M. TYNDEL 1 LHCC Interactions May 2003 ATLAS SCT SCT Production Status ‘Snap-shot’ of the status of the SCT production (May 2003) 1. Barrel Modules 2. Barrel Opto-harnesses 3. Barrel support structures & cooling 4. Endcap Modules 5. Endcap Opto-harnesses 6. Endcap support structures & cooling 7. Power & Cables 8. Off-detector readout 9. Assembly & Integration
2
M. TYNDEL 2 LHCC Interactions May 2003 ATLAS SCT Modules Barrel module PRRMay 01 Detector productionMay 03 ( I.e. complete) Hybrids target end date Aug 031214/2500 (49%) Baseboards target end date Oct 031481/2530 (59%) Modules-Japan 356/ 786 (45%) Modules-UK 79/ 549 (14%) Modules-US 48/ 483 (10%) Modules-Scand (qualification soon)16/ 404 ( Total (2112+5%)499/ 2218 (22%) Modules target end date Apr 04 Barrel Modules
3
M. TYNDEL 3 LHCC Interactions May 2003 ATLAS SCT Barrel Optoharnesses Opto-harnesses Production now underway after slow start-up Main problem was ESD damage to DORIC ASIC First 2 harnesses fully evaluated Schedule can be recovered B3Jun 03 B6Jul 03 B5Sep 03 B4Oct 03
4
M. TYNDEL 4 LHCC Interactions May 2003 ATLAS SCT Barrel Structure & Cooling Support structures All 4 CF cylinders delivered …but there are ~40000 small parts! Cooling Design is finalised Production of cooling circuits underway On critical path
5
M. TYNDEL 5 LHCC Interactions May 2003 ATLAS SCT Endcap Modules Modules Endcap module PRRAug 02 & Nov 02 Hybrid design was validated as suitable for production Hybrid production & assembly transferred to industry Thermal performance validated Production Hybrids Pre-series of 200 in production – some delivered Full order for 2500 placed Spines 200 in production by Protvino/MPI Contract in place for 2500 Module assembly All 3 clusters have started ‘qualification’ process 1rst modules within specification Aim is to have all sites qualified in 2 months Goal is to complete module production in Sep 04 Very ambitious – will require extra resources
6
M. TYNDEL 6 LHCC Interactions May 2003 ATLAS SCT Endcap Optoharnesses, Structure & Cooling Opto-harnesses Simpler as the electronics is incorporated in the hybrid Production can start as soon as fibre lengths finalised Cooling Design is finalised & prototyped Production of cooling circuits ready to start Support structures CF disks & support cylinders ordered First 4 delivered; complete by Dec 03 Again many small parts 4 first disks & Stub cylinder delivered Expect delivery of cylinders by Aug 03 Disk PAR MAY 19 Critical issue is to complete disc machining by July
7
M. TYNDEL 7 LHCC Interactions May 2003 ATLAS SCT SCT Power, Cables, Readout, Assembly & Integration Power & Cables System designed & all elements prototyped FDR/PRR scheduled for May 28 Early production necessary for macro-assembly Cable tender in June Readout System designed & all elements prototyped FDR/PRR May 13 Early production necessary for macro-assembly Assembly & Integration B3 is at RAL to be equipped with services B3 will go to Oxford to have modules added Jul 03 – Nov 03 SR building at CERN now available Program of work underway to commission cooling, power & readout