Eco Sustainable Solutions Limited Piddlehinton AD Facility
2
AD Process – “The Concrete Cow”
3
Piddlehinton AD Facility Regulatory Framework Bespoke Permit – EPR/FP3692SU – 12/2010 Planning Permission – 1/D/2008/0989 – 6/2010 ABPR Validation – 11/445/0041/ABP/CMP – 4/2012
4
Piddlehinton AD Facility Site Civils 1 Site Cleared Made Ground Removed Site Fully Lined
5
Piddlehinton AD Facility Site Civils 2 Reception / Compound Area Digester and Tank Bases
6
Piddlehinton AD Facility AD Plant 1 Digester Construction Tank Construction
7
Piddlehinton AD Facility AD Plant 2 Site Pipe Work Site Control System
8
Piddlehinton AD Facility AD Plant 3 Site CHP Unit & Flare Stack Gas Conditioning
9
Piddlehinton AD Facility AD Plant 4 Pasteurisation Plant End Storage Tank
10
Piddlehinton AD Facility Reception Barn 1 Reception Barn Water System
11
Piddlehinton AD Facility Reception Barn 2 Biofilter system Clearance Should be Sufficient...
12
Piddlehinton AD Facility Plant Process 1 Waste Discharge Waste Processing & Blending
13
Piddlehinton AD Facility Plant Process 2 Digestion Power Generation
14
Piddlehinton AD Facility Plant Process 3 Pasteurisation Storage and Discharge Field Injection
15
Piddlehinton AD Facility Issues So Far... Construction Contracts Health & Safety Management Ground Conditions Budget Over Runs Weather Grid Connection German / English Translations