1 THEMIS MRRI&T − 1GSFC, January 5, 2007 Integration and Test

2 THEMIS MRRI&T − 2GSFC, January 5, 2007 Integration Agenda Recent Activities Environmental Tests Completed Delivery to Astrotech Probe Processing Fueling Preparations Carrier Processing Probe and Instrument Status Instrument Status and Remaining Items Probe Status and Remaining Items Integration Plan Review Process RFAs in Work Reviews Ahead

3 THEMIS MRRI&T − 3GSFC, January 5, 2007 Environments Thermal Vacuum Acoustics Spin Balance EMC Vibration Magnetics

4 THEMIS MRRI&T − 4GSFC, January 5, 2007 Probe Processing Bolt Cutter Installation Performance Tests Solar Array Illumination Delivery to ASO

5 THEMIS MRRI&T − 5GSFC, January 5, 2007 Probe Fueling Preps FM2/FM3 Thermal Vacuum Vibration Thermal Vacuum Acoustics Spin Balance Storage Dry Weigh & Pressurize Ready for Fuel

6 THEMIS MRRI&T − 6GSFC, January 5, 2007 Carrier Processing VibrationAcoustics Spin Balance Storage PC Unload SSS Installation Ready for Probes

7 THEMIS MRRI&T − 7GSFC, January 5, 2007 Instrument Status Flight Hardware Ready Flight Software Ready Recent Activities Performance Test Remaining Items  ESC Verification  SST/ESA Covers  EFI Hats  Contamination Samples

8 THEMIS MRRI&T − 8GSFC, January 5, 2007 Probe Status Hardware Complete Software Complete Recent Activities at ASO Performance Tests Solar Array Illumination RCS Pressurization to 1.1*MEOP Dry Weigh Remaining Items  Fueling  Flight Plugs  Integrate to PC  Attach Sep System

9 THEMIS MRRI&T − 9GSFC, January 5, 2007 Integration Flow Probe Fueling Probe RCS Electr. Verif. Weigh Wet Probes, Attach Pyro PCA Funct. Spin Balance PCA Comm Check @ Blockhouse Install Pyro Signal SMDC/ Weigh PCA Engr Walk- down/ Trans- port Preps Move Probes to HPF Weigh PCA PCA Mate to 3 rd Stage/ Clamp- band Instl Transport to Pad S/C Functional & RF Test Launch Rehearsal Power On & Stray Voltage Install Fairing Prop. Load Prep 2 nd Stage Fueling, Ordnance Launch Readiness Review Launch Shipping from JPL 12/08/06 12/21/06 02/02/07 02/15/07 02/14/07 ASTROTECH and Launch Pad Flow 12/11/06 12/12/06 01/08/07 01/15/07 01/13/07 01/05/07 12/22/06 12/13/06 02/03/07 02/05/07 02/12/0702/13/07 PCA Functional 01/23/07 01/22/07 12/23/06 01/02/07 Reserve Christmas Shutdown 12/11/06 to 12/18/06 12/19/06 12/15/06 12/11/06 THEMIS Launch 01/03/07 02/07/0702/06/07 12/15/0612/14/0612/19/0612/15/06 12/20/0612/19/06 5 Probes plus EGSE, MGSE at ASO Probe Carrier Unpack Unpack, Setup EGSE PC-VCO Electrical Test Install Sep. Harness Install SMDC Lines F1 RCS MEOP, LPT, S/A Test Install Bolt Cutters, Therm. Closeouts F2-3 RCS MEOP, LPT, S/A Test F4-5 RCS MEOP, LPT, S/A Test Weigh, Move to Stands Pre-Vos MRR (GSFC) 01/03 01/05 LVRR (KSC) 01/12 Media Day 01/12 01/09/07 01/10/07 01/11/07 01/12/07 MRR (HQ) 01/23 01/24/07 01/25/07 01/26/07 01/27/07 01/29/07 01/30/07 LSRR (CCAFS) 02/01 01/3107 02/01/07 02/09/07 02/08/07 LMCM (KSC) 02/13 FRR (KSC) 02/12

10 THEMIS MRRI&T − 10GSFC, January 5, 2007 RFAs RFA Status Incomplete: 0 Complete:308 Closed:304 Total:308 Final Four Closure Method RCS Proof Issue: Expected to Close with Risk Definition BAU EEPROM Plots Provided were Insufficient to the reviewer but it is no longer practical to obtain better plots. Energy Balance was Provided using Best Thermal Model at the time. Reviewer repeated request using new mission profile and correlated thermal model. This was delivered in December. Launch Window Analysis will be reviewed by GSFC by 1/15/07

11 THEMIS MRRI&T − 11GSFC, January 5, 2007 Reviews Ahead