Testing of Low Voltage Installations
(Textbook Chapter 11) Electrical Installation II
2
Procedure for Inspection, Testing and Certification
Divided into inspection and testing. Inspection Identification of conductors Cable rating Fire barriers Isolation etc. Electrical Installation II
3
Testing of LV Installations
Sequence of Test Continuity of protective conductors Continuity of ring final circuit conductors Insulation resistance Polarity Earth electrode resistance Earth fault loop impedance Functions of all protection device Functions of other equipment Electrical Installation II
4
Testing of LV Installations
In the event of any test indicating failure to comply, that test and those preceding, the results of which may have been influenced by the fault indicated, should be repeated after the fault has been rectified. Electrical Installation II
5
Testing of LV Installations
Continuity of protective conductors Every protective conductor, including all conductors and any extraneous conductive parts used for equipotential bonding should be tested for continuity. At the mains, connect together the neutral and protective conductors, then check the continuity between the neutral and the earth at every socket outlet. Electrical Installation II
6
Testing of LV Installations
Continuity of ring final circuit Electrical Installation II
7
Testing of LV Installations
Insulation resistance Fuse links and switches should be closed. Lamps should be removed, if not practical, lighting switches should be switched off. Electronics equipment should be isolated. Electrical Installation II
8
Testing of LV Installations
Electrical Installation II
9
Testing of LV Installations
Electrical Installation II
10
Testing of LV Installations
Polarity Electrical Installation II
11
Testing of LV Installations
Earth electrode resistance Electrical Installation II
12
Testing of LV Installations
Electrical Installation II
13
Testing of LV Installations
Electrical Installation II
14
Testing of LV Installations
Earth fault loop impedance Before the test, the bonding connection to electricity supplier’s earthing should be disconnected. The value should not exceed the requirements of Code 11, Tables 11(8) to 11(14) Electrical Installation II
15
Testing of LV Installations
Functional test of protective devices RCD by RCD tester, e.g. within 0.3s at rated residual current MCB and other protective devices by hand operation Electrical Installation II