jan 2012 (input to CoU V1a)

2 Introduction Summary of timeline discussion at Washington meeting: [M2MCons02_31 Draft Meeting Report.doc] “Mr. Foote presented a table that captures a summary of the SDO positions along with a list of consensus items [M2MCons02_26]. There is agreement that the launch of the consolidated group should take place no later than 1Q2012, with the understanding that milestones will be met along the way to meet the established threshold criteria.” [M2MCons02_26 - Summary of SDO proposals on M2M Consolidation 4.4.pptx] “Launch of consolidated group no later than 1Q2012, with milestones to be met along the way to meet the threshold criteria.” In order to keep the envisaged date for launch of the M2M consolidation (Q1/2012) a more detailed time schedule with well defined milestones is necessary. The next pages propose a timeline including milestones and definition of milestones. 2

3 JULAUGSEPOCTDECJANFEBMARAPRMAYJUNJULAUGSEPOCT M5: TP start prepared M6: WG start prepared Virtual meetings 20112012 Timeline 3 SDO Meeting#01, Seoul, 21 Jul SDO Meeting#02, Washington, 17-18 Aug SDO Meeting#03, Berlin, 15-16 Dec Reach out to verticals M1: “Soft Launch” M2: Final Consensus M4: Official Signing Technical Plenary Meeting#1 Virtual SDO meetings SDO Meeting#04, Tokyo, 28-29 Mar M3: Final Draft Virtual meetings Steering Committee Meeting#1 Steering Committee Meeting#2 Vertical outreach is an ongoing effort

4  Milestone M1 – “Soft Launch” IPR regime agreed Communiqué released Material for communication with verticals updated to include Berlin meeting results Target date: 18 Jan 2012, completed  Milestone M2 – Final Consensus Feedback from vertical reach outs incorporated into major principles Final Consensus reached and documented on all major principles (scope, partnership and participation principles, structure, legal status, participation rules, rights and responsibilities, level of secretariat services, funding) Initial Organizations identified and start work on drafting the founding documents Target date: [17 Feb] 14 Mar 2012 (declared with exceptions) Target date: 29 Mar 2012 (completed) Milestones (1) 4

5 Milestones (2)  Milestone M3 – Final Draft Final review of feedback from vertical reach outs Final draft of founding documents available (Participation rules, procedures, IPR policy and anti-trust policy, membership fee structure and initial resources agreed upon) Secretariat support activities identified (e.g. online web presence, on-site meeting support, document editing, document management, branding/publicity) Convenor of Steering Committee nominated Meetings for rest of year planned Kick-off event planned (media event plus additional partners) Target date: [9 Mar] 30 Mar 2012 Milestone M4 – Official Signing Founding agreement signed Provision of secretariat function agreed upon Members of Steering Committee identified Preliminary list of members of the initiative identified Target date: [30 Mar] 04 May 2012 5

6 Milestones (3)  Milestone M4A Kick-off event First Steering Committee Meeting (Convenor) TP start prepared (meeting location, date, etc.)  Milestone M5 – [TP start prepared] Second SC Meeting and prep for TP Start Convenor of Technical Plenary nominated [Participants] Estimate of number of Participants to Technical Plenary [identified] Working Procedures approved List of standards/specifications to be transferred into GI agreed Target date: [19 Jun] 24 Jul 2012  Milestone M6 – [ WG start prepared] First TP Meeting Initial Work Plan defined Initial Working Groups defined Convenors of Working Groups nominated Meeting schedule defined Target date: [31 Jul] 04 Sep 2012 6