Presentation is loading. Please wait.
Published byDouglas Peters Modified over 9 years ago
2
Reservoir Findings and Sediment Sampling The ACM is only along the berm Small amounts of tires and debris were found in or on the floor Two rounds of sediment sampling (March and August) March No asbestos VOCs, SVOCs, Metals – some low levels hits/similar to RI August – Validated results due in approximately 1 month
3
Reservoir Findings and Sediment Sampling ABS conducted on reservoir sediment – awaiting results Activity – disturbing sediment Sampling at 5 minutes, 1, 3, 6, and 10 hours Temperature survey conducted before reservoir was empty to identify springs/seeps – visual inspection on-going Groundwater level synoptics – rainy and dry
7
Removal Update
8
Aerial provided by Salvatore A. Boccuti
12
Pond Dewatering The pond is dry... as dry as it will get. Most likely we will have to pump after rain events. Began pumping on 12/24/13. Finished last week in July. Pumped for 116 days. As of 8/5/14 we have pumped 29.4 million gallons of water.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.