Parallel Ops / Go-Live Checkpoint Weekly Update – Friday Meeting December 20, 2013
2
Agenda Look-Ahead: 9:00A – 9:20A Updated IDT Schedule and Conditions, 9:00 – 9:10A Updated Dec and Jan Friday Meetings / Look-Ahead, 9:10-9:15A Announcements, 9:15 – 9:20A IDT Debrief: 9:20A – 9:50A IDT Report Review: IDT 12/10 and IDT 12/12, 9:20-9:40A IDT 12/15 and IDT 12/17 Preliminary Debrief, slides for reference IDT 12/19 Preliminary Debrief, 9:40 - 9:50A Analysis, Announcements, and Updates: 9:50A – 10:10A Scenario Analysis, 9:50 – 10:00A Updates, 10:00 – 10:10A Settlements Update: 10:10A – 10:15A 2
3
IDT Schedule and Conditions page 1 of 2 3 Ginny Watson IDT DateIDT TimeConditionNotes Various IDTs Follow Resource Online If you have a Resource already planning on coming online during a regularly scheduled IDT, please let us know via RMS.RMS 1/7/143:30P-1:30A 8hr IDT begins at 4:30P, crosses midnight *changed from 2:30P – 12:30A (IDT at 3:30P) Crosses Midnight Regulation Pre- Selection / Co- Optimize Regulation SPP will exercise Regulation pre-selection during the 01/07 IDT. This will run through normal ID-RUC regulation pre-selection, allow BA Operators to change Resources from certain regulation, etc. 1/9/148:30A-12:30P 2hr IDT begins at 9:30A ICCP Failover SPP has requested that an MP perform an ICCP failover in the middle of the January 9th IDT. This was a request from the CWG for a real world condition. SPP will coordinate with individual MP.
4
IDT Schedule and Conditions page 2 of 2 4 IDT DateIDT TimesConditionsNotes 1/10/146:30A-4:30P 8hr IDT begins at 7:30A *changed from 5:30A – 3:30P (IDT at 6:30A) Simple Failover Failover will be a standard model upload failover and primary systems will not be down for but a few minutes. The secondary system will be up and providing setpoints along with the XML signals. Loss of ICCP Disable all outbound data from both the primary and secondary ICCP systems creating a complete loss of all setpoints for all MPs for 15-30 min. MPs will follow XML instructions. SPP BA Operators exercise procedures for selecting and communicating Reg movement to resources. The loss of ICCP data will only be simulated from SPP to members. 1/21/144:30P-8:30P 2hr IDT begins at 5:30P Tieline Drop SPP loses select tie-line measurements. SPP will simulate the loss of real-time data with significant tie- line data providers. MPs will not need to take any action; this is an internal process for our operators. SPP will lose generator real-time and tie-line data EDR Testing with specific MPs will occur during this IDT 1/27/144:30P-10:30P 4hr IDT begins at 5:30P Ginny Watson
5
IDT Schedule and Conditions page 2 of 2 5 IDT DateIDT TimesConditionsNotes 1/30/14 – No IDT, moved to 2/25 2/25/148:30A-12:30P 2hr IDT begins at 9:30A *moved from Jan 30 to Feb 25 2/28/147:00P 4hr IDT begins at 8:00P, cutover to Go-Live *newly added Cutover for March 1 Go-Live Ginny Watson
6
December and January Fri Meetings: 6 Fri Dec 27: No Meeting Fri Jan 3: No Meeting Wed Jan 8: Parallel Ops / Go Live Checkpoint Fri Jan 10: No Meeting (Integrated Deployment Test) Fri Jan 17: Regular Fri Meeting: Parallel Ops / Go Live Checkpoint Fri Jan 24: Regular Fri Meeting: Parallel Ops / Go Live Checkpoint Fri Jan 31: Regular Fri Meeting: Parallel Ops / Go Live Checkpoint Ginny Watson
7
Look-Ahead: Dec 22 – Jan 4 7 Parallel Ops Calendar Parallel Ops Calendar on spp.org spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents Settlements details on the Settlements CalendarSettlements Calendar marketplace.spp.org > Public > Settlements > Calendars Dec 22 – Dec 28 Schedule: Ramp Sharing Off Dec 22 – Dec 28 Tues Dec 24: SPP Holiday Wed Dec 25: SPP Holiday No Parallel Ops Meeting Friday Dec 27 Dec 29 – Jan 4 Schedule: Ramp Sharing On Mon Dec 30: R1.9 in PROD Wed Jan 1: SPP Holiday No Parallel Ops Meeting Friday Jan 3 Ginny Watson
8
Announcements 8 New job aid: “How to Clear Operating Reserve Products: A Checklist” “How to Clear Operating Reserve Products: A Checklist” spp.org > Training > Integrated Marketplace Training Page February 2014: Extended maintenance window SPP to perform needed maintenance on PROD environment while keeping available to members webMirroring off December 16 MP Participation status from Shari Brown Ginny Watson / Shari Brown
9
Regulation Selection Condition Currently during Integrated Deployment Tests (IDTs) MPs are bidding in their Regulation as Fixed for Resources carrying Regulation in EIS In order to fully test the Regulation selection processes, SPP would like to run an IDT with MPs offering in Regulation as they would in Production This allows SPP and MPs to test the processes and procedures surrounding the clearing and selection of Regulation during the IDT timeframe This will also allow the RTBM clearing engine to clear Regulation based on economics including impacts to constraints 9 Casey Cathey
10
Regulation Selection Condition Planned to occur during the IDT scheduled for 1/7/2014 MPs with Regulation qualified Resources will offer Up and Down Regulation to the market with appropriate prices – It is vitally important that MPs submit correct Eco limits and Regulation limits to fully exercise this condition SPP will exercise the normal Regulation selection process to select all Resources that will be eligible to clear Regulation in RTBM each hour and as necessary RTBM will then clear Regulation based upon the Offers submitted by participants and RTGEN will deploy based on these cleared Resources 10 Casey Cathey
11
11 Casey Cathey
12
12 Casey Cathey
13
13 Casey Cathey
14
14 Casey Cathey
15
Deltas from first 4 IDTs During the IDT SPP utilized offsets to account for Resources not following dispatch at the beginning of the test – Biasing the load with offsets requires more energy to be dispatched moving Resources into more expensive bands or less expensive bands depending on the direction of the offset There was a large difference on Dec 3 at 6:55 – SPP approved offset case of 80 MW Base case max LMP = $165 80 MW offset case max LMP = $850 – 150 MW offset case would have raised max LMP to $1,200 15 Casey Cathey
16
IDT 12/10 Report IDT reports posted to spp.org here 7 calendar days after each IDThere spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test IDT 12/12 Report IDT reports posted to spp.org here 7 calendar days after each IDThere spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test 16 For Reference Only
17
12-15-13 Deployment Test Debrief Overall the Seventh Deployment test was another success –BAs and MPs were on the call 60 min before IDT began. Thank you! Only 1 MP was missing –Ramp Sharing will be on for all three of the IDTs during the week of Dec 15 –Smooth transition into test; best entry to date ACE under control; SPP well within L10 Successful entry attributed to EIS and IM Resource Plans matching up well –Resource trip managed without calling a CRD event due to the high ACE prior to the trip Immediate recovery with Regulation; process worked properly –No big issues; overall, test managed and controlled well 17 For Reference Only
18
12-15-13 Deployment Test Debrief Though a “Success” - areas of concern/opportunities to improve –Start of test was delayed 1 hour due to one BA having issues with ICCP SPP delayed IDT start to ensure entry into test was smooth and stable Official 3 hour IDT 1:30P – 4:30P Official NERC Waiver Period 1:15P – 4:45P –2 CPS2 Violations Following the initial smooth transition into the test – experienced a high positive ACE for 40 minutes Not enough Ramp capability available Units on Reg that couldn’t perform as offered in SPP worked directly with a number of MPs who were off dispatch to remedy SPP finally able to cross ACE and the remainder of the test went smoothly –SPP followed up with MPs as normal business issues occurred CMODES Failed individual setpoints 18 For Reference Only
19
12-15-13 Deployment Test Debrief REMINDERS: –webMirroring off December 16 –IDT Call starts at 2:30A on December 17 19 For Reference Only
20
Set Points Details on the different set points that SPP provides via ICCP Target Base Point = 5 minute stepped energy only Set Point (4 second signal) = Stepped energy and deployed Operating Reserves Ramped Set Point (4 second signal) = Ramped Energy + Deployed Operating Reserves achievable but reset every 5 minutes 20 For Reference Only
21
Set Points 21 For Reference Only
22
12-17-13 Deployment Test Debrief Overall the Eighth Deployment test was a great success! –All BAs and a majority of MPs were on the call 60 min before IDT. Thank you! 7 MPs missing –Ramp Sharing on for all three of the IDTs during the week of Dec 15 –Smooth transition into test; another successful entry ACE under control; SPP well within L 10 –Resource came online during the 0400 hour; everything worked well –Overall, MPs did a better job following IM setpoints –Test managed and controlled well 22 For Reference Only
23
12-17-13 Deployment Test Debrief Though a “Success” - areas of concern/opportunities to improve –1 CPS2 Violation Following the smooth transition ACE dipped at the top of the 0400 hour due to: – SPP ramping in a lot of schedules ~700 MW NSI change » Ramp Reservation System is not limiting schedule changing; this will be different in Production – Wind Generation was dropping – Steep Load Growth Recovered quickly and came out of the interval in good shape – The entire remainder of 4 hour IDT went well –SPP continues to work directly with MPs who are off dispatch 23 For Reference Only
24
12-17-13 Deployment Test Debrief IDT Conditions – webMirroring off as of December 16 –Please make a better effort to get schedules in –SPP is handling through NSI offset MPs need to get schedules in so SPP doesn’t have to put in an offset and can test OATI system 24 For Reference Only
25
IDT Reminders 12/19 IDT Call starts at 5:30 AM, 2 hour IDT begins at 6:30 AM –Pseudo Tied In Resources An MP requested permission to test a Pseudo-Tied in Resource during the 12/19 deployment test. SPP had asked the MP not to include the Resource in deployment testing before 12/19 due to the pseudo-tied issue. –RSG Event First IDT with all RSG changes effective –Follow Resource Online Please remember to coordinate with SPP if you have a Resource coming online during an IDT An MP brought a large unit on during today’s test but did not coordinate with SPP operators – SPP was able to manage ACE but coordination woul dmake the process much easier. IDT 12/19 Debrief and Parallel Ops Friday Meeting 12/20 at 9:00 AM 25 For Reference Only
26
26 For Reference Only
27
12-19-13 Deployment Test Debrief Overall the Ninth Deployment test was a success –All BAs and a majority of MPs were on the call 60 min before IDT. Thank you! 3 MPs missing –Ramp Sharing on 100% for the Dec 19 IDT as SPP continues to gather data Ramp Sharing stayed on 100%; SPP did not move to 50% as announced on call –Another smooth transition into test –No CPS2 Violations –Overall, MPs did a better job following IM setpoints Small dispatch deltas; not in the same direction –Test managed and controlled well 27 Brian Strickland
28
12-19-13 Deployment Test Debrief Though a “Success” - areas of concern/opportunities to improve –705 interval solved but was not approved SPP is investigating cause –SPP worked directly with MPs who had issues with the Markets UI / API KIL #876: New issue logged after Markets UI and API issues some MPs experienced –SPP continues to work directly with MPs who are off dispatch 28 Brian Strickland Issue #Component Known Issue Log: Synopsis Severity 876 Markets UI Currently the Markets UI and API servers only allow 400 concurrent sessions. During IDT testing, users were receiving Internal System Errors when the maximum number of concurrent sessions was reached. To resolve this, the maximum number of concurrent connections needs to be increased to support Parallel Ops. Severity 2: High
29
12-19-13 Deployment Test Debrief IDT Conditions: Pseudo Tied In Resource and RSG Changes –Both 12/19 conditions successful with minor follow ups recorded 29 Brian Strickland
30
Non-functional Testing Scenario Results 30 *Scenario document on spp.org herehere spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents > Scenarios in Parallel Ops Planned Non-Functional Test Exercise terminated early on 12/13: RTBM solutions failed to solve after failing over to SPP’s secondary facility Failover exercise successful in that ALL but two systems failed over as expected During the simulated primary Chenal facility outage the secondary site was available and supported the following systems and applications: Expected Result: EMS is fully functioning with RTGEN for CBA Actual Result: EMS failed over correctly, functioned as expected Expected Result: ICCP is fully functioning and sending setpoints Actual Result: ICCP failed over correctly, functioned as expected Expect Result: Marketplace Portal User Interface and API available for data entry and retrieval Actual Result: Failed over correctly, functioned as expected. Users may have experienced brief intermittent connectivity while Chenal was taken offline. Expect Result: Web Services (RTO_SS) available Actual Result: Remained available, as expected Casey Cathey
31
Non-functional Testing Scenario Results 31 During the simulated primary Chenal facility outage the secondary site was available and supported the following systems and applications (continued): Expected Result: Market System is fully functioning and solving RTBM for approx. 1 hr Actual Result: RTBM missed intervals between 22:15 and 23:05 After this decision to fail back to Chenal, the first study was successful at 23:10 Expected Result: Email is available for sending and receiving communication Actual Result: Email was unavailable during the failover After the exercise was terminated, all systems and applications were restored successfully back to Chenal Follow-up tests will be conducted to validate corrections that have already been made to Email and Market systems. Planning team working to define and schedule next recommended Non-Functional Testing exercise during Parallel Ops Casey Cathey
32
Scenario 29 RSG Results 32 *Scenario document on spp.org herehere spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents > Scenarios in Parallel Ops Results Each RSG Member successfully submitted an RSS Event on 12/16 Area-to-Area Transfers from each event were sent from RSS through to MOS and where applied correctly in the studies (RTBM and RTGEN) Only issue observed was a minor refresh issue with the RSS Screen and that has been submitted for a fix Settlements portion will be reviewed next week by each RSG Member after the initial statement is available on 12/23 Casey Cathey
33
33 Summary – Scenarios in Parallel Ops: –4 Scenarios, 2 Partial Scenarios, Dispatch Simulator Test successful: Scenario 7 Must Offer pending Settlements results Scenario 28a Scenario 15 Commitment Mismatch Part 2 Scenario 24 Dispatch Simulator Test – Note: COP True-up “Off” will occur again for 2-3 days in January Scenario 13 DDR w/ Settlements Scenario 29 RSG pending Settlements results Summary – Retests Pending: –3 entire Scenario retests pending Scenario 11 scheduled for Jan 21 Scenario 31 BDR w/ Settlements to be retested Jan 14 Non-Functional Testing Scenario to be retested –10 individual retest requests pending Scenario Tracker as of Dec 19 Ginny Watson
34
Migration and Maintenance Report 34 Migration and Maintenance Report Migration and Maintenance Report posted to spp.org spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents Wendy Reynolds
35
35 Release Scorecard Release Scorecard posted to spp.org: spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents Release Scorecard Ginny Watson
36
Known Issues Log 36 Please review the Market Trials Known Issues Log on spp.org Market Trials Known Issues Log spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder Carrie Simpson Issue #Component Synopsis Severity 876 Markets UI Currently the Markets UI and API servers only allow 400 concurrent sessions. During IDT testing, users were receiving Internal System Errors when the maximum number of concurrent sessions was reached. To resolve this, the maximum number of concurrent connections needs to be increased to support Parallel Ops. Severity 2: High
37
Market Trials Useful Resources Integrated Marketplace Parallel Operations Project Documents spp.org > Integrated Marketplace > Market Trials > Parallel Operations Test> Integrated Marketplace Parallel Operations Project Documents Parallel Ops Presentations, Statistics, MP Meetings Folder Parallel Ops Reference Documents Folder Scenarios in Parallel Ops Folder > Scenarios Schedule Scenarios in Parallel Ops Folder Scenarios Schedule Parallel Ops Communication Plan Parallel Ops MP Guide Parallel Ops Calendar Known Issues Log Release Scorecard Migration Report Integrated Deployment Test (as part of Parallel Ops) spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test IDT MP Guide Parallel Ops Calendar Additional documents: Settlements Calendar marketplace.spp.org > Public > Settlements > Calendars Settlements Calendar Change Tracker spp.org > Integrated Marketplace > Marketplace Documents Change Tracker Integrated Marketplace Structured/Unstructured Test Project Documents spp.org > Integrated Marketplace > Market Trials > Structured / Unstructured Test> Integrated Marketplace Structured / Unstructured Test Project Documents 37
38
Market Trials Useful Resources Scheduling Information spp.org > Integrated Marketplace > Market Trials > Integrated Deployment Test Interchange Scheduling Reference Manual http://www.spp.org/publications/Interchange%20Scheduling%20Reference%20Manual%20Published%202-1-2013.doc MT Tagged Transactions and Tag Validation Criteria http://www.spp.org/section.asp?group=2802&pageID=27 Ramp Reservation User Guide http://www.spp.org/section.asp?group=2479&pageID=27 38
39
Settlements Cutover - January All January Operating Days will be processed using the December release (this is the release we will go live with on 3/1/2013). –SD 1/7 has been added to the days that may post late. The December release is scheduled to move into production around Jan 8 th. –Some days in early January may post late due to the timing of the migration of this release. Please see the highlighted section of the January calendar for details. 39 Brent Wilcox
40
Settlements Cutover - February Last statements (1/31 I) will be posted Feb 3 rd. –Please see highlighted section of February calendar for details Statements will remain on portal until noon on Feb 5 th Settlement system cutover begins Feb 6 th. Market Participants can start to submit their bilaterals on Feb 22 nd. –Thirty day window will not be followed in this instance. Meter windows will open on OD+1 (3/2/14). 40 Brent Wilcox