Asphalt Pavement Association of Indiana Annual Winter Conference Michael B. Cline Commissioner, INDOT December 14, 2010
2
State Highway Fund
3
Major Moves
4
Today 41 corridors complete 185 new centerline miles complete 2,800 preservation centerline miles complete 588 bridges rehabbed or replaced Nearly $5.7 billion invested in Major New and Preservation Indiana hasn’t borrowed money since 2004! Major Moves
5
Major Moves Update 84% of Major New projects on original schedule 2006 thru 2011 have been completed or under construction now 84% of Major New projects on original schedule 2006 thru 2011 have been completed or under construction now Status of Major Projects Status of Major Projects Est $ CN Open to Est $ CN Open to Miles % Let Cost (m) Traffic Miles % Let Cost (m) Traffic US 24 Fort to Port 11 100% $ 81 Sep 2012 I-80/94 Interchange - 100 187 Jul 2011 Accelerate 465 11 100 423 Dec 2011 Madison-Milton Bridge 1 100 104 Sep 2012 US 31 Plymouth to SB 20 67 233 Dec 2014 US 31 Kokomo 13 55 175 Dec 2013 I69 Evansville to Crane 67 50 700 Dec 2012 SR 25 Hoosier Heartland 36 41 377 Dec 2013 I-69 Crane to Bloomington 27 0 400 Dec 2014
6
I-69 Construction: 2008-2014 Sections 1-3: 67 miles Evansville to Crane 50% miles let CN Cost: $700M Open to traffic: 12/12 Section 4: 27 miles Crane to Bloomington 1 st letting: summer 2011 Est. CN Cost: $400M Open to traffic: 12/14 MPO Vote approved design and environmental Major Moves
7
Hoosier Heartland (SR 25) 36 miles 41% let Next letting: February 2011 Mainline, US 421 interchange Alternate Bid Final letting: 7/12 Open to traffic: 12/13 CN Cost: $377M Major Moves Carroll County line
8
US 31 Kokomo 13 miles 55% let Next letting: August 2011 SR 26 to US 35 Alternate Bid TBD Final letting: 7/12 Open to traffic: 12/13 CN Cost: $175M Major Moves New SB mainline looking north from CR 100S bridge
9
US 31 Plymouth to South Bend 20 miles 67% let Next letting: February 2011 SR 4 extension & interchange Asphalt Final letting: 4/13 Open to traffic: 12/14 CN Cost: $233M Major Moves New bridge two miles south of SR 4
10
US 31 Hamilton County 13 miles Next letting: February 2011 SR 38 interchange Alternate Bid Final letting: 2/17 Open to traffic: 2018 CN Cost: $436M Major Moves 146 th Street
11
Illiana P3
12
Ohio River Bridges Ohio River (IN Share) $1.1B KY/IN Bridge Authority – funding mechanism Target construction start date: August 2012 Partnerships
13
Pavement Preservation HMA Tonnage INDOT Contracts
14
Pavement Preservation HMA Lane Miles INDOT Contracts
15
Pavement Preservation Project Spending INDOT Contracts (Resurfacing, Restoration, Reconstruction, Replacement)
16
Pavement Preservation
17
INDOT
18
Thank You