The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Mandalay Region Office Priorities and Detailed Description.

Similar presentations


Presentation on theme: "The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Mandalay Region Office Priorities and Detailed Description."— Presentation transcript:

1 The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Mandalay Region Office Priorities and Detailed Description of Electrification Plan For Mandalay Region Dated -21.Oct.2015

2 NoDistrictTownshipNos of VillageRemark 1Mandalay Amrabura12 Within 2 miles Distance from existing grid Line Pathein gyi8 2 Pyin Oo Lwin Mogoke22 Mattaya32 SinGu18 Thabeikkyin1 3Kyauk Se Kyaukse64 Sintgaing5 PaLeik7 Tada U12 Ku me29 Myitta18 Priority Electrification Project List for Mandalay Region 2

3 NoDistrictTownshipNos of VillageRemark 4MeikTilar Meiktlar21 Within 2 miles Distance from existing grid Line Thazi6 Wundwin16 Ma Hlaing21 Meiktlar21 5Myin Gyan 8 TaungTha24 Nato Gyi16 Nga Zun15 6Naung OO Naung Oo10 Kyauk Pa daung10 Nga Tha Youk11 Priority Electrification Project List for Mandalay Region 3

4 NoDistrictTownshipNos of VillageRemark 7Yamethin YamaeThin10 Within 2 miles Distance from existing grid Line PawBwe6 Yan Aung10 Total412 Priority Electrification Project List for Mandalay Region 4

5 YaMeThin District No. of Villages-26 Nos Household-3170 Estimated Cost-1605.26 (million Kyats) Electrification Plan for Villages of Mandalay Region (Within 2 miles from Existing 11 kV Distribution Line) Mandalay District No. of Villages-20 Nos Household-3152 Estimated Cost-1370.06 (million Kyats) NyaungOo District No. of Villages-31 Nos Household-6083 Estimated Cost-1858.42 (million Kyats) Meiktila District No. of Villages-64 Nos Household-6550 Estimated Cost-3919.06 (million Kyats) To be Constructed  11 kV Distribution Line464.58miles  400 V Distribution Line339.67miles  11/0.4 kV Distribution Transformer 396 Nos MyinGyan District No. of Villages-63 Nos Household-7593 Estimated Cost-3470.21 (million Kyats) PyinOoLwin District No. of Villages-73 Nos Household-8352 Estimated Cost-4418.5 (million Kyats) Kyaukse District No. of Villages-135 Nos Household-15654 Estimated Cost-9288.85 (million Kyats) 5

6 Detailed Electrification Plan for Mandalay Region (Within 2 miles from Existing 11 kV Distribution Line) NoTownship Total Numb er Of Villag e No of Hous e Hou se hold Popu lation To be constructed Estim ated cost (Mil Kyate s) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Lines (Mile s) Estimat ed Cost (Mil Kyats) mile Material Purcha se Trans port Cost Const r uctio n Cost TotalKVANo Material Purcha se Tran spo rt Cost Con stru ctio n Cos t Total 1Mandalay2019623152980819.4 407.4 19.477.6504.4434020 347 730377881.412.27343.56 2 Pyin Oo Lwin 738352 2568 4 76.3 1602.3 76.3305.21983.8999575 1301.25 26.2 5 112. 5 1413. 75 3397.658.751645 3Kyauk Se135 1426 5 1565 4 5901 5 164.2 6 3449.5 164.2 6 657.04270.8 1783 0 13 5 2342.25 47.2 5 202. 5 2544. 75 6815.594.952658.6 4MeikTilar6495406550 2112 3 74.27 1559.7 74.27297.11931.0 1166 5 62 1075.7 21.793 1168. 7 3099.780.522254.56 5Myin Gyan63 1206 1 7593 3278 2 66.15 1389.2 66.15264.61719.9994550 867.5 17.575942.52662.445.451272.6 6Naung OO31 1009 5 6083 2242 8 32.53 683.1 32.53130.1845.8484028 485.8 9.842527.81373.628.4795.2 7Yamethin 264001 344 5 2086 6 31.67757.1741.17 121.3 0 919.63316026400.099.10 20. 80 429.9 9 1349.6 2 19.33541.2 Mandalay Ragion Total 412 6096 1 505 54 1812 10 464.5 8 11107.1 8 530.4 1852. 9 13490. 47 6241 0 39 6 6870.60 138. 6 594 7603. 2 21093. 7 339.6 7 15247.4 5 6

7 The additional electrification statement due to newly and upgrading 66/33/11kV substation and related power line for Mandalay Region Sr No Township To Be Constructed The effective area (within 2 Miles) Estimated Cost (millon kyats) Substation 66kV Line (mile) 33kV Line (mile) Total Vill(ages (Nos) Total Househol d (Nos) Total Populatio n (Nos) Material cost Installatio n cost Total Cost 1 Patheingyi (Htone Bo) 33/11kV 10 MVA x 2 Newly --1110203480 1397.25150.971548.22 2 Thabeikkyin (Kyauk Phar) 33/11kV 3MVA to 5MVA Replacement Substation --15310012000 599.7414.7614.44 3 Kume 33/11kV 5MVA to 10MVA Replacement Substation --35425117220 698.6323.5722.13 4 * Myitthaar 33/11kV 3MVA to 5MVA Replacement Substation --39423217168 529.7414.7544.44 5 Tada Oo 33/11kV 5+2.5MVA to 10 MVA --271368 698.6323.5722.13 6 (a)KyauKse (Inn Yaung) 33/11kV 5 MVA Newly --69731245528 599.73105.83705.56 7 (b)KyauKse -5--- 202.9428.9231.84 Total-5171532084964 4726.66362.15088.76 REMARK – * The former 33/11 kV, 5MVA Transformer From Kume is Intended to use for Myitthaar. 7

8 Mandalay District 8

9 Amarapura Township No. of Villages-12 Nos Household-2142 Estimated Cost-657.35 (million Kyats) Mandalay District No. of Villages-20 Nos Household-3152 11 kV Line-19.40miles 400 V Line-12.27miles 11/0.4 kV Transformer-20Nos Estimated Cost-1370.06 (million Kyats) Location Map of Electrification Plan for Mandalay District (Within 2 miles from Existing 11 kV Distribution Line) PaTheinGyi Township No. of Villages-8 Nos Household-1010 Estimated Cost-712.71 (million Kyats) 9

10 Detailed Electrification Plan for Mandalay District (Within 2 miles from Existing 11 kV Distribution Line) NoTownship Total Numbe r Of Village No of Hou se Hous e hold Pop u latio n To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estimat ed Cost (Mil Kyats) mile Mater ial Purc hase Store Tran spor t Cost Cons truc tion Cost Tota l kVANo Material Purcha se Store Transp ort Cost Cons tructi on Cost Total 1Amrabura12174521428726 12.6 5 276.3 2 12.752.6 328. 9 286012 208.2 4.218226.2555.16.86192.1 2 Pathein gyi 8216101010826.75 147.4 6.828.1 175. 5 14808 138.8 2.812150.8326.35.41151.5 Mandalay District Total 20 196 1 3152 980 8 19.43.880.190.784.854340200.6235.610.5 12.2 7 3.4 10

11 PyinOoLwin District 11

12 Mogoke Township No. of Villages-22 Nos Household-2128 Estimated Cost-1242.79 (million Kyats) PyinOoLwin District No. of Villages-73 Nos Household-8352 11 kV Line-76.30miles 400 V Line-58.75miles 11/0.4 kV Transformer-75 Nos Estimated Cost-4418.50 (million Kyats) Mattaya Township No. of Villages-32 Nos Household-3999 Estimated Cost-1849.08 (million Kyats) SinGu Township No. of Villages-18 Nos Household-2155 Estimated Cost-1252.76 (million Kyats) ThaBeikKyin Township No. of Villages-1 Nos Household-70 Estimated Cost-73.87 (million Kyats) Location Map of Electrification Plan for PyinOoLwin District (Within 2 miles from Existing 11 kV Distribution Line) 12

13 Detailed Electrification Plan for PyinOoLwin District (Within 2 miles from Existing 11 kV Distribution Line) NoTownship Total Numbe r Of Village No of Hou se Hous e hold Pop u latio n To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estima ted Cost (Mil Kyats) mile Mater ial Purc hase Tran sCo st Cons tr uctio n Cost Tota l kVANo Material Purcha se Trans Cost Const ructio n Cost Total 1Mogoke222128 894919.7 430.2 6 19.782.0 512. 2 280023 399.05 8.0534.5 433.5 5 945.814.9417.2 2Mattaya323999 802831.6 690.1 8 31.6131.5 821. 6 480033 572.55 11.5549.5 622.0 5 1443.725.1702.8 3SinGu182155 863723.5 513.2 23.597.8 611. 0 229518 312.3 6.327339.3950.3 17.7 5 497.0 4 Thabeikkyi n 170 1.5 32.8 1.56.239.01001 17.35 0.351.518.8557.9128.0 Pyin Oo Lwin District Total 73 835 2 256 84 76.315.26 0.76 3 3.052 19.0 8 999575120075112.51388 1406.5 8 58.7 5 1645.0 13

14 Kyaukse District 14

15 Kume Township No. of Villages-29 Nos Household-3058 Estimated Cost-2832.63 (million Kyats) KyaukSe Township No. of Villages-64 Nos Household-7251 Estimated Cost-3922.99 (million Kyats) KyaukSe District No. of Villages-135 Nos Household-15654 11 kV Line-164miles 400 V Line-94.95miles 11/0.4 kV Transformer-135Nos Estimated Cost-9288.85 (million Kyats) Myittha Township No. of Villages-18 Nos Household-1712 Estimated Cost-882.53 (million Kyats) SintGaing Township No. of Villages-5 Nos Household-395 Estimated Cost-331.55 (million Kyats) PaLeik Township No. of Villages-7 Nos Household-1797 Estimated Cost-324.21 (million Kyats) Tada-U Township No. of Villages-12 Nos Household-1441 Estimated Cost-994.94 (million Kyats) Location Map of Electrification Plan for Kyaukse District (Within 2 miles from Existing 11 kV Distribution Line) 15

16 Detailed Electrification Plan for KyaukSe District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship Total Numbe r Of Village No of Hous e Hous e hold Pop u latio n To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estimat ed Cost (Mil Kyats) mile Mater ial Purc hase Tran sCo st Constr uction Cost TotalkVANo Materi al Purch ase Trans Cost Cons tructi on Cost Total 1 Kyauks e 647251 217 53 85.65 1870. 62 85.7356.3 2226. 9 842064 1110.4 22.496 1206. 4 3433.3 43.8 5 1227.8 2 Sintgain g 5395 11997.5 163.8 7.531.2195.06105 86.75 1.757.594.25289.33.7103.6 3PaLeik71797 529 4 8.3 181.2 4 8.334.5215.85507 121.45 2.4510.5 131.9 5 347.82.467.2 4Tada U121441 710 3 21.5 469.6 21.589.4559.0285012 208.2 4.218226.2785.212336.0 5Ku me2922153058 155 03 25.9 565.6 2 25.9107.7673.4339529 503.15 10.1543.5 546.6 5 1220.121.5602.0 6Myitta1811661712 816 3 15.41 336.5 28 15.464.1400.7200518 312.3 6.327339.3740.011.5322.0 KyauKse District Total 135 1426 5 1565 4 590 15 164.33285 164. 3 6574107178301352160135202.52498660413514265 16

17 Meiktila District 17

18 Meiktila District No. of Villages-64 Nos Household-6550 11 kV Line-74.27miles 400 V Line-80.52miles 11/0.4 kV Transformer-62Nos Estimated Cost-3919.06 (million Kyats) Thazi Township No. of Villages-6 Nos Household-1071 Estimated Cost-444.41 (million Kyats) WunDwin Township No. of Villages-16 Nos Household-1803 Estimated Cost-1245 (million Kyats) Meiktila Township No. of Villages-21 Nos Household-1860 Estimated Cost-1119.46 (million Kyats) MaHlaing Township No. of Villages-21 Nos Household-1816 Estimated Cost-1110.19 (million Kyats) Location Map of Electrification Plan for Meiktila District (Within 2 miles from Existing 11 kV Distribution Line) 18

19 Detailed Electrification Plan for Meiktila District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship Total Numbe r Of Village No of Hous e Hou se hold Pop u latio n To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estimat ed Cost (Mil Kyats) mile Materi al Purch ase Tran sCo st Constr uction Cost TotalKVANo Mater ial Purc hase Trans Cost Cons tructi on Cost Total 1Meiktlar211860 746 8 19.3 5 422.58 19.480.5503.1352521 364.3 5 7.3531.5395.85899.0 14.2 5 399.0 2Thazi620131071 402 5 6.35 138.68 6.426.4165.114306 104.1 2.19113.1278.27.27203.6 3 Wundwi n 161803 190 2 32 698.9 32.0133.1832.0412016 277.6 5.624301.61133.641.51162.0 4 Ma Hlaing 2138641816 772 8 16.5 7 361.85 6 16.668.9430.8259019 329.6 5 6.6528.5358.15789.017.5490.0 MeikTila District Total 6495406550 211 23 74.2 7 1485 74.2 7 297.11857116656299262931147 3003.7 5 649540 19

20 MyinGyan District 20

21 MyinGyan District No. of Villages-63 Nos Household-7593 11 kV Line-66.15miles 400 V Line-45miles 11/0.4 kV Transformer-50Nos Estimated Cost-3470.21 (million Kyats) NaToGyi Township No. of Villages-16 Nos Household-2297 Estimated Cost-1203.35 (million Kyats) TaungTha Township No. of Villages-24 Nos Household-2852 Estimated Cost-1636.2 (million Kyats) MyinGyan Township No. of Villages-8 Nos Household-1996 Estimated Cost-389.55 (million Kyats) NgaZun Township No. of Villages-15 Nos Household-448 Estimated Cost-241.11 (million Kyats) Location Map of Electrification Plan for MyinGyan District (Within 2 miles from Existing 11 kV Distribution Line) 21

22 Detailed Electrification Plan for MyinGyan District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship Total Numbe r Of Village No of Hous e Hous e hold Popu lation To be constructed Estimat ed cost (Mil Kyates) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estimat ed Cost (Mil Kyats) mile Material Purcha se Tran sCo st Const r uction Cost Tota l KVANo Material Purcha se Trans Cost Cons tructi on Cost Total 1 Myin Gyan 81996 53824.85 105.88 4.920.2 126. 1 131 5 8 138.8 2.812150.8276.96.05169.4 2 TaungTh a 2447222852944332.8 716.34 32.8136.4 852. 8 261 5 23 399.05 8.0534.5 433.5 5 1286.421.7607.6 3Nato Gyi162297 1186 5 23.5 513.2 23.597.8 611. 0 241 5 16 277.6 5.624301.6912.614.5406.0 4Nga Zun15304644860925 109.2 5.020.8 130. 0 360 0 3 52.05 1.054.556.55186.63.289.6 Myin Gyan District Total 63 1206 1 7593 3278 2 66.1 5 1323 66.1 5 264.6 165 4 994 5 5080050759252578.75 45.4 5 1272.6 22

23 NyaungOo District 23

24 NyaungOo District No. of Villages-31 Nos Household-6083 11 kV Line-32.53miles 400 V Line-28.40miles 11/0.4 kV Transformer-28Nos Estimated Cost-1858.42 (million Kyats) NgaThaYouk Township No. of Villages-11 Nos Household-2352 Estimated Cost-666.41 (million Kyats) KyaukPaDaung Township No. of Villages-10 Nos Household-1446 Estimated Cost-271.17 (million Kyats) NyaungOoTownship No. of Villages-10 Nos Household-2285 Estimated Cost-920.84 (million Kyats) Location Map of Electrification Plan for NyaungOo District (Within 2 miles from Existing 11 kV Distribution Line) 24

25 Detailed Electrification Plan for NyaungOo District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship Total Numbe r Of Village No of Hous e Hous e hold Popu lation To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estimat ed Cost (Mil Kyats) mile Material Purcha se Tran sCo st Constr uction Cost Tota l KVANo Material Purcha se Trans Cost Cons tructi on Cost Total 1 Naung Oo 1051212285 1024 2 19.5 3 426.524 19.581.2 507. 8 160 0 13 225.55 4.5519.5 245.0 5 752.812.3344.4 2 Kyauk Pa daung 101446 51303.4 74.22 3.414.188.4 162 0 3 52.05 1.054.556.55145.05.4151.2 3 Nga Tha Youk 113528235270569.6 209.68 9.639.9 249. 6 162 0 12 208.2 4.218226.2475.810.7299.6 Naung District Total 31 1009 5 6083 2242 8 32.5 3 650.6 32.5 3 130.1 813. 3 484 0 284482842518 1331.2 5 28.4795.2 25

26 Yamethin District 26

27 YameThin District No. of Villages-26 Nos Household-3170 11 kV Line-31.67miles 400 V Line-19.33miles 11/0.4 kV Transformer-26Nos Estimated Cost-1605.26 (million Kyats) YanAung Township No. of Villages-10 Nos Household-1169 Estimated Cost-631.098 (million Kyats) PyawBwe Township No. of Villages-6 Nos Household-810 Estimated Cost-396.96 (million Kyats) YameThin Township No. of Villages-10 Nos Household-1191 Estimated Cost-577.2 (million Kyats) Location Map of Electrification Plan for YaMeThin District (Within 2 miles from Existing 11 kV Distribution Line) 27

28 Detailed Electrification Plan for Yamethin District (Within 2 miles from Existing 11 kV Distribution Line) No Town ship Total Numb er Of Village No of Hou se Hous e hold Pop u latio n To be constructed Estima ted cost (Mil Kyates ) Task by regional Cost for 11 kV Line11/0.4 kV Transformer 400 V Line s (Mile s) Estimat ed Cost (Mil Kyats) mile Material Purcha se Tran sCo st Cons tr uctio n Cost TotalKVANo Material Purcha se Trans Cost Cons tructi on Cost Total 1 YamaeThi n 10 146 6 147 98 11.5274.94 14.9 5 44.05 333.9 4 80010153.883.58165.38 499.31 7 6.8190.4 2PyawBwe6810 261 8 6.1145.847.9323.36 177.1 3 760692.3282.14.899.228 276.35 98 6.4179.2 3YanAung10 172 5 1169 345 0 14.0 7 336.39 18.2 9 53.89 408.5 6 160010153.883.58165.38 573.94 47 6.13171.6 YameThin District 26 400 1 3445 208 66 31.6 7 757.17 41.1 7 121.3 0 919.6 3 3160. 0 26400.099.1020.80429.99 1349.6 2 19.3 3 541.2 28

29 The Statement of Fiscal Yearly Budget and Electrified Connection for Mandalay Region NoNo Fiscal Year State/Region Capital Budget for ESE (mil Kyats) State/Region Capital Budget for DRD (mil kyats) Electrified Connection On GridOff Grid Total Cost for 11 kV Line & 11/0.4 TR Total Cost for 400 V Line TotalOff Grid Villag e (Nos) Consu mer (Nos) Villag e (Nos) Consu mer (Nos) 1 2014--2015 Estimate (BE+RE) 1343.18- 2523.7718923247 1547392 2 2015-2016 Estimate (BE+RE) 1353.33- 2316.03222706 -- 3 2016-2017 Budget Estimate (BE) ------ -- Grand Total 2696.51- 4839.821125953 1547392 29

30 Main Materials List Transported to Mandalay District Office Sr No DescriptionUnit Quantitie s Transported Site 111/0.4 kV Distribution TransformerNo20Mandalay District,PMO Office 210 meter Concrete PoleNo820Mandalay District,PMO Office 3ACSR 95mm 2 Kg46100Mandalay District,PMO Office 411kV Disc InsulatorsSet466Mandalay District,PMO Office 411kV Pin InsulatorsNo1805Mandalay District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set20Mandalay District,PMO Office 6Other MaterialLot1Mandalay District,PMO Office 30

31 Main Materials List Transported to Pyin Oo Lwin District Office Sr No DescriptionUnit Quantiti es Transported Site 1 11/0.4 kV Distribution Transformer No75Pyin Oo Lwin District,PMO Office 2 10 meter Concrete Pole No3157Pyin Oo Lwin District,PMO Office 3 ACSR 95mm 2 Kg181289Pyin Oo Lwin District,PMO Office 4 11kV Disc Insulators Set1835Pyin Oo Lwin District,PMO Office 4 11kV Pin Insulators No7100Pyin Oo Lwin District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set75Pyin Oo Lwin District,PMO Office 6 Other Material Lot1Pyin Oo Lwin District,PMO Office 31

32 Main Materials List Transported to Kyauk Se District Office Sr No DescriptionUnit Quantiti es Transported Site 111/0.4 kV Distribution TransformerNo135Kyauk Se District,PMO Office 210 meter Concrete PoleNo6765Kyauk Se District,PMO Office 3 ACSR 95mm 2 Kg390283Kyauk Se District,PMO Office 411kV Disc InsulatorsSet3943Kyauk Se District,PMO Office 411kV Pin InsulatorsNo15277Kyauk Se District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set135Kyauk Se District,PMO Office 6Other MaterialLot1Kyauk Se District,PMO Office 32

33 Main Materials List Transported to Meiktilar District Office Sr No DescriptionUnit Quantiti es Transported Site 1 11/0.4 kV Distribution Transformer No62Meiktilar District,PMO Office 210 meter Concrete PoleNo3075Meiktilar District,PMO Office 3 ACSR 95mm 2 Kg176466Meiktilar District,PMO Office 411kV Disc InsulatorsSet1783Meiktilar District,PMO Office 411kV Pin InsulatorsNo6908Meiktilar District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set62Meiktilar District,PMO Office 6Other MaterialLot1Meiktilar District,PMO Office 33

34 Main Materials List Transported to Myin Gyan District Office Sr No DescriptionUnitQuantitiesTransported Site 111/0.4 kV Distribution TransformerNo50 Myin Gyan District,PMO Office 210 meter Concrete PoleNo2747 Myin Gyan District,PMO Office 3 ACSR 95mm 2 Kg157173 Myin Gyan District,PMO Office 411kV Disc InsulatorsSet1588 Myin Gyan District,PMO Office 411kV Pin InsulatorsNo6152 Myin Gyan District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set50 Myin Gyan District,PMO Office 6Other MaterialLot1 Myin Gyan District,PMO Office 34

35 Main Materials List Transported to Nyaung Oo District Office Sr No DescriptionUnit Quantiti es Transported Site 1 11/0.4 kV Distribution Transformer No28 Naung Oo District,PMO Office 210 meter Concrete PoleNo1353 Naung Oo District,PMO Office 3 ACSR 95mm 2 Kg77292 Naung Oo District,PMO Office 411kV Disc InsulatorsSet781 Naung Oo District,PMO Office 411kV Pin InsulatorsNo3026 Naung Oo District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set28 Naung Oo District,PMO Office 6Other MaterialLot1 Naung Oo District,PMO Office 35

36 Main Materials List Transported to Yamethin District Office Sr No DescriptionUnitQuantitiesTransported Site 111/0.4 kV Distribution TransformerNo26 Yamethin District,PMO Office 210 meter Concrete PoleNo1312 Yamethin District,PMO Office 3ACSR 95mm 2 Kg75248 Yamethin District,PMO Office 411kV Disc InsulatorsSet761 Yamethin District,PMO Office 411kV Pin InsulatorsNo2946 Yamethin District,PMO Office 5 Surge arresters, Disconnectors, Fuses Set26 Yamethin District,PMO Office 6Other MaterialLot1 Yamethin District,PMO Office 36

37 Main Materials List Transported to Mandalay Region Office Sr No DescriptionUnitQuantitiesTransported Site 1 11/0.4 kV Distribution Transformer No396 Mandalay Region,PMO Office 210 meter Concrete PoleNo19229 Mandalay Region,PMO Office 3ACSR 95mm 2 Kg1103851 Mandalay Region,PMO Office 411kV Disc InsulatorsSet11157 Mandalay Region,PMO Office 411kV Pin InsulatorsNo43214 Mandalay Region,PMO Office 5 Surge arresters, Disconnectors, Fuses Set396 Mandalay Region,PMO Office 6Other MaterialLot7 Mandalay Region,PMO Office 37

38 38