Presentation is loading. Please wait.

Presentation is loading. Please wait.

Estimating Concrete Construction and Material Cost

Similar presentations


Presentation on theme: "Estimating Concrete Construction and Material Cost"— Presentation transcript:

1 Estimating Concrete Construction and Material Cost

2 Concrete weights and measures.
A. One sack of cement = 94 pounds or one cubic foot B. One gallon of water = 8.3 pound C. 7.5 gallons of water = 1 cubic foot D. One cubic yard = 27 cubic feet E. One cubic foot of sand weighs about 100 pounds F. One cubic foot of gravel weighs about 100 pounds

3 Estimating concrete for a job.
A. The unit of measure for concrete is the cubic yard, which contains 27 cubic feet. B. To determine the needed amount of concrete, find the volume in cubic feet of the area to be concreted and divide this figure by 27. C. Formula for determining the amount of concrete needed for any square or rectangle area: Cubic yards of concrete = Width in feet x length in feet x thickness in feet 27

4 Estimating concrete for a job.
Example: a 4" thick floor for a 30 x 60 ft. building would require: 30' x 60' x 1/3' = 600 cu. ft. = cu. yards 27 cu. ft cu. ft.

5 Estimating concrete for a job.
D. The determined amount of concrete must allow for waste or slight variation in concrete thickness. An additional five to 10 percent will be needed to cover waste and other unforseen facts.

6 Estimating concrete for a job.
E. Fuller method: It takes 42 parts of materials to make 27 parts of cement. $       Volume = 200 cu. ft. $       Cu. ft. of raw materials needed 42/27 ( 200 cu ft.) = 311 cu. ft. $       Cu. ft. of raw materials per batch: = 7 2 cu. ft. $       Number of batches = 311 cu. ft. = 7 2 cu. ft. $       Sacks of cement = 1 (41.467) = or 42 sacks $       Cu. ft. of fine aggregate (41.467) (2 2) = or 104 cu. ft. $       Cu. ft. of coarse aggregate (41.467) (4) = or 166 cu. ft. $       Water to add per batch 7-5/8 = 6 3/8 gals.

7 Estimating concrete for a job.
F. Absolute volume method. $                                           Formula: Absolute Volume = Weight of loose materials Specific gravity x unit wt. of water $                                           Cement: Absolute Volume = 1 cu. ft. x 94 lbs./cu. ft. = 94 = cu.ft. 3.15 x $                                           Fine Aggregate: Absolute Volume = 2 2 cu. ft. x 100#/cu. ft. = 250 = cu.ft x

8 Estimating concrete for a job.
F. Absolute volume method. $                       Coarse aggregate: Absolute Volume = 4 cu. ft. x 100#/cu. ft. = 400 = cu.ft. 2.65 x $                         Water: Absolute Volume= 7/7 2 x 62.4 = 7/7 2 = cu. ft. 1 x 62.4

9 Estimating concrete for a job.
F. Absolute volume method. $       Total volume of concrete per sack cement = cu. ft. $       Cement = 1 (200/5.43) = 36.8 or 37 sacks $       Fine aggregate = 2 2 (200/5.43) = 92.1 or 93 cu. ft. $       Coarse aggregate = 4 (200/5.43) = or 148 cu. ft. Water to add = 7-5/8=6 3/8 gallons per batch

10 Estimating concrete for a job.
Changing the thickness in inches to fractions and decimal parts of a foot. For calculating quantities of concrete use the following table. Inches Fractional Part of Foot Decimal Part of Foot or 1/3 .33 5 5/ 6 6/12 or 7 7/ or 2/3 .67 10 10/12 or 5/6 .83

11 CONCRETE WEIGHTS AND MEASURES
1 Sack of Cement = 94 pounds = 1 Cubic Foot 1 Gallon of Water = 8.3 pounds 7.5 Gallons of Water = 1 Cubic Foot 1 Cubic Yard = 27 Cubic Feet 1 Cubic Foot of Sand Weighs About 100 Pounds

12 PROBLEM: How many square feet will a cubic yard of concrete cover if it is placed 4 inches thick?

13 There are 27 Cubic Feet in 1 Cubic Yard
Each Cubic Foot May Be Divided Into Three Volumes 4 Inches Deep and 1 Foot Square

14 THE CONCRETE MIX YIELDS OF CONCRETE
1. Rule of Thumb: Yield Equals 60 Percent of Volume 2. Absolute Volume Cement 47% Solids Sand 60% Solids Gravel 55% Solids Water 100% Solids

15 WHAT WILL A 1 : 2 : 3 - 6 GALLON MIX YIELD?
-ABSOLUTE VOLUME FT3 X % SOLIDS = FT3 Cement ______ 47 ______ Sand ______ 60 ______ Gravel ______ 55 ______ Water ______ ______ TOTAL YIELD (FT3) ______ (YARD3) ______ MIXES ______ YARD3

16 HOW MANY BAGS OF CEMENT ARE NEEDED TO MIX 1 CUBIC YARD OF CONCRETE USING A 1 : 2 : 3 - 6 GALLON MIX?
(Rule of thumb) Yield =_______ YD3 = FT3/MIX 27 FT3/YARD3 1 CUBIC YARD = _______1 BAG MIXES YARD3/MIX USE________BAGS OF CEMENT

17 WHAT WILL A 1 : 2 : 3 - 6 GAL. MIX YIELD?
FT3 Cement ________ Sand ________ Gravel ________ Water ________ Total ________ FT3 x 60% ________ FT3 Yard3 ________ Mix Mixes ________ Yard3 CALCULATED BY THE RULE OF THUMB


Download ppt "Estimating Concrete Construction and Material Cost"

Similar presentations


Ads by Google