Presentation is loading. Please wait.

Presentation is loading. Please wait.

Resource analysis 1 Project management (seminar).

Similar presentations


Presentation on theme: "Resource analysis 1 Project management (seminar)."— Presentation transcript:

1 Resource analysis 1 Project management (seminar)

2 Introduction Sometimes one or more resources (especially skilled workers) are equally or more important than time. According to priority, there are: – time-limited and – resource-limited projects. Priority can change over time but it is not wise to have double priorities. Basic tools came from production engineering: loading (resource allocation)

3 Resources Definition: anything that is scarce and required for any activity in the project. Resources are constraints for the project. Resources can be: – Non-storable: has to be renewed for each period e.g. work – Storable: depleted only by usage (remains available if not used) e.g. money The most common resource typology, the 4Ms: – Men – Machines – Money (cost) – Material – Other

4 Loading (resource allocation) The assignment of work to an worker, machine or unit (generally: to a workstation) in time. A workstation can be: – underloaded (load < capacity) – fully loaded (load = capacity) – overloaded (load > capacity) Fully loading is nearly impossible to reach except in flow production. Underloading is the most common, because it respects time. Overloading leads to be late.

5 Defining resources for projects SOW WBS Task list – Resource needs given in resource-hours (e.g. man-hour, machine-hour) – Two forms of resource specification: Rate-constant (can be changed to a constant function/patter): constant usage rate defines the duration, too Total constant: to finish the activity

6 What to do with non-linear duration-resource functions? Use a computer Focus on quasi-linear parts of the functions

7 Capacity Be realistic: – Usual efficiency – Estimated absenteeism, sickness, holidays – Existing commitments – Ancillary tasks and their resource needs – Any additional constraints (like methodology) and limitations (like work contracts) Also calculate with the possibilities (cost, time, trade-offs) to increase capacity

8 Defining resources for projects 2 SOW WBS Task list Logical connections (PNT) Gantt chart and histogram Levelling

9 Using the bar chart Set up and analyse the network – Assign the resource data to the activities Draw the Gantt chart – Aggregate each resource time period by time period throughout the total project Cumulating (Summation or S Curve): Use levelling the load for optimization

10 Network with single resource data START (0) 0 00 0 0 0 0 e (1) 10 130 10 13 3 0 d (2) 2 73 5 10 5 3 c (3) 2 100 2 8 0 b (4) 0 55 5 10 5 5 a (1) 0 20 0 2 2 0 FINISH (0) 13 0 0 0

11 Aggregation with a bar chart (single resource, earliest start) activity12345678910111213 a11 b44444 c33333333 d22222 e111 Res. aggr. 5599955333111 Cum. res. 5101928374247505356575859 Resource units 11 10 9 8 7 6 5 4 3 2 1 123456789 111213 Time

12 Aggregation with a bar chart (single resource, latest start) activity12345678910111213 a11 b44444 c33333333 d22222 e111 Res. aggr. 1133399999111 Cum. res. 1258112029384756575859 Resource units 11 10 9 8 7 6 5 4 3 2 1 123456789 111213 Time

13 The S Curve analysis The minimum slope level is the less ‘critical’ from the viewpoint of availability

14 S Curve of the example

15 Scheduling with constraints Three approaches: Allocation: Activities are scheduled so that an initially defined limit of resources or time is not exceeded. Levelling: A previously generated schedule must be given. Then it levels out the peaks and troughs without changing the TPT. Smoothing: A start time, a TPT and resource priorities.

16 Other possibilities Alternative resources Alternative methods Alternative sequences (if there is no technical dependency)

17 Levelling the load We must have a starting allocation of activities over time and a resource constraint (previous example). Resource units 11 10 9 8 7 6 5 4 3 2 1 123456789 111213 Time Trying to keep the original TPT unchanged means that critical activities should not be moved. Thus try to move activities with free float. Resource units 11 10 9 8 7 6 5 4 3 2 1 123456789 111213 Time

18 Solution There are only 2 activities with free float: b & d Which one to move and to where? Moving activity d 3 days in advance is eliminating the peak. Resource units 11 10 9 8 7 6 5 4 3 2 1 123456789 111213 Time

19 activity12345678910111213 a11 b44444 c33333333 d --- 22222 e111 Res. aggr. 55 777 55 555 111 Cum. res. 5101724313641465156575859

20 S Curve

21 Effect of levelling New „activity”: waiting for the resource (it is a lag, not a true activity) START (0) 0 00 0 0 0 0 e (1) 10 130 10 13 3 0 d (2) 5 100 5 5 0 c (3) 2 100 2 8 0 b (4) 0 50 0 5 5 0 a (1) 0 20 0 2 2 0 FINISH (0) 13 0 0 0 Changes: new precedence relationship, floats, late start and finish times

22 Reading Lockyer – Gordon (2005): Chapter 17

23 Thanks for your attention


Download ppt "Resource analysis 1 Project management (seminar)."

Similar presentations


Ads by Google