MUSE KO: MUSE Support at ESO ‘customer’ MUSE Team Created (ESO-customer), contacts with the Consortium and support activities on-going Budget and Manpower in the ESO Long Range Plan SoW and Tec Spec advanced, several iterations took place, within ESO and with the Consortium Reflective Slicer Prototypes contract (130 K) agreed, supporting the project until contract signature Reporting to ESO management, governing bodies
2
MUSE KO: PHASE A Follow-up (Management) 1) Missing Manpower, Staffing: Collaboration with LAOMP National agency support ? New Key-Personnel ensured (e.g. System Engineer) Relatively high turnover 2) Contain the Budget: Reflective Image Slicer Review of some requirements pending (e.g. Cal Unit, AI @ PDR) 3) Product Assurance: WP created, responsible individuated, staff trained
3
Muse KO: Phase A Action Items (Consortium) AI19) Identify Responsible VPHG work (closed) AI21) Identify how PA activities will be carried out (~closed) AI22, AI23) Prepare consolidate and manpower budget (~closed) 8 AI to be closed within the next months! E.G. Space (Electronics on Platform), Specs of detector system, NFM error budget, case for back focal distance..
4
MUSE KO: Phase A Action Items (ESO) AI25) Add requirements on data analysis in Tec Spec (~Closed) AI26) Specify minimum instrument throughput in Tec Spec (~Closed: values not yet agreed by Consortium) AI27) Include in TecSpec specs access around the Instrument (Closed) 2 Important AI to be closed in the next months (increase of VLT back focal distance, platform vibrations): some work is started AI30) Review AO+LGS: pending (see Hubin presentation)
5
MUSE KO: Strategic Risk The MUSE project is strictly connected to two R&D projects: AO Deformable Secondary and development of new lasers While an AO-assisted MUSE is clearly the baseline option and ESO will make all reasonable efforts to fulfill this task, a non negligible risk exists that one of these developments cannot be completed and MUSE will have no AO system The MUSE Consortium should consider this scenario, and fully develop a strategy which takes it into account (science cases, review of top instrumental characteristics...)
6
MUSE KO: Next Milestone PDR: In addition to ‘usual’ analysis a number of AI have been stressed at Phase A Review (Stability during operations, Thermal power budget, Enclosure Integration Plan Europe and Chile, Maintenance concept..) Image Slicer Prototypes fully tested and evaluated, all critical items assessed.