Presentation is loading. Please wait.

Presentation is loading. Please wait.

CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.

Similar presentations


Presentation on theme: "CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in."— Presentation transcript:

1 CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in sections, AT/VAC, AB/CO, TS/IC, TS/SU groups for their support and collaboration 2006.01.25

2 GR, AT/ACR-cd 2 Contents QRL layout Installation »Main features »Present status »Schedule Operation  Reception tests »Schedule »Main results Conclusions

3 GR, AT/ACR-cd 3 QRL layout Tested part is marked in blue A G F E D C B H I A - Vacuum sub-sector “A” QRL is a continuous cryostat of ~3.2 km length no header (4 or 5) sectorisation  9 vacuum sub-sectors (A…I)  vacuum insulation separate from machine QRL elements in one sector ~ 38 service modules ~ 40 fixed point/vacuum barrier elements ~ 235 straight pipe elements ~ 10 steps/elbows ~ 1-2 cryogenic extensions

4 GR, AT/ACR-cd 4 QRL layout Sector 3-4 Sector 5-6 Pipe element Service module

5 GR, AT/ACR-cd 5 QRL sector installation Installation of ~ 700 external supports Positioning of ~ 325 elements Welding and testing of ~ 325 interconnections  > 2000 welds »~ 180 “O” type interconnections (1 butt-weld per header) »~ 75 “C” type interconnections (2 butt-welds per header) »~ 70 “A” type Interconnections (3 welds per header)

6 GR, AT/ACR-cd 6 QRL sector installation Overall installation: 6 teams Installation by sub-sectors Automatic welding for the inner headers »Nominal rate: 20 int./week »Achieved rate: 30 int./week Manual welding of the external sleeves »Nominal rate: 20 int./week »Achieved rate: 35 int./week NDT tests »Internal (video camera) and external visual control: 100% »Radiography tests: from 100 % to 10 % as a function of weld quality »Leak tightness tests: 100 % (each weld, each sub-sector, each sector) Head of the machine Tool for He leak test

7 GR, AT/ACR-cd 7 Status of the installation

8 GR, AT/ACR-cd 8 Schedule

9 GR, AT/ACR-cd 9 Reception tests QRL tests: »Sector 7-8, sub-sectors A and B: about 700 m »Sector 8-1, full sector: about 3200 m Tests »Pressure tests »Flushing of the circuits »Cooldown »Instrumentation commissioning »Heat inleak measurements »Warmup

10 GR, AT/ACR-cd 10 Reception test schedule

11 GR, AT/ACR-cd 11 Pressure test Sector 8-1

12 GR, AT/ACR-cd 12 Configuration for flushing and cool-down

13 GR, AT/ACR-cd 13 High-flow rate flushing with He Original colour ! New filter (8-1) Old filter (7-8, A-B)

14 GR, AT/ACR-cd 14 QRL layout for reception test

15 GR, AT/ACR-cd 15 Tests for the sector 8-1

16 GR, AT/ACR-cd 16 Cool-down Valve blockage by a “plastic film” coming from header B

17 GR, AT/ACR-cd 17 Thermometer validation Header C, SSA: 8 TT fully in accordance

18 GR, AT/ACR-cd 18 Heat inleak measurement Q B,C,D = (mD·hD+mB·hB) - mC·hC (indirect calculation of the mass-flow by using the heaters EH) Q EF = mF·(hFout-hFin) + mE ·(hEout-hEin) B, C and D E and F

19 GR, AT/ACR-cd 19 Results for headers E and F Boundary conditions »Insulation vacuum in the main envelope: 10 -6 mbar (8-1) 10 -5 mbar (7-8) »Headers E and F: 50-75 K »Headers C, D and B: 8-15 K [W]Sector 7-8Sector 8-1 Calculated24009850 Measured2250 +/- 1509000 +/- 400

20 GR, AT/ACR-cd 20 Results for headers C, B, D (sector 7-8, A and B) - without JR and without JC ~ 0.25 W/m - JC ~ 50 W  4.2 W/JC - JR ~ 70 W  1 W/m Measurement cross-checked with independent refrigerator input JC = jumper connection JR = junction region

21 GR, AT/ACR-cd 21 Results for headers C, B, D (sector 8-1) Boundary conditions »Insulation vacuum in the main envelope: 10 -6 mbar »Headers E and F: 50-75 K »Headers C, D and B: 8-15 K [W] B+C+DBCD Calculated 525260123142 Measured [+/- 30] 535270108157 Measurement cross-checked with independent refrigerator input Mass-flow cross-checked by using the valve opening QRL with JR and without JC

22 GR, AT/ACR-cd 22 Results for headers C, B, D (sector 8-1) - without JR and without JC ~ 0.16 W/m - JC ~ 90 W  2.4 W/JC - JR ~ 35 W  0.4 W/m

23 GR, AT/ACR-cd 23 Temperatures of the vacuum jacket

24 GR, AT/ACR-cd 24 Conclusions 1/2 Installation progresses well: »External support installation at 75 % »Element installation at 50 % Installation in the sectors 3-4 and 5-6 (JR excluded) meets the target rates At present the main concerns for the installation are: »delay for leak detection and repair »availability of singularities for the sector 1-2 (2 JR  18 elbows/steps) »installation of the QRL in UJ22 and UJ24 and possible interference with magnet transport: tooling for QRL installation shall allow the magnet transport Pressure tests successfully performed for sectors 7-8 (A+B), 8-1 and 4-5 (without the JR) Flushing of headers required and sufficient time shall be allocated

25 GR, AT/ACR-cd 25 Conclusions 2/2 Cold reception tests performed for sectors 7-8 (A and B) and 8-1 Successful thermo-mechanical validation of the QRL design Thermometer accuracy of about +/- 50 mK, much better than specification (+/- 1 K for T> 6K) Heat inleaks to 50-75 K (headers E and F) circuit within specification For sector 7-8 (sub-sectors A and B) heat inleaks to 4-20 K (headers B, C and D) above specification. Possible causes identified: »Higher thermal shield temperature than expected »Higher insulation vacuum than nominal »Not nominal insulation vacuum in the jumpers: impact on the heat flux through MLI For sector 8-1 heat inleaks to 4-20 K circuit are within specification »Important: Header B heat inleaks within the specification (QRL heat inleaks represents more than 95 % of the corresponding total budget) Other QRL sectors cold tested with the cryo-magnets: still possibility to measure the heat inleaks to the headers only (at present no allocated time for this test)


Download ppt "CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in."

Similar presentations


Ads by Google