ECE 477 DESIGN REVIEW TEAM 14 SPRING 2010
2
Project Overview Target Audience: Amateur Musicians Obtain a “Guitar Tab” format of music View Tabs on LCD and export via SD Card SD Card contains.txt file to be viewed/shared/printed
3
Outline Project overview Project-specific success criteria Block diagram Component selection rationale Packaging design Schematic and theory of operation PCB layout Software design/development status Project completion timeline Questions / discussion
4
Project-Specific Success Criteria An ability to capture sound from a guitar and perform an FFT on the samples An ability to convert an arbitrary set of samples into a set of guitar notes An ability to export tabbed guitar music to a removable digital media text file. An ability to interact with the user via LCD Screen and Pushbuttons Allow exportation of recorded song as MIDI OR An ability to interactively guide guitar tuning
5
Block Diagram
6
Component Selection Rationale μ C: SHARC 21262 DSP with FFT Capabilities Interface w/ peripherals Cost ADC: TLV2541 12 Bit resolution Sufficient Sample Rate SPI
7
Component Selection Rationale Filter: MAX7404 Low Pass Adjustable Freq. Corner LCD: CFAG24064A-FTI-TZ 8 Rows Large display (7” x 2.56”) RAM: CY7C1069AV33 10 ns Parallel interface 2 MB SRAM
8
Packaging Design
9
Schematic/Theory of Operation OVERALL
10
Schematic/Theory of Operation LCD
11
Schematic/Theory of Operation POWER
12
Schematic/Theory of Operation AUDIO INPUT
13
Schematic/Theory of Operation SRAM
14
PCB Layout
16
Software Design/Development Status Accomplished so far: Sound analysis proof of concept (MATLAB) Preliminary work with LCD and SD Card Left for Completion: Port Sound Analysis to μ C Interface with Peripherals Implement Pushbutton controls and menus
17
Project Completion Timeline WEEK #: END DATE GOALS FOR END OF WEEK WEEK 9: MARCH 12 th Final PCB and Schematic, Proof of Parts WEEK 10: MARCH 19 th Matlab Note Analysis Complete, Homeworks Revised WEEK 11: MARCH 26 th Software Design Narrative WEEK 12: APRIL 2 nd Patent Liability, Packaging Prototype Complete WEEK 13: APRIL 9 th Reliability and Safety, Peripherals Working WEEK 14: APRIL 16 th Ethical and Safety Analysis, Finish Note Analysis on Micro WEEK 15: APRIL 23 rd User Manual, Live Testing WEEK 16: APRIL 30 th Software and Hardware Working, Poster Complete WEEK 17: MAY 3 rd Final Report