Download presentation
Presentation is loading. Please wait.
Published byMaude Briggs Modified over 8 years ago
1
Construction Schedule for Baseline and Hybrid A’ Configuration 1 5 th September, 2014 J-POWER MDI-CFS Meeting - Ichinoseki City, JAPAN
2
The Configuration of the Baseline and the Hybrid A’ Outline of the Construction Schedule ‒ The Baseline ‒ The Hybrid A’ ‒ Assumption of the schedule Issues 2 Contents MDI-CFS Meeting - Ichinoseki City, JAPAN
3
Baseline 3MDI-CFS Meeting - Ichinoseki City, JAPAN
4
4 Hybrid – A’
5
Ex. Tunnels around D/H 5 Outline of the Detector Hall (D/H) construction procedure - Baseline Design - Time-line (const. period: 115.9 months) Lower A/T Upper A/T Upper A/T Cavern Ex. by bench cut Cavern Ex. by bench cut Concreting Utilities (Pipes, Ducts etc.) Utilities (Pipes, Ducts etc.) Pacman, Platform Pacman, Platform ILD, SiD Assembling ILD, SiD Assembling Assembly Hall (@ A/T portal) Access Tunnel (A/T) Access Tunnel (A/T) MDI-CFS Meeting - Ichinoseki City, JAPAN Crane 34.0 25.4 42.7 56.9 60.1 67.9 79.9 115.9 Tunnels Detector Hall(D/H) Assembly Utilities & Test Equip DR A/T
6
6 Outline of the Detector Hall (D/H) construction procedure - Hybrid A’ Design - Time-line (const. period: 103.0 months) Utility Shaft Utility Shaft Concreting Utilities (Pipes, Ducts etc.) Utilities (Pipes, Ducts etc.) Pacman, Platform Pacman, Platform SiD Assembly Assembly Hall (above the D/H) Assembly Hall (above the D/H) DR A/T MDI-CFS Meeting - Ichinoseki City, JAPAN Crane 47.2 27.1 54.6 51.4 62.4 74.4 103.0 Tunnels Detector Hall(D/H) Utilities & Test Equip Assembly Main Shaft Main Shaft Cavern Ex. by bench cut Cavern Ex. by bench cut 28.6 32.7 31.0 ILD Assembly 97.0 Platform 37.0 Platform Ex. Tunnels around D/H 29.4 Underground assembly Underground assembly 91.0 Lowering 85.0 79.0 85.0
7
MDI-CFS Meeting - Ichinoseki City, JAPAN7 Const. Schedule for the Baseline Design
8
8MDI-CFS Meeting - Ichinoseki City, JAPAN Const. Schedule for the Hybrid A’ Design
9
- Backhoe - Wheel Loader - Jumbo - Shotcrete Machine - Crawler Drill - Dump Truck - Lifting Equipment 87.6m 108.0m 42.0m Excavation Method for the Baseline Excavation Method for the Hybrid-A’ 144.0m 42.0m 9MDI-CFS Meeting - Ichinoseki City, JAPAN
10
Preparation work : Land forming - 6 months + temporary work - 2 months Access tunnel gradient (only for Baseline) : max. 10% D/H excavation commencement Baseline: After completion of upper A/T Hybrid A’: After completion of the main shaft (by using the main shaft) Construction speed of tunnel and D/H: same as the TDR Construction speed of shafts (only for Hybrid A’) : newly estimated Utility shaft (only for Hybrid A’): After completion of the utility cavern Detector platform installation After completion of the D/H floor concreting and utilities installation 10 Assumption for the schedule MDI-CFS Meeting - Ichinoseki City, JAPAN
11
Detector assembly Baseline: to be assembled in the underground Detector Hall Hybrid A’: to be assembled on the ground surface ‒ ILD: to be assembled on the floor of the assembly hall (5 pieces) ‒ SiD: to be assembled on the platform basically (only 1 piece will be assembled on the floor) Platform for the detector installation is to be made in the beginning of the assembly in parallel ‒ Parallel work might be carried out in the assembly hall ‒ For SiD, platform might be constructed during the detector assembling which will be assembled on the floor (not on the platform) MDI-CFS Meeting - Ichinoseki City, JAPAN11 Assumption for the schedule
12
When are the surface platforms located in assembly hall installed? Parallel work is possible or not. It’s assumed that they will be made in the beginning of the detector assembly. ‒ The detector assembly and platform construction is to be carried out in parallel. ‒ 6 months was considered. It will not affect the detector assembling schedule because of the parallel work. ‒ Otherwise, the platform installation period (6 months) might be affect the detector assembling schedule, or surface assembly yard might be increase in size for the platform assembly yard securing. Whether or not the environment affect the detector assembly, is not clear. ‒ Therefore, we would like to consider the possibility of the steel construction applicability for the platforms (not reinforced concrete). 12 Issues MDI-CFS Meeting - Ichinoseki City, JAPAN
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.