26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI1 2013 New recuperation system for n-Pentane: Installation of the module in parallel of the first recuperation Coordination of the safety gas detection Test and running for a week (Result at 3500l/h, increase of the recuperation by nearly a factor 2). Maintenance and modification of the first recuperation: Dismountling and rebuild of the recuperation as the new one Installation and test forseen in summer 2014. Modification of the system to reach the new specification: New specification ask by the detector team: nominal flow from 2500 l/h to 5000 l/h. (Means new Mixer, new Purifier and new Pump) Dismountling of the mixer and purifier. New modules in construction and hopefully ready for summer. Installation and test forseen in summer 2014. PH-DT-DI 2013/2014 ATLAS activities TGC gas system
2
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI2 2013 Modification of the 5 distribution input valve: The idea was to reduce the pressure increase at the start-up of the modules. Leak search on the distribution: Reduce C2H2F4 consumption and monitor the increase of Oxygen inside the system Modification of the distribution for detector safety: Quick connector change at the output of the chambers Installation of hand valves to open chamber to air during long stop. Modification of the system to reach the new needs: Actual flow of 3000 l/h increase to 5000 l/h Modifiaction of the pump module (passing from 2 pumps to 3 pumps) Gas line from USA 15 to SGX1 has been double with another 28mm pipe. 2014 Modification of the purifier pilot valves and new pressure regulation device: To improve purifier module and buffer pressure regulation. PH-DT-DI 2013/2014 ATLAS activities RPC gas system
3
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI3 2013 Modification of the distribution pilot valves: During stops some channel valves stayed open because of leak inside pilot valve blocks (around 450 pieces in total for all systems). PH-DT-DI 2013/2014 ATLAS activities MDT gas system
4
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI4 2013 NEW MIXER WITH ARGON MIXTURE supply mixture with argon to leaky chambers Recalibration of Mass flow controlers adapt some flow to new requests PH-DT-DI 2013/2014 ATLAS activities TRT gas system
5
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI5 PH-DT-DI 2013/2014 ATLAS activities LUCID gas system 2013 LUCID Gas system dismountling : Dismounting of the 2 distribution racks in the cavern Dismounting of the Pré-distribution rack in the USA15
6
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI6 PH-DT-DI 2013/2014 ATLAS activities TFC gas system 2013 TFC pump maintenance: Problem with the new pump after 3 months of running. Restart of the full system Mars 2014
7
26/03/20147 PH-DT-DI 2013/2014 CMS activities 2013/2014 Gas systems/Analysis maintenance list: circulation pumps safety valves and bubblers power supplies profibus quality pressure regulators analysis devices fill TGC with N-Pentane check/repair heating cables/connectors calibrations MFC L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI
8
26/03/20148 A lot of activities completed/on-going during 2014 Many new consolidation projects for all experiments Conclusions L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI