Download presentation
Presentation is loading. Please wait.
Published byBranden Powell Modified over 9 years ago
1
adem.alabama.gov Alabama Tier II Update Jimbo Carlson Chief, Facilities Engineering Section Governmental Hazardous Waste Branch Land Division
2
Key Topics My Perspective on Partnering Partnering in Alabama The Redstone Challenge Other Hot Topics in Alabama
3
Alabama Tier II Perspective Partnering Roles –Partner vs Regulator –Partner vs Mission Trust
4
Partnering in Alabama Alabama Teams –Fort Rucker –Anniston Army Depot –Fort McClellan –Maxwell Air Force Base –Marshall Space Flight Center –Redstone Arsenal
5
Partnering in Alabama cont.. State Challenges –Lack of Experienced Personnel –7 of 12 Tier I Members < 2.5 Years Experience –Training Ground –No Risk Assessors
6
The Redstone Challenge Site Complexity New Faces/Members Lack of Trust Solutions
7
Site Complexity 356 Total Sites (RCRA & Restoration) 13 Commingled Groundwater Plumes RODs Proposed for the coming years Year2008200920102011201220132014 RODs 9594439151
8
New Faces/Members ADEM has four RPMs –Plus 2 Hydrogeologist –ADEM also has Contract Support Risk Assessors and UXO Expertise EPA has 2 RPMs along with 1 additional FTEs – Also has Contract Support
9
Lack of Trust No Actual Partnering Taking Place –Technical Oversight –Significant Arguing at the Table –Tier II Not Welcome
10
Solutions Personnel Changes –EPA and ADEM Back to Basics –Tier I tasked by Tier II to determine type of training/facilitation needed –Redstone Tier II representative procured training funds –Tier I Chose Facilitator
11
Federal Facility Agreement FFA Background Current Status
12
Groundwater IROD RSA – 99 (Abandoned Plating Shop) –Two Party ROD signed in 2004 ADEM Position Tier II tasked Tier I to develop a Groundwater Interim Record of Decision
13
Other Hot Topics Anniston Chemical Demilitarization Facility
14
ANCDF Finished GB Campaign in March 06 VX Campaign started in July 06 –All VX M55 Rockets destroyed as of March 07 Eliminated 97% of Risk to Community –Recently began destroying 155mm Projectiles 140,000 155mm & 44,000 Mines Left Mustard Campaign scheduled to begin in September 2010, finishing in August 2013 –106 Ton Containers & 430,000 4.2” Mortars
15
M55 Rocket (VX)
16
Camp Sibert Site 8 – Former Toxic Munitions Impact Area –6870 Anomalies Dug 23% Hot Soil 27% Cultural Debris 40% Munitions Debris 0.3% UXO –18 4.2” Mortars with a Liquid Fill Sites 17 &18 Former Japanese Pill Boxes –To date: 1 Conventional 4.2” Mortar and 3 Liquid Filled 4.2” Mortars Site 19 Conventional Impact Mortar Range Area –1 Livens Projectile (Liquid Filled)
17
Camp Sibert Site 8
18
4.2” Liquid Filled Mortar
19
4.2 “ Liquid Filled Mortar
21
Interim Holding Facility
22
Blast Containment
23
4.2” Conventional Mortar
24
Post Destruction
25
Questions ? Jimbo Carlson - ADEM (334) 270-5627 jhc@adem.state.al.us
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.