Phase-A close-out why do we need it ? Phase-A products messages structure of report timeline Andy Lawrence MSSL June 2002.

Similar presentations


Presentation on theme: "Phase-A close-out why do we need it ? Phase-A products messages structure of report timeline Andy Lawrence MSSL June 2002."— Presentation transcript:

1 Phase-A close-out why do we need it ? Phase-A products messages structure of report timeline Andy Lawrence MSSL June 2002

2 why do we need a formal close-out ? show the money was well spent –must have something concrete to show inform/educate community –astro and e-Science produce "Bible" for Phase-B –record key decisions and reasons help partner projects –position ourselves internationally Andy Lawrence MSSL June 2002

3 Phase-A products The Architecture Collection of science problems and use-cases Collection of s/w products –VOtable –demo sw Written report –including Phase-B plan Andy Lawrence MSSL June 2002

4 Phase-A report physical book –c.f. ESA "red book" single portable file on-line suite of web pages should be formally released and widely circulated Andy Lawrence MSSL June 2002

5 messages we did what we said we would we now have a clearly defined project we are on top of this technologically this was a lot of work this work was of significance for astronomy and for e-science we are well placed internationally Andy Lawrence MSSL June 2002

6 timing Aug 1st A.O.C. –draft Phase A report – final Phase B request –money released Oct 15th G.S.C. –final Phase A report –feedback, congratulations... Nov 1strelease Andy Lawrence MSSL June 2002

7 report structure (1) Vision documentAL leads (2) Short narrative summaryTL leads (3) Science Requirements summaryNAW leads (4) Architecture overviewTL leads (5) Proto-VO market survey reportCGP leads (6) Grid technology assessment reportGTR leads (7) Datamining technology reportCGP leads (8) Pilot Programme reportsBM leads (9) Financial and Management reportTL leads (10) Phase B planTL leads workplan deliverables milestones/Gantt chart management plan personnel plan budget

8 deadlines Andy Lawrence MSSL June 2002 pre-MSSLAGLI discussion Jun 26Consortium meeting agree principles and approx contents agree responsibilities Jul 7first drafts Jul 15prelim Phase A report to AOC Jul 30AOC meets Oct 1full Phase A report to GSC Oct 15GSC meets Nov 1release report

9 April 2001 "one year goals"  Phase B plan  Science Requirements Document including set of example use cases  Functional Requirements Document  Functionality Market Survey Report  Agreed division of labour with international partners  Working datagrid including demonstration of multi-site browsing and database searching  Federation of databases : SOHO and Yohkoh SuperCOSMOS, SDSS and INT-WFC XMM and Chandra CLUSTER and EISCAT MERLIN and VLA  Preliminary visualisation tool  Preliminary database management system


Download ppt "Phase-A close-out why do we need it ? Phase-A products messages structure of report timeline Andy Lawrence MSSL June 2002."