Silica Fume Inspection
2
Surface Preparation Initial Clean all repair areas by sandblasting
Clean reinforcing and repair Final Clean entire surface by air blasting Flush with water and keep wet for 2hrs before placement Right before placement Blow out water puddles with compressed air
3
Placing 45-80 deg Evap rate not > 0.10
Brush slurry out in front of lay down using the paste portion and removing aggregate larger than #4
4
Finishing Vibrate and Rake to ¼” above final grade Vibrate end of deck
bulkheads repair areas curb lines Burlap drag Apply evaporation retardant
5
Why Evaporation Retardant ?
6
Plastic Shrinkage Cracking
Evaporation Rate Exceeds Bleed Rate High Air & Concrete Temps Low Humidity High Winds
7
Tining Control timing to avoid tearing of surface
Grooves from an 1/8”-3/16” deep No overlap
8
Curing Two applications of PAMS curing compound
When set cover with wet burlap and poly sheeting 4 days
9
Keys to Success Prevent Premature Moisture Loss Night-time placements
Fogging Applications Use of Evaporation Retarder Moist Cure blankets
10
Research Pull-off Test ASTM C 1583 Restrained Ring Test ASTM C 1581
Length Change Prisms ASTM C 157
11
Future Possibilities ? Based on Research conclusions/recommendations
Gradation changes Cementitious content Requiring fogging SRA’s Requiring seals or epoxy overlays
12
Questions?