Freeway Planning Process Michelle Bitner Project Manager Kern Council of Governments
2
Project Development Procedures Manual Available on the Caltrans website: http://www.dot.ca.gov/
3
Planning Planning begins long before project development A study identifies the transportation system problem/need Defines the purpose and need Planning concept/ scope
4
Plan Line Designation of Route Local entity process: city/county and State Corridor study or MIS
5
Funding/Programming RTP STIP Conformity Analysis
6
Project Study Report PSR – 1 year to complete Determines project alternatives Gathers all needed preliminary data
7
Milestones Detailed Environmental Studies and Engineering Studies – 4 years Project Design – 1 year ROW purchase – 1 to 2 years Construction – 1 ½ - 2 years
8
Metropolitan Bakersfield Transportation Systems Study Preliminary Engineering Studies Alternatives Development Evaluation of Candidate Alternatives Fatal Flaw Analysis Define Feasible Alternatives
9
Metropolitan Bakersfield Transportation Systems Study Preliminary Environmental Studies Identify Right of Way Needs Construction Cost Estimates PSRs