MTA Installation Meeting March 7, 2007 Agenda 1)Progress report (Fernanda) 2)Water skid discussion (Maurice) 3)Alignment needs (O’Sheg + all) 4)AOB Key Red – critical Orange – warning Green – good to go
2
03/07/07F.G. Garcia2 Progress Report Relay Racks All racks have been delivered to X- Gallery Hi Bay area ☺ Base toe will arrive later this week. Racks, side panels, doors and bases need to be painted! Darrel Sigmon will coordinate this task. Hopefully by the end of next week this task will be completed.
3
03/07/07F.G. Garcia3 Progress Report – Power Supply 3 (or 4) magnets Shielding Wall Garage area 14 Quadrupoles Bartleson power supply ✔ Perhaps one needs 2 bulk supplies? It will depend on the rack location for the elements located beyond the shielding wall.
4
03/07/07F.G. Garcia4 Progress Report – Power Supply (cont.) Cooling Ring (CR) Dipoles Requirements: String of 4 CR Single CR For the string of 4 CR use a Trans Rex Supply has been moved from BEG to Linac Klystron gallery Final destination: Linac Lower Level (South end) For the single CR one still can use Power Ten ✔ PEI from TEL area Has it been confirmed?
5
03/07/07F.G. Garcia5 Progress Report - Instrumentation Instrumentations/Diagnostics First meeting was held last Monday Highlights 10 BPMs Use Booster style pickups Retrieve one out of the tunnel for measurements/development. Expert would like to use the same system used by Pbar group in the target region. Big question is whether the board can be modified to work on a 200MHz environment. 2 Toroids Booster has 2 ceramic gaps and 1 3 1/4in Pearson toroid. The setup will be similar as 400MeV Meet again in 2 weeks for status report and discuss further MWs and BLMs needs.
6
03/07/07F.G. Garcia6 Progress Report Mechanical Support Meet with D. Pushka (PPD/Mechanical Engineer) Help with stands modifications Help developing SQA “cradle fixture” to aid the removal of the magnets from the old 8GeV area Help plan the fixtures to safely lower equipment down into the Linac enclosure Meet with D. Erickson (PPD/MAB) They have material to build 5 cooling ring stands They need to buy material for the rest of the stands (quadrupoles, MWs) Drawings need to be identified/finalized ☹
7
03/07/07F.G. Garcia7 Old 8GeV line SQA Magnet Looking from below 3 in 0.5 in 0.5” 3”
8
03/07/07F.G. Garcia8 Alignment Needs Network setup Do we really need this new network? If YES… Hopefully it will be done prior the shutdown One access to mark the monuments location (~ 2 hrs/2 man crew) Another access to secure the monuments in place (~ 8 hrs/3 man crew) Involve drilling through the floor and wall Involve open the garage door Involve janitors to clean up the area If NOT … Start directly by staking survey the magnet stands.
9
03/07/07F.G. Garcia9 Organization Chart