Ohio Department of Transportation www.transportation.ohio.gov John R. Kasich, Governor Jerry Wray, Director 2015-D08-04 CLE-32 Eastern Corridor Phase 4a October 13, 2015
2
www.transportation.ohio.gov 2 Project History 2009: District 8 requested $59.60 million for Environmental through Construction 2010: Design Consultant Authorized for all three projects in Phase 4a PID 82370 TRAC Presentation 10/13/15
3
www.transportation.ohio.gov 3 Project History 2015: TRAC List committed $1.3M for PE and $1.8M for DD Alternative Evaluation Report Approved PID 82370 TRAC Presentation 10/13/15
4
www.transportation.ohio.gov 4 PID 82370 TRAC Presentation 10/13/15
5
www.transportation.ohio.gov 5 TRAC Funding Request Right-of-Way: Total cost: $15.63 Million $3.13 Million from Local Funding (20%) TRAC Amount Requesting: $12.50 Million (80%) TRAC B/C Ratio – 7.11 (Score of 10) PID 82370 TRAC Presentation 10/13/15
6
www.transportation.ohio.gov 6 Thank You Questions? PID 82370 TRAC Presentation 10/13/15