Estimating Hip Roofs
2
Estimating Hip Roofs- Rafters
Pitch = 24⁰ Note – Change of Layout of Ceiling Joists to Accommodate Creepers Determine No of Rafters 12 500/ 600 = = = 22 Rafters each side = 44
3
Determine Rafter Length
Span = 6900
4
Determine Rafter Length
Span = 6900 Half Span = 3450
5
Determine Rafter Length
Span = 6900 Half Span = 3450 Run = 3450
6
Determine Rafter Length
Span = 6900 Half Span = 3450 Run = 3450 – 9.5 = Run of Eaves = 600 Total Run = = 4050 Total Length =4050/ cos 24 = offset =4473
7
Estimating Sheet
8
Estimating Hip Roof - Ridge
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Ridge 140 x 19 Purlin 90 x 70 F7 Ridge Runs Between Crown End x 3600 = 5300 ½ Rafter Thickness for each hip end =5345 mm
9
Estimating Sheet
10
Estimating Hip Roof - Purlin
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof Ridge 140 x 19 Purlin 90 x 70 F7 Spacing 2200 centres 1 Row Purlins at Centre Span Deduct ¼ span for every hip 12500 – 1725 – 1725 = 9050 allow 150 for joints = 9200 6900 – 1725 – 1725 = 3450
11
Estimating Sheet
12
Estimating Hip Roof – Hip Rafter
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Hip 140 x 19 Ridge 140 x 19 Purlin 90 x 70 F7 Method 1 Hip = √(Rise² + ((Half Span + O/H) x 1.414)² Hip = √(1.803² + (( ) x 1.414)² ) Hip = √( ) Hip = for Plumb Cut Hip = 6.153 Method 2 Hip = √(Total Rafter² + (Half Span + O/H)² Hip = √(4433² + ( )² ) Hip = √( ) Hip = for Plumb Cut Hip = 6.154
13
Estimating Sheet
14
Estimating Gable Roof - Struts
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Struts are Difficult to Estimate Develop a Best Guest Method Determine No Required 9.050/2700 =3.4= 4= 5 Each Side Determine No Required 3.450/2700 =1.28= 2= 3 Each Side
16
Estimating Gable Roof - Struts
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Length Half Rise x √2 x √2 (3.450/2 x tan24) x 2 0.768 x 2 = 1.536
17
Estimating Sheet
18
Estimating Gable Roof – Collar Ties
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Collar Ties 90 x 35 Collar Ties on Every 2nd Rafter On top of Purlins Length of Ridge / Rafter Spacing / 2 22/2 = HALF SPAN 3450
19
Estimating Sheet
20
Estimating Tile Quantities
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Collar Ties 90 x 35 Calculate Roof Area
21
Determine Rafter Length
Span = 6900 Half Span = 3450 Run = 3450 – 9.5 = Run of Eaves = 600 Total Run = = 4050 Total Length =4050/ cos 24 = offset =4473
22
Estimating Tile Quantities
Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Collar Ties 90 x 35 True Length of Rafter = 4433 Area of Roof = 4433 x ( x 0.45) x 2 = x 7 tiles per sqm =