1 Dynamo use cases on the New Rennes Subway Line

2 London General Contractor & Construction company 1400 employees 380 M€ Turnover Engineering Office: INGENOVA

3 Rennes Subway line B

4 Project location LEGENDRE SCOPE OF WORK

5 Stations & Maintenance hall

6 Classic use of Navisworks to get clashes Question: How to send clashes to contractors, knowing they only have Revit skill? Coordination Phase

7 Answer: Push clashes into Revit with Dynamo using Dynaworks package (Author: Adam Sheather) Coordination Phase

8 Next step: Openings Validation Coordination Phase

9 Openings Validation Create 3D Cropped Views for selected elements Setup Views accordingly Coordination Phase

10 Openings Validation Coordination Phase

11 Geometry Operation: Attach and Cut Host from Validated Openings Coordination Phase

12 Tagging…. Quality check Coordination Phase

13 Dynamo used as a Swiss Army knife Small tasks automation Filling Revit gaps Documentation Phase

14 One Dynamo definition Rule: Run before any documentation issue Wall thickness Floor thickness Top Bottom Elevation Tags Documentation Phase

15 PreConstruction Phase Specific Revit use Structural model as link Construction Site documentation Features involved: –Parts –Assemblies –IFC

16 PreConstruction Phase Families aware of their environment

17 PreConstruction Phase Families aware of their environment

18 PreConstruction Phase Assemblies for Equipment Documentation

19 PreConstruction Phase Assemblies for Equipment Documentation

20 Dealing with Parts coming from IFCs PreConstruction Phase

21 Dealing with Parts coming from IFCs PreConstruction Phase

22 Dealing with Parts coming from IFCs PreConstruction Phase

23 THANK @jbenoit44 julien.benoit@groupe-legendre.com YOU