Project Management Requirements Prof. Ralph Locurcio, PE Dr. Troy Nguyen, PE
2
Project 1 – Prepare proposal – Fall Semester Purpose is to win the project Proposal must state why your team is best Must include a Project Management Plan in the proposal Must include your proposed fee Project 2 – Construct the project – Spring Semester Verify the proposal @ 5% stage Construction phases @ 15, 50, 95, 100% Develop project details & construction drawings Manage & report on status@15, 50, 95,100% Integrate all elements into unified project Prepare display for Design Showcase in April Estimate cost of construction @ 15, 50, 95,100% Prepare and include a construction schedule Turn in written report
3
1.Title Page – follow instructions 2.Table of Contents – separate tab for each section 3.Introduction Problem Statement, Background & Scope of Work - what’s included & what’s not Discussion of Key Elements, Project Sketch – what is it, geometry Team Organization – who will do it 4. Project Management Plan Work Breakdown Structure & Project Budget Project Flow Diagram – flow of design tasks over time (Draft-1) Design Schedule (MS Project) – (Draft-2) Construction Cost Estimate – cost to actually build the project Conceptual in Proposal, 5% & 15% design Detailed at 50%, 95% & 100% in Design-2 Construction schedule at 50% – when project will be built
4
6.Project Sketch & Layout Shows boundaries and major features Sketch adds “proposed” size & features All team members should participate in these drawings 7.Design Investigation Report Written Technical Report – consult with advisor Include such items as: Problem(s) to be solved in the design Logic of size of key features Options considered; cite the pros & cons of each Applicable codes, ordinances or criteria that will control the project Cite all technical information to be used Concept decision – what engineering design method will be used and why Constraints – cite any political, environmental or physical limitations 8. Appendices & List of References
5
They enable you to be proactive rather than reactive…
6
Project Flow Diagram your road map/GPS Project Schedule your speedometer Project Budget your fuel gauge
10
Don’t forget To update duration At each % stage!!! WBS
11
Don’t forget To show totals At each % stage!!! Don’t forget To update duration At each % stage!!! Budget
13
Conceptual Construction Cost Based on historical data Itemize components. Use cost per SF or unit pricing data Data from similar project Be sure to update for location & timing
14
Detailed Construction Cost – 50%, 95%, 100% Due in Project-2 reports Based on actual data Itemize all components More detail as design is completed Obtain pricing for elements online, RS Means, other. Include all cost elements: materials, labor, logistics See template; all use same format Be sure to summarize cost of entire project Should be 90-95% accurate
16
http://my.fit.edu/~locurcio/05-CON 4091-Const Capstone Slides & Sample documents located at: