PCF Project Preparation Cycle
2
5 PCF Project Preparation Stages 13 1. Activity: Preparation of PCF PIN ( 1. Activity: Preparation of PCF PIN (7 weeks indicative) 2. Activity : Preparation of PCF PCN ( ) 2. Activity : Preparation of PCF PCN ( 14 to 18 weeks indicative ) Output : PCF PCN (PCF Annex to PCD) Output : PCF PIN Output : PCF PCN 3. Activity : Preparation of PCF Annex to PAD (16 weeks indicative) Output : PCF Annex to PAD Output : Project Approval 4. Activity: Negotiation of Carbon Purchase Agreement ( 4. Activity: Negotiation of Carbon Purchase Agreement (11 to 15 weeks indicative) Fourteen Months
3
PCF Project Preparation Stages 13 Early Host Country Notification Review of PCF PIN by Fund Mgmt Unit (FMU) Output : PCF PIN Activity 1: Preparation of PCF PIN PIN - 7 weeks
4
PCF Project Preparation Stages 13 Host Country Endorsement Review of PCF PCN by Fund Mgmt Committee (FMC) Review of PCF PCN by Participants Committee Output : PCF PCN (PCF Annex to PCD) Activity 2: Preparation of PCF PCN PCN - 14 to 18 weeks
5
PCF Project Preparation Stages 13 Preparation of Monitoring and Verification Protocol Baseline Study as part of Feasibility Study Activity 3: Preparation of PCF Annex to PAD Output : PCF Annex to PAD PCF Annex to PAD - 16 weeks
6
PCF Project Preparation Stages 13 Output : Project Approval Validation process and opinion Output : Carbon Purchase Agreement Negotiation of Carbon Purchase Agreement Activity 4: Negotiation of Carbon Purchase Agreement Negotiation and Approval - 11 to 15 weeks
7
PCF Project Cycle Timeline PCF activities shown integrated with Bank project cycle, time requirements are indicative and compressible except where indicated Blue lines -Blue lines - PCF preparation activities, time requirements indicative Red lines - PCF activities with non-compressible time requirements Orange lines - concurrent Bank project preparation activities, time requirements indicative Dotted lines - ongoing activities
8
PIN Stage - Typical Time Requirement: 7 Weeks Month OneMonth Two Step 1: Receipt of Project Idea
9
PIN Stage - Typical Time Requirement: 7 Weeks Month OneMonth Two Step 7: Project organization workshop ( 1 week indicative) Step 6: GEF Review of PIN (2 weeks required) Step 4: Review of PIN by FMU (2 weeks indicative) Step 3: Development of PIN (2 weeks indicative) Step 5: Early notification of Host Govt Step 2: Project screening (1 week indicative)
10
PCN Stage - Typical Time Requirement: 14-18 Weeks Month ThreeMonth Four Step 8: Preparation of PCN (8-12 weeks indicative) Step 10: Host Government endorsement (required before FMC review) Step 9: Independent Risk Assessment (4 weeks indicative)
11
PCN Stage - Typical Time Requirement: 14-18 Weeks Month FiveMonth Six Step 11: FMC review of PCN (2 weeks required) Step 12: Review of PCN by Participants Committee (4 weeks required) Step 13: Review of PCF Annex to PCD by CMU (2 weeks indicative)
12
PAD Preparation Stage - Typical Time Requirement: 16 Weeks Month SevenMonth Eight Step14 -1: Preparation of PCF Annex to PAD (16 weeks indicative) a) Formal Baseline Study b) MVP Step 15: Preparation of Pre- Negotiations Workshop/Consultation
13
PAD Preparation Stage - Typical Time Requirement: 16 Weeks Month NineMonth Ten Step 15 (continued): Preparation of Pre-Negotiations Workshop/Consultation Step14 -1 (continued): Preparation of PCF Annex to PAD a) Formal Baseline Study b) MVP Step 15: Pre-Negotiations Workshop/Consultation (required before Appraisal) Step 14 - 2: (3-4 weeks indicative) c) Reassessment of Project Risk d) Formal Validation
14
Negotiation and Approval Stage - Typical Time Requirement: 8 weeks Month ElevenMonth Twelve Step 17: Review of PAD by CMU (3 weeks indicative) Step 18: Appraisal Mission to Host Country (2 weeks indicative) Step 67: Review of PCF Annex to PAD by FMU (3 weeks indicative) Step 19: Negotiations for underlying project (4 weeks indicative) Step 20: Negotiation of final PCF Component (3 weeks indicative)
15
Negotiation and Approval Stage - Typical Time Requirement: 8 weeks Month ThirteenMonth Fourteen Step 20 (Continued): Negotiation of final PCF Component (3 weeks indicative) Step 21: FMC clearance and RVP approval for disbursement of PCF funds (2 weeks required) Step 22: World Bank Board review of underlying project (3 weeks indicative) Step 23: Post Negotiation Workshop (3 days plus organizing time) Step 19 (Continued): Negotiations for underlying project (4 weeks indicative)