Download presentation
Presentation is loading. Please wait.
Published byPhilippa Francis Modified over 9 years ago
1
N. Walker, K. Yokoya LCWS ’11 Granada September 27 2011 TeV Upgrade Scenario: Straw man parameters
2
Two tentative parameter sets Document distributed on 29.08.11 –ILC-EDMS D*965015 Primary constraints: –P AC ≤300 MW –Baseline 500 GeV machine unchanged upgrade scenario: add more linac Two sets proposed for study – BS ~5%,L ~2.8×10 34 cm -2 s -1 – BS ~10%L ~4.7×10 34 cm -2 s -1 27.09.11 LCWS - Granada
3
From 500 to 1000 GeV 2.2 km 1.3 km 10.8 km 1.1 km BDS Main Linac e+ src bunch comp. <26 km ? (site length <52 km ?) Main Linac = 31.5 MV/m G eff ≈ 22.7 MV/m (fill fact.= 0.72) IP central region <10.8 km ? Snowmass 2005 baseline recommendation for TeV upgrade: G cavity = 36 MV/m ⇒ 9.6 km (VT≥ 40 MV/m) Based on use of low-loss or re- entrant cavity shapes Assume Higher Gradient 27.09.11 LCWS - Granada
4
Construction Scenario(s) BDS Main Linac e+ src IP BC BDS Main Linac e+ src IP BC BDS Main Linac e+ src IP BC BDS Main Linac e+ src IP BC start civil construction 500GeV operations Installation/upgrade shutdown civil construction + installation final installation/connection removal/relocation of BC Removal of turnaround etc. Installation of addition magnets etc. Commissioning / operation at 1TeV 27.09.11 LCWS - Granada
5
Ramifications of upgrade scenario Beam pulse structure constrained by baseline 500 GeV machine –RF pulse length(1.6-2.0 ms) –Main linac current (≤ 9mA) –Cryogenics, CF etc. Original linac (5-250 GeV) must now transport 250-500 GeV beam –Implications of quadrupoles, lattice and beam dynamics (emittance) Most cost-effective approach –least invasive schedule 27.09.11 LCWS - Granada Assumes no major installation/upgrade of RF power source
6
Luminosity constrained P AC what are the options? 27.09.11 LCWS - Granada
7
Luminosity Goes down with increasing gradient (longer fill time) Constrain to ≤220MW (linac) little to be gained here (factor <1.5) Constrained by physics? shorter increases stability (integrated lumi) 27.09.11 LCWS - Granada
8
AC Power (RDR Linac) 27.09.11 LCWS - Granada Wall Plug P beam = V acc ×I beam ≈ 20 MW P RF ≈ 32 MW
9
AC Power (RDR Linac) 27.09.11 LCWS - Granada Wall Plug RF Power Generation (Modulator, klystron, Waveguide distribution) P beam = V acc ×I beam ≈ 20 MW P RF ≈ 32 MW P AC(RF) ≈ 76 MW ≈ 44%
10
AC Power (RDR Linac) 27.09.11 LCWS - Granada Wall Plug RF Power Generation (Modulator, klystron, Waveguide distribution) P beam = V acc ×I beam ≈ 20 MW P RF ≈ 32 MW P AC(RF) ≈ 76 MW ≈ 44% to beam dump 56 MW to remove! +24 MW water (CF)
11
AC Power (RDR Linac) 27.09.11 LCWS - Granada Wall Plug RF Power Generation (Modulator, klystron, Waveguide distribution) P beam = V acc ×I beam ≈ 20 MW P RF ≈ 32 MW P AC(RF) ≈ 76 MW ≈ 44% to beam dump 56 MW to remove! +24 MW water (CF) Cryogenic Power 33 MW
12
AC Power (RDR Linac) 27.09.11 LCWS - Granada Wall Plug RF Power Generation (Modulator, klystron, Waveguide distribution) P beam = V acc ×I beam ≈ 20 MW P RF ≈ 32 MW P AC(RF) ≈ 76 MW ≈ 44% to beam dump 56 MW to remove! +24 MW water (CF) Cryogenic Power 33 MW 132 MW
13
Reducing the Repetition Rate P AC = 215 MW (RDR) Doubling linac: 215+140* = 355 MW Reduce rep. rate 5Hz to 4Hz: –2×4/5×P RF 130 MW –(1+4/5)×P CF 41 MW –(1+4/5)×P cry 60 MW Total313 MW 27.09.11 LCWS - Granada RDR * 132×250/235 This scenario still assumes 31.5 MV/m @9mA Does not include: additional overhead for gradient spread (+12% RF power) new damping ring configuration
14
The (Upgrade) Gradient Question Primary a capital cost issue 45 MV/m ⇒ ~20% potential saving in upgrade linac costs Higher Q 0 beneficial –reduced cryo power ⇒ capital cost and power reduction Higher gradient ⇒ reduced efficiency –assuming same current and beam pulse length Hence influences AC power –and therefore luminosity if AC power is constrained 27.09.11 LCWS - Granada
15
Gradient, Power & Luminosity 27.09.11 LCWS - Granada Q0Q0 Luminosity reference: n b = 2625 n b scaled to give 300 MW 4Hz operation assumed chosen for straw man parameters n b = 2280 Note: simple scaling only!
16
Luminosity Parameters Have already reduced P beam –5 down to 4Hz –Reduced n b by 13% Increase x → x to constrain BS Reduce bunch length z (and y → y ) –assume two-stage compressor –(irrespective of decision for 500GeV baseline) Assume y = 30 nm at the IP –Aggressive –Beam dynamics issues 27.09.11 LCWS - Granada
17
Published Numbers For study purposes only –both machine and detector Machine parameters will be reviewed this workshop Subject to change! 27.09.11 LCWS - Granada
18
Example: Vertical Emittance 27.09.11 LCWS - Granada Original 500 GeV linac Assumed FFDD focusing for higher-energy beam BPM scale (calibration) error in conjunction with earth curvature 30 nm K. Kubo (KEK) Simulations of beam-based alignment Standard assumed alignment errors
19
Pair Angle Kaoru Yokoya Sep.27.2011 LCWS11 Granada, Spain 19
20
Out-coming Angle of Pairs Pair particle of energy Same sign of charge with the on-coming beam Horizontal angle is comparable to vertical angle Given by (very crudely) Ignore log factor 20
21
If bunch length is increased –Hourglass serious –But beamstrahlung loss decreases can make horizontal beam size smaller luminosity larger can make vertical beam size larger e.g., 21
22
22
23
Very reliminary 10% 150 m 10% 300 m 23
24
24 Black: 10% 150 m Red : 10% 300 m
25
25 Black: 10% 150 m Red : 10% 300 m
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.