1FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Peter Plug Chairman of the electricity working group Use and management of interconnections – The.

Similar presentations


Presentation on theme: "1FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Peter Plug Chairman of the electricity working group Use and management of interconnections – The."— Presentation transcript:

1 1FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Peter Plug Chairman of the electricity working group Use and management of interconnections – The European regulatory framework

2 2FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 What has to be done to reach 2014 internal market deadline (1/2) Market integration Internal market Coordinated network development

3 3FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 What has to be done to reach 2014 internal market deadline (2/2) Establishment of new institutions ENTSO-E (European Network of TSOs – Electricity) ACER (Agency for the Cooperation of Energy Regulators) Framework GuidelinesCodesDevelopment of Framework Guidelines and Codes Priority list (Commission) Framework Guidelines (ACER) Codes (ENTSO-E) Adoption of binding codes (Commission) Coordination of network development Ten-year network development plan

4 4FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 ACER Tasks as Regards the ENTSO-E Opinions Draft statutes, list of members and draft rules of procedures of ENTSO-E Draft annual programme, non-binding 10-year network development plan and network codes Where it considers that the draft annual work programme / non- binding 10-year network development plan / network code do not ensure non-discrimination, effective competition and the efficient functioning of the market Monitoring tasks Execution of the tasks of ENTSO-E Regional cooperation of the TSOs

5 5FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 ACER work on electricity framework guidelines Framework guidelines (non binding) set out clear and objective principles for the development of network codes relating to the areas identified in the priority list contribute to non-discrimination, effective competition and the efficient functioning of the market Deliverables in 2011: Grid connection Capacity allocation and congestion management System operation Balancing

6 6FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Development of framework guideline Identification of problem and objectives Identification of policy options Selection of policy option Public workshop Meetings of ad- hoc expert group Meetings with ENTSO-E ACERStakeholdersTSOs Draft Frame- work Guideline + GA Approval Public consultation Network Code process Revised FG + GA Approval ENTSO-E

7 7FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Grid connection Highlights Minimum requirements for all transmission grid users (Generators, Consumers, DSOs) New and (where applicable and necessary) existing grid users Next steps Final Framework Guideline (July 2011) Follow up on Network Codes on Grid Connection including ACER opinion ongoing until 2012

8 8FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Capacity Allocation & Congestion Management Highlights Intraday Day ahead Forward Governance (EC guideline) Next steps Final Framework Guideline (September 2011) Follow up on Network Codes Capacity Allocation and Congestion Management Forward Market network code

9 9FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 System operation Objectives operate the electrical system within defined limits apply same principles for different systems enable the integration of innovative technologies (Smart grids applications, renewable energy sources) make full use of information and communication technologies Next steps Final Framework Guideline (July 2011) Follow up on Network Codes NC on operational security NC on operational planning and scheduling NC on load-frequency control and reserves

10 10FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Balancing Highlights Depends on scoping discussions Most technical subject of the 3 rd package Next steps Final Framework Guideline (early 2012) Follow up on Network Code on balancing

11 11FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 EC priorities after 2011 Third party access rules Rules regarding harmonised transmission tariff structures Ten-year network development plan

12 12FTS-CEER bilateral meeting, St Petersburg, 17 May 2011 Thank you for your attention! www.energy-regulators.eu