Congestion Management Work Group Update WMS 8-18-10 I Flores, S Reedy—ERCOT M Wagner--PSEG TX
2
CMWG Met on 7/30/10 Constraint Competitiveness Test (CCT) –Decision Making Entity (DME) List –List of Competitive Constraints CRR Auction Details –Several outstanding issues in ERCOT systems No showstoppers DA Model
3
Constraint Competitiveness Test – DME List http://www.ercot.com/gridinfo/sysplan/ Key Documents Controlling Entity Declaration Form (03/26/10,.doc, 82.5 KB)Controlling Entity Declaration Form Planning and Market Reports - Roadmap to P.U.C. Rule 25.505 (09/28/09,.doc, 72 KB)Planning and Market Reports - Roadmap to P.U.C. Rule 25.505 Resource Controlling Entity (07/28/10,.xls, 107.5 KB)Resource Controlling Entity
4
Constraint Competitiveness Test – DME List DME list persists as potential issue for CCT IMM attended CMWG and noted that DME list potentially does not reflect common control and decision making for entities ERCOT has done one follow up already—another may be desirable No insight on whether more concentrated DME list could potentially remove constraints on draft CCT list Recommend WMS ask for update from IMM
5
Constraint Competitiveness Test, ctd. CMWG was to report to WMS in August to with updated CCT list –Behind schedule –No results from LFC testing yet to determine whether competitive constraints seem reasonable
6
TAC Must Approve Competitive Constraints Protocol Definition “Competitive Constraint” “A contingency and limiting Transmission Element pair that is determined to be competitive by an appropriate TAC subcommittee.” –Requires analysis of nodal cases with congestion on competitive constraints and same load flow case without competitive offers in there to understand difference CCT is making –To meet go live schedule, TAC needs to approve this in Sept. Should NATF take this work on to ensure ERCOT involvement?
7
Congestion Revenue Rights Auction Working but with a couple of bugs –Outages not transferring smoothly into auction tool-- ERCOT has a work around –Connectivity Nodes (used to transform model from EMS format to CRR format)—a few transformation problems yet to resolve ERCOT responded to questions about recent auction results –Results were explainable due to various items— binding constraints, nonzero impedance between transformers at single location –BOD anticipated to approve go live prior to WMS meeting
8
Other DAM – to date does not include PCAPs, RAPs, SPS –No consistent process (to date) to incorporate in the DAM –ERCOT is working on the issue