Download presentation
Presentation is loading. Please wait.
Published byGriffin McDowell Modified over 9 years ago
1
1 13 September 2006 EXPENDITURE TO 30 JUNE 2006 bbbbbbbbbbbbbbbbb
2
2 CONTENTS OF PRESENTATION Opening Purpose: Sec 32 reporting Budget Challenges & Constraints Policy Imperatives Interventions & Corrective measures
3
3 PROJECTION METHODOLOGY If projections are calculated linearly for 3 months out of 12 then the projected expenditure is 25% of the total Projects start and stop at different times and this is not a suitable method for evaluating projects An alternative method of Activity Based Costing is used: –linear projections but with adjustments for individual projects and interventions such as performance bonuses and salary increases.
4
4 BUDGET
5
5 MAIN INDICATORS: Programmes
6
6 Projected for 3 months: (R1066 mil / 12) * 3 = R 267 mil DEPARTMENTAL UNDER- EXPENDITURE 30 JUNE 06
7
7 MAIN INDICATORS: Economic Classification -12% -28% -27% -40%
8
8 30 June 06 Spending Outcomes 19% 23% 15% 26% 7% % of budget spent: Target = 25%
9
9 PROGRAMME 3: Roads Infrastructure
10
10 Approaches to bridges washed away
11
11 Bridge decks damaged
12
12 Drainage structures (pipes) exposed
13
13 Gravel wearing course washed away
14
14 Gravel wearing course washed away
15
15 Erosion damage along roads Erosion damage along roads
16
16 Underlying damage Underlying damage due to water ingress into brittle and cracked seals due to water ingress into brittle and cracked seals The total effect will only be evident in the months to come…
17
17 Underlying damage Underlying damage due to water ingress into brittle and cracked seals due to water ingress into brittle and cracked seals
18
18 Resultant damages
19
19
20
20 MAIN INDICATORS: Programmes -32% -7% -70% 0% +3% -300% % Over/Under linear projected amount
21
21 ROADS CONSTRUCTION Cash flow per month
22
22 ROADS CONSTRUCTION Capital full capacity spending
23
23 PROGRAMME 4: Public Transport
24
24 PROGRAMME 4: Traffic Management
25
25 PROGRAMME 1: Administration
26
26 PROGRAMME 2: Public Works
27
27 PROGRAMME 6: CBPWP
28
28 Works Expenditure for clients 30 June 06 28% 42% 10% 20% 16% 9% % of Linear projection: Target = 25%
29
29
30
30 Clinic Construction
31
31 SEDERHOF
32
32 REVENUE
33
33 REVENUE -20% -14% +25% Over/Under Projected
34
34 CHALLENGES AND CONSTRAINTS Infrastructure delivery Planning procedures Project Management Monitoring Consultants Client departments Floods Identify appropriate staff, engineers, project and financial managers Material supplies
35
35 Policy imperatives EPWP implementation Construction charter Financial institutions CIDB Taxi Recapitalisation – Testing stations 2010 requirements and deadlines
36
36 Interventions and corrective measures Appropriate staff for infrastructure delivery Changed planning patterns Fast-track payments Streamline operations Batho Pele: Testing stations and Revenue Authorities
37
37 THANK YOU
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.