Freeway Planning Process Michelle Bitner Project Manager Kern Council of Governments.

Similar presentations


Presentation on theme: "Freeway Planning Process Michelle Bitner Project Manager Kern Council of Governments."— Presentation transcript:

1 Freeway Planning Process Michelle Bitner Project Manager Kern Council of Governments

2 Project Development Procedures Manual Available on the Caltrans website: http://www.dot.ca.gov/

3 Planning Planning begins long before project development A study identifies the transportation system problem/need Defines the purpose and need Planning concept/ scope

4 Plan Line Designation of Route Local entity process: city/county and State Corridor study or MIS

5 Funding/Programming RTP STIP Conformity Analysis

6 Project Study Report PSR – 1 year to complete Determines project alternatives Gathers all needed preliminary data

7 Milestones Detailed Environmental Studies and Engineering Studies – 4 years Project Design – 1 year ROW purchase – 1 to 2 years Construction – 1 ½ - 2 years

8 Metropolitan Bakersfield Transportation Systems Study Preliminary Engineering Studies Alternatives Development Evaluation of Candidate Alternatives Fatal Flaw Analysis Define Feasible Alternatives

9 Metropolitan Bakersfield Transportation Systems Study Preliminary Environmental Studies Identify Right of Way Needs Construction Cost Estimates PSRs