Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling.

Similar presentations


Presentation on theme: "Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling."— Presentation transcript:

1 Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling

2 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 2 History: summer 2011

3 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 2 m Decoupe murPlateforme prolongee Courtesy: Stephane Maridor Maximize space on floor 3

4 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 4.1m 2 m Courtesy: Stephane Maridor 4 All racks on platform CV says NO... Cooling restrictions

5 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 5 Hall 170 ventilation systems platform wall 1 st extension 2 nd extension

6 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 6 platform wall 1 st extension 2 nd extension Hall 170 ventilation systems

7 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 7 Max heat dissipation platform wall 1 st extension 2 nd extension Max 70kW 100kW ? Max 45kW

8 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling Rack distribution

9 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 6x3 RACKS “PC” 500A DIPOLE 45˚ 20 RACKS “PC” QUAD/STEERER 2x2 RACKS “PC” 250A DIPOLE 22.5˚ 3 spare RACKS dipole 5 VAC racks 2 BI racks(+3) 4 WIC racks Electric. Dist. racks Rack distribution

10 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling Cable distribution All EPC, BI and VAC cabling installed in stage 1 before experiments in place – cables for stage 2(b) rolled and stored on the hall floor

11 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling All EPC, BI and VAC cabling installed in stage 1 before experiments in place – cables for stage 2(b) rolled and stored on the hall floor Cable distribution

12 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 12 Minimizing floor occupancy 2x2 RACKS “PC” 250A DIPOLE 22.5˚ 3 spare RACKS dipole 6x3 RACKS “PC” 500A (+1 cabling rack) DIPOLE 45˚

13 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 13 Minimizing floor occupancy

14 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 14 Heat to air dissipation 6x3 RACKS “PC” 500A (+1 cabling rack) DIPOLE 45˚ 20 RACKS QUAD/STEERER 2x2 RACKS “PC” 250A DIPOLE 22.5˚ 3 spare RACKS dipole 5 VAC racks 2 BI racks(+3) 4 WIC racks Max 4x12.5=50kW Max 29kW Max 12.5kW Max 2x4kW Max 5kW or Platform: Max 46.5kW to air (if spare runs for a 44.5 ˚ magnet) Floor: Max 50kW to air (if bend running at max) – leaving 20kW for experiments

15 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 15 Alignment platform

16 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 16 Nicole experiment?

17 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 17 Acknowledgement EN/MEF: STEPHANE MARIDOR, ELEFTHERIOS ZOGRAFOS GS/SE: DANIEL PARCHET, ELISEO PEREZ-DUENAS BE/OP: DIDIER VOULOT EN/HDO: YACINE KADI EN/CV: PAUL PEPINSTER, BENOIT LACARELLE EN/EL: RENE NECCA EN/STI: RICHARD CATHERALL, ANA-PAULA BERNARDES TE/ABT: BRENNAN GODDARD BE/RF: MATHEW FRASER TE/EPC: MICHELE MARTINO

18 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 18 Extra slides

19 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling STAGE 1

20 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling STAGE 2a

21 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling STAGE 2b

22 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 1580 892 1344

23 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

24

25

26 26 Hie-Isolde Planning Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4 201120122013201420152016 Civil Main services Cryo CM 1&2 CM 3&4 5.5MeV/u 10MeV/u Beam Transfer Line CM 5&6 17 Dec 2012 - Q3 2014 sd CM1&2 Isolde & REX Ops shutdown LS1 Cryo Mod 1 & 2 install (Isolde normal operations) Timeline: sd Ventilation Demi water Electrical syst.s Start LS1 3 dec 2012 17 End LS1:Start Low E physics Commissioning (Isolde normal operations) Commissioning during shutdown (EBIS beam) Beam commissioning Nov. + 5 months Cryo only ready Feb 2014 Start-up 2015 HIE physics at 5.5MeV/u

27 Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 27 Commissioning planning


Download ppt "Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling."