1 Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

2 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 2 Abstract Isolde today Hie-Isolde – The Energy upgrade –Planning –Civil Engineering, Cryogenics and Ventilation –Superconducting Linac and Beam Transfer Line User requirements? Impact on Isolde & REX operation User facilities ( under discussion) Future projects

3 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 3 Isolde Today

4 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 4 Isolde Today Target Zone

5 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 5 Isolde Today Separator zones GPS and HRS Separator

6 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 6 Isolde Today Experimental hall: Beam delivery

7 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 7 Isolde Today REX post-accelerating Linac Miniball experiment REX post-accelerating Linac

8 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 8 From Isolde to Hie-Isolde Step by Step

9 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 9 Hie-Isolde Planning A simplified presentation of the different stages: -What is the impact on operations? Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4 201120122013201420152016 Civil Main services Cryo CM 1&2 CM 3&4 5.5MeV/u 10MeV/u Beam Transfer Line CM 5&6

10 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 10 Civil Engineering Construction starting date: June 2011

11 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 11 Civil Engineering Removal of the transport hangar

12 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 12 Civil Engineering Terrain flattening

13 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 13 Civil Engineering New SAS September 2011

14 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 14 Civil Engineering Move of the controlled access September 2011

15 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 15 Civil Engineering Compressor Building Start end September 2011

16 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 16 Civil Engineering Cold Box Building Civil Engineering finished by July 2012

17 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 17 Main Services Electrical systems, Cooling & Ventilation

18 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 18 Electrical systems: July 2012 – March 2013 Cooling & Ventilation: Aug 2012 – March 2013 Main Services

19 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling Ventil units 19 Cooling & Ventilation

20 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 20 Cooling & Ventilation

21 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling Ventilation unit Cooling unit 21 Cooling & Ventilation

22 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling Cooling units 22 Cooling & Ventilation

23 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling Cryo equipment 23 Cryogenics Compressors: April 2013 – October 2013 Cold Box & Cryo-line: Jan 2014 – June 2014

24 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 24 Hie-Isolde New controlled access point

25 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 25 Hie-Isolde

26 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 26 Hie-Isolde

27 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 27 Hie-Isolde

28 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 28 SC Linac Cutting walls & install tunnel: long 2013 shutdown Cold Line: January 2014 – June 2014 Allowing a normal 2012 REX / Miniball run

29 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 29 Modular installation Cryo Modules 1 & 2: July 2014 – Oct 2014 REX physics at 5.5MeV/u for 2015 First beam at 5.5MeV/u autumn 2014 High β Low β 1 2 3 4 5 6

30 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 30 Cryo Modules 3 & 4: January - April 2016 Modular installation High β Low β 1 2 3 4 5 6 Final Energy 10MeV/u Cryo Modules 5 & 6: January - April 2017

31 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 31 Hie-Isolde SC Linac 5.5MeV/u by the autumn of 2014 First 10MeV/u by April 2016 Hie-Isolde SC Linac:

32 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 32 Beam Transfer Line

33 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 33 Beam Transfer Line Straight line with 2 branches – July 2013 - April 2014 Miniball move: Oct 2013 – April 2014 Miniball Actar / Helios Miniball Beam diagnostics Stage 1:

34 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 34 Beam Transfer Line The bend Spectrometer installation and 2nd Miniball move Miniball Spectrometer Actar / Helios Miniball Stage 2: TSR TSR and beyond.. Stage 3:

35 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 35 User Requirements Requirements for the experiments Info needed on: Power consumption Cooling & ventilation Cryogenics Alignment & spacing (nr of racks) Sensitivity to radiation, temp & vibrations Transport requirements

36 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 36 Isolde & REX Operations long shutdown 2013Lin4 major sdsd CM1&2 Isolde & REX Operations: ///// shutdownIsolde & REX perturbationsREX stop Main serv. Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4 201120122013201420152016 Civil Main services Cryo CM 1&2 CM 3&4 5.5MeV/u 10MeV/u Beam Transfer Line CM 5&6 Jan 2013 Aug 2014

37 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 37 User Facilities 1. Increasing the surface of the Solid State Lab in building B.115: For RP safety reasons all solid state activities will be moved from B.275 to B.115 This will suppress the existing workshop in B.115 and courtyard between B.115 and B.601 2. Replace the existing building 507 by a new full concrete building : Ground floor (only accessible from within the surveyed area): - Labs and workshop First floor (accessible from outside the surveyed area): - Data Acquisition rooms - Visitor Centre - Kitchen Long shutdown 2013? under discussion

38 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 38 Present situation (ground floor Jura side): Control room User Facilities

39 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 39 Solid State Lab 115 1. Increasing the surface of the Solid State Lab in B.115: Control room

40 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 40 Replace building 507 Control room 2. Replacing the existing building 507 by a new building - Ground floor (only accessible from within the surveyed area):

41 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 41 Control room 2. Replacing the existing building 507 by a new building - First floor (accessible from outside the surveyed area): Replace building 507

42 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 42 TSR @ Hie-Isolde TSR Max Planck Institute Heidelberg TSR@HIE-ISOLDE LOI submitted Jan 2011 (K. Blaum, Y. Litvinov) Future

43 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 43 TSR @ Hie-Isolde Would the TSR fit? No. CH F But could be an option for additional beamlines

44 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 44 TSR @ Hie-Isolde

45 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 45 TSR @ Hie-Isolde Possible TSR installation above the CERN cable-tunnel. Tilted beamline coming up from the machine.

46 HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 46 Acknowledgement EN/HDO: YACINE KADI, BE/RF: MATTEO PASINI GS/SE: DANIEL PARCHET, ELISEO PEREZ-DUENAS EN/CV: PAUL PEPINSTER, BENOIT BELLIN-CROYAT EN/EL: RENE NECCA TE/CRG: NICOLAS DELRUELLE, JOS METSELAAR EN/STI: ANA-PAULA BERNARDES, RICHARD CATHERALL EN/MEF: STEPHANE MARIDOR GS/DI: CYRILLE BEDEL TE/MSC: YANN LECLERCQ