Download presentation
Presentation is loading. Please wait.
Published byChad Milo Bailey Modified over 8 years ago
1
Scheduling CTC-370
2
Value Engineering Provides alternatives to the proposed design –Save Owner $$ –Must be as good or better than original design –Must save enough $$ so that contractor can recover his cost of doing VE –Usually comes from contractor’s or engineer’s previous experience
3
Value Engineering Can save $$ either due to savings in time or materials –Ex: Composite Wall and roofs –Material cost per sf is higher than regular roof –Labor cost is lower –Requires a crane
4
Value Engineering Ex: –Replace infiltrators with Eljen In drains System size is reduced to 50% Also reduces amount of sand, clay, topsoil Reduces dozer time and installation time In-drain costs about 2x infiltrator
5
Updating Schedule Frequency –Depends on Complexity –More complex -> more updates Unexpected events –Update after event to determine new completion date –Helps team evaluate strategies to mitigate impacts When specified –By contract documents
6
Updating Schedule How –Gather Activity Status Info Update Date – when the info is gathered Activity status –Actual start date – meaningful work begins –% complete »Work in place -> work in place/planned work quantity »Time expended -> time expended/ planned duration (only good for time dependent activities like concrete curing) »Cost Incurred - >cost incurred/planned cost (depends on actual resource productivity being constant and resource costs not varying) »Resource used -> Resource Used/Planned resource amount
7
Updating Schedule How –Activity status –Remaining duration – Remaining Work quantity/Anticipated Productivity –Actual finish date – all completed activities »Provides data for future jobs –Gathering Data Direct observation, Update meetings, field reports, turnaround reports, photos and videotape
8
Analyzing Schedule Status What is the basis for evaluating schedule status? –Usually the original schedule is the baseline What is planned completion date –Is updated schedule completion date same as baseline If not – why not (is there an error)
9
Analyzing Schedule Status Has the critical path shifted? –If so – why –Are CP activities really “critical” Has the float changed on any activities? Has weather become a factor for any activity Are there trends worth watching Any changes since last update?
10
Modify and Revise Schedule Revise network logic –Change duration to meet contracted completion –Reflect changes in planned means and methods for completing activity –Shift activity to better time (summer for concrete)
11
Modify and Revise Schedule Revise Activity Durations –Planned quantity of work has changed –Amount of resources has changed –Productivity is either higher or lower than planned Add & Delete Activities –Scope of work changed –Activities divided into smaller activities
12
Review and Analyze Schedule Make sure new schedule does not contain errors Implement updated schedule
13
Out of Sequence Work Why? –Keep crews busy –Preparatory work starts early Gives crew a chance to test means and methods Preserve Schedule Logic –Shorten successor activity caused by out of sequence work –Keep all other logic intact
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.