U.S. ATLAS Facility Planning U.S. ATLAS Tier-2 & Tier-3 Meeting at SLAC 30 November 2007
2
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 2 Planning ahead … Scope: ~6 months Milestones and Items on the following slides are guided by Production and Analysis needs U.S. ATLAS Computing Integration Program will translate them into the technical steps sites have to perform
3
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 3 Analysis Analysis at Tier-2s q Implement analysis queues at all 5 Tier 2's o Complete by 15 December q Replicate all R13 AOD's (and some selected R12 AOD's) to all Tier 2's o How much space is needed at each Tier-2 o Who makes decision on datasets? o Who makes subscriptions and runs DDM operations? o Complete by 31 December Demonstrate automatic redirection of analysis jobs to all Tier 2's by pathena 15 January
4
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 4 Analysis Interactive Analysis q BNL PROOF farm available to all US ATLAS users for testing o Complete 31 January q BNL PROOF farm in production mode o Complete 31 March q Tier 2 PROOF farms available o Complete 30 June o Does this fit our model (User account management etc.)? q Support Tier-3 activities as part of the Computing Integration Meeting o Immediately, ongoing
5
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 5 Storage Services At Tier-1 q Evaluate Pinning with SRM v2.2 o Complete by 21 December q Propose data placement plan for data at Tier 1, including pinning, disk only partitions etc o Complete by 31 December q Develop and deploy software necessary to mange pinned files o Complete 15 January q Disk space reconfiguration according to computing model o Complete 31 January Develop and deploy disk-only dCache space management tools o Complete 21 December q User space management at Tier 1, including user management, cache cleanup o Proposal: Complete 31 December o Deployment: 31 January q LFC o Test system deployed: Complete 31 December o Test system production ready: 31 January o Migration to LFC completed for US, assuming successful tests: 28 February
6
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 6 U.S ATLAS Data Data Management q Deploy storage quota system US ATLAS wide o Complete by 28 February q DQ2 data deletion fully operational o Complete by 15 December q Complete DQ2 lost file tagging for US o Complete 15 January What is data flow model in Pathena? What if researcher produces data at Tier3? How is the decision to archive made? Are Tier2’s expected to maintain precious data indefinitely? User Data Lifetime? Consistency Checks?
7
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 7 Operations & Performance Incident tracking / Communication q Elog deployed & operational o Complete 15 December Performance q Demonstrate 2007 WLCG pledge with 90% average efficiency o Complete 31 December q Demonstrate 90% 2008 WLCG pledge o Complete 30 June o Contingent to funding situation
8
28 November 2007 M. Ernst Tier-2/3 Meeting at SLAC 8 Next Meeting Jointly with OSG All-Hands Meeting at RENCI (Chapel Hill, North Carolina) 3 - 5 March 2008