Gettering and Outgassing
System Requirements Gettering Technology Design layout Test setup Status Future Work
3
Situation What are the requirements for the vacuum Pressure for MCP
Pressure for Photocathode CsI and CsTe Pressure limits For cesiated GaN cathodes degradation occurs above 10-7 torr Pressures at 10-9 torr show no degradation of QE CsI is hygroscopic Bialkali is sensitive to hydrogen and oxygen How long does it need to be functional Current goal is ten years
4
Gettering How does it work? Chemisorption of active gases
O2, H2, CO2, H2O, and CO are active gases Ar, He, & other inert gases cannot be sorbed Two main types of getters Flash getters - Ba, Ca, Sr, Ti Non-evaporable getters – Zr, Th, Ti Flash getters are heated and evaporated onto the walls of the vacuum vessel. These have a long history in the CRT and picture tube industries. Non-evaporable getters These come in a variety of shapes but the most prominent are pills and strips In both cases the getter material is milled to small particles to maximize their surface area. The particles are either sintered into pills or pressed into a metal strip Gettering takes place on the clean surface where active chemical sites are available to form a strong bond with the gas within the photo-detector From Saes Getter Literature
5
Gettering Operational considerations
Need to heat it to activate the getter material Activation in an atmosphere of vacuum or inert gas Heated to 350 to 450 degree C for 10 minutes During activation weakly sorbed gases are exhausted into the vacuum system. While getters are more efficient at elevated temperatures they are used in numerous room temperature applications From Saes Getter Literature
6
Gettering Pumping Hydrogen Pumped on the surface of the getter
Active gases: CO, O2, CO2, H2O Pumped by diffusion into the bulk Inert gases Not pumped at all 10 m From Saes Getter Literature
7
Gettering From Saes Getter Literature Capacity Capacity will be based on the pressure, gas load of the active gases, exposure time, and the total functional area of the getter Hydrogen presents a different situation, since it is pumped on the surface and by diffusion into the bulk it has a limitation where the getter become embrittled and ceases to pump. From Saes Getter Literature
8
Gettering Materials Example: Alloy of ST707 is made up of: 70% Zr, 25% V, and 5% Fe From Saes Getter Literature
9
Materials From Saes Getter Literature
10
Design Layout- Mechanical Design and Space Allocations
Plan is to attach the getter strips to the side walls of the housing Getter will be activated during baking of the house assembly Once the seal in made the getter will provide the pumping for the photo-detector The getter will only be able to be reactivated if it is re-processed through the exhausting station and the active layer of the photo-cathode may need to be re-coated. Getter attached to side wall
11
“A User’s Guide to Vacuum Technology, Second Edition”
Outgassing Sources of gas within a vacuum system Gas interaction with solids Diffusion Permeation Vaporization Desorption Thermal Electron stimulated desorption Ion stimulated desorption Photon stimulated desorption Leaks Real Virtual or internal Backstreaming Related to diffusion and mechanical pumps “A User’s Guide to Vacuum Technology, Second Edition” J. O’Hanlon, 1989, pg. 57
12
“A User’s Guide to Vacuum Technology, Second Edition”
Outgassing In addition to the various sources of outgassing there is a different time factor associated with these sources. “A User’s Guide to Vacuum Technology, Second Edition” J. O’Hanlon, 1989, pg. 131
13
QSample=C(PA-PB)-QSystem
Outgassing System Schematic Cross Calibrated gauges 100 AMU QMA with EM QSample=C(PA-PB)-QSystem The orifice has been calibrated to a flow meter using a single species of gas
14
Test Setup Pictures Vacuum Pump Vacuum Gauge
15
System Under Bake Residual Gas Analyzer Vacuum Gauge Vacuum Pump
16
Status Status First bakeout was halted after 5 days due to limitations of temperature. Max Temperature 275 C After cool down the base pressure was high, 1 x 10-7 Torr. Orientation of components with insufficient heat lead to cold spots that limited base pressure. Small leak found in system. Heating issues resolved and the system is able to reach 400 C Pressures are improving with the reorientation of the valves and the heater tapes. Both helium leak detection and the RGA have shown the system to be free of leaks. Plan Outgassing system continues bake
17
Future Activities Going Forward
By measuring the outgassing rate and identifying the species of the residual gas evolving from the parts will aid in the estimation of the gas load that the getters will pump. Will be able to experiment with different temperatures to determine the best bake out temperature. Will be able to perform trials on some of the proposed processes. Like Indium sealing and examples of glass frit joints. A note of appreciation to Bob Garcia from Saes Getters for his assistance on this talk.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.