SCT week: 14th - 16th Dec 04 Spine progress R. Bates University of Glasgow
2
SCT week: 14th - 16th Dec 04 Spines produced at IHEP AprilMayJuneJulyAugustSept.Oct.Nov. Outer905833739911876137 Middle38746062673210019 Inner255628734502444 Total15318895222200 Total% of orderTo make ISTCInc. new order Outer96772283333 Middle52480127277 Inner366100-17200 Overall185781410810
3
SCT week: 14th - 16th Dec 04 Spines to be produced at IHEP Dec. 04Jan. 05Feb. 05March 05 Outer7486 87 Middle7667 Inner5550 45 Total205203 199 Inners of extra order required before ISTC finished, therefore IHEP will make extra inners early
4
SCT week: 14th - 16th Dec 04 Shipments from CERN Fall in Nov due to late delivery of shipment Nov + Dec = 194, all from IHEP November shipment Average per month since July (inc) –Outer : 77 –Middle : 59 –Inner : 42 –Total : 178
5
SCT week: 14th - 16th Dec 04 Cumulative total So far supply keeping up with demand – Just! –Very tight over Christmas period (CERN closed) –Extra mid-month delivery will ease delivery situation Totals: Outer:876 Middle:535 Inner:408 (note includes INTAS spines)
6
SCT week: 14th - 16th Dec 04 Yield Yield as observed at production sites (from database) –Outer88% –Middle92% –Inner84% Many causes –Bow is now rare, as is spacer damage in transit Far-end washer size now checked at Geneva –Occasionally Oversized (2.01mm) but appears un-damaged! Worried that quality will be affected at CERN due to extra work load caused by late shipments
7
SCT week: 14th - 16th Dec 04 Supply Delays in shipping from Moscow a serious problem with schedule Delay of 14 days in last shipment –Some spines delivered by hand but IHEP not keen on this –Adds extra work load on CERN based technician Added extra shipments to ISTC contract to allow 2 shipments per month Attempts being made to convey urgency of shipping problem to ISTC via senior management.
8
SCT week: 14th - 16th Dec 04 New Order All TPG required has been delivered ISTC contract adjusted to allow extra shipments (another 5 to go) ISTC contract adjusted to purchase extra ceramics Spine assembly contract in process of being signed –Work progresses regardless of slight delay